LABOR AND MATERIAL
ITEM
UNIT
QUANTITY
UNIT COST
SUBTOTAL
8' WIDE PATH EXTENSION
Site Prep & Earthwork
SELECTIVE BRUSH CLEARING (BRUSH SAW)
ACRE
0.15
$
2,350.00
$
353
SELECTIVE TREE CLEARING (CHAINSAWS)
EA
30
$
300.00
$
9,000
STRIP & STOCKPILE 4" TOPSOIL
SY
440
$
3.80
$
1,672
Trail Construction
WOVEN TEXTILE
SY
440
$
1.50
$
660
4" BARK MULCH (HAND SPREAD)
SY
440
$
10.00
$
4,400
SIGNAGE
EA
1
$
200.00
$
200
Erosion Control
SILT FENCE
LF
225
$
1.50
$
338
SUBTOTAL
$
16,622
Miscellaneous
3% Mobilization & Setup
3%
$
16,622.00
$
499
10%Contingency
10%
$
16,622.00
1$
1,662
CONSTRUCTION SUBTOTAL
$
18,783
5% Engineering, Legal, & Admin Fees
LS
5%
$
18,782.86
$
1
939
TOTAL
$
19,722
Item costs were determined by referencing the "RS Means Site Work and Landscape Cost Data",
"RS Means Heavy Construction Cost Data", the New York State Department of Transportation weighted
average bid prive program, as well as similar projects and professional experience.