HomeMy WebLinkAbout20260098 56 Duplainville Rd Regeneron Sketch Plan Regeneron Supplemental SubmissionC.T. MALE ASSOCIATES
Engineering, Surveying, Architecture, Landscape Architecture & Geology, D.P.C.
50 Century Hill Drive, Latham, NY 12110
518.786.7400 FAX 518.786.7299 www.ctmale.com
Civil Engineering • Environmental Services • Survey Services • Land Services • Architecture •
Energy & Building Systems Services • Electrical Engineering
May 18, 2026 VIA EMAIL & HAND DELIVERY
Susan Barden, Administrator of OPED
City of Saratoga Springs
City Hall
474 Broadway
Saratoga Springs, New York 12866
Re: Regeneron Saratoga Project
Supplemental Submission
56 Duplainville Road
City of Saratoga Springs, Saratoga County, NY
C.T. Male Project No. 25.0998
Dear Susan:
C.T. Male Associates Engineering, Surveying, Architecture, Landscape Architecture &
Geology, D.P.C. (C.T. Male), on behalf of Regeneron Pharmaceuticals, Inc. (Regeneron or
Applicant), is providing this submission to supplement the sketch plan/SEQRA
application currently under review by the Planning Board, based on discussion at the
May 14, 2026 workshop meeting. The following attachments are provided, with a brief
explanation of each item below:
List of Attachments
Updated Part 1 Full EAF (Clean Version) Attachment 1
Updated Part 1 Full EAF (Redlined Version) Attachment 2
Updated Site Master Plan (V4) Attachment 3
Updated Part 1 Full Environmental Assessment Form (EAF) – An updated full EAF is
provided to document for the SEQR record updates made to the project since the first
submission on February 3, 2026. For your convenience, we are also providing a redlined
version so that the Planning Board can see where updates were made.
Updated Site Master Plan (V4) – The following Master Plan updates are provided to
align with the Full EAF and current development metrics:
- Adjusted the proposed limit of disturbance line around the proposed process
water tanks and access to the north.
- Removed the outdated line work and callout that states “Future City Domestic”
on the north side of the site, since Regeneron will purchase water from the
C.T. MALE ASSOCIATES
May 18, 2026
Supplemental Submission
Regeneron Saratoga Project
Page - 2
Saratoga County Water Authority and will be supplied by a proposed 20-inch
main as shown on the master plan.
- Re-balanced the site statistics table on the Overall Zoning Review sheet, to
account for 0.8± acres of proposed new impervious surface associated with
redevelopment activities. The slight increase in total impervious area is due to
the proposed process water tanks.
Tree Replacement – Regeneron commits to replacing significant trees that will be
removed from the site, mostly in the western parking lot area, in accordance with the
City standards for tree replacement. Landscaping plans and tree replacement metrics
will be presented on future site plan applications.
City Water Supply – Regeneron proposes to connect to the Saratoga County Water
Authority system and will construct two storage tanks on site for operational and
redundancy needs. This application does not include requesting additional water
supply from the City of Saratoga Springs for planned phases of development. If in the
future, through the due course of water system upgrades that the City may undergo,
there is a change in the City’s water supply that would allow Regeneron to be partially
supplied as an emergency backup source, Regeneron would work with the Department
of Public Works (DPW) at that time.
Respectfully Submitted,
C.T. MALE ASSOCIATES
Engineering, Surveying, Architecture, Landscape Architecture & Geology, D.P.C.
Chris Koenig
Project Manager
Environmental Services
Cc: Mark Pingel (Planning Board Chairman)
Regeneron Pharmaceuticals, Inc. (Applicant)
Bruce Steves, Esq. (Applicant’s Counsel)