HomeMy WebLinkAbout20240551 453-457 Broadway Site Plan SEQRAFull Environmental Assessment Form
Part I - Project and Setting
Instructions for Completing Part 1
Part I is to be completed by the applicant or project sponsor. Responses become part of the application for approval or funding,
are subject to public review, and may be subject to further verification.
Complete Part 1 based on information currently available. If additional research or investigation would be needed to fully respond to
any item, please answer as thoroughly as possible based on current information; indicate whether missing information does not exist,
or is not reasonably available to the sponsor; and, when possible, generally describe work or studies which would be necessary to
update or fully develop that information.
Applicants/sponsors must complete all items in Sections A & B. In Sections C, D & E, most items contain an initial question that
must be answered either "Yes" or "No". If the answer to the initial question is "Yes", complete the sub -questions that follow. If the
answer to the initial question is "No", proceed to the next question. Section F allows the project sponsor to identify and attach any
additional information. Section G requires the name and signature of the applicant or project sponsor to verify that the information
contained in Part 1 is accurate and complete.
A. Project and Applicant/Sponsor Information.
Name of Action or Project:
Broadway, Saratoga Springs
Project Location (describe, and attach a general location map):
453-457 Broadway, Saratoga Springs NY
Brief Description of Proposed Action (include purpose or need):
The proposed project is proposed to redevelop an existing commercial and residential space into an additional 15 apartments while keeping the
commercial space on the ground level. The second and third level will each have 5 new apartments joining the 2 existing on each floor. The fourth level will
have 5 new apartments. The ground level will now have additional parking in the back of the building
and will have an elevator that goes up to the fourth
floor. As well as stairwells, and hallway circulation space. Site improvements will include 8 parking spaces, a courtyard and a new parking lot.
Name of Applicant/Sponsor:
Telephone: 585.225.0140
Bob DeWeese
E-Mail: spoton.cm22@gmail.com
Address: 550 Latona Rd. Bldg E, Suite 501
City/PO: Rochester
State: NY
Zip Code: 14626
Project Contact (if not same as sponsor; give name and title/role):
Telephone: 315.422.0201
Christopher Burdick
E-Mail: cburdick@dalpos.com
Address:
1001 N Clinton St Suite 300
City/PO:
State:
Zip Code:
Syracuse
NY
13202
Property Owner (if not same as sponsor):
Telephone: 585.225.0140
Angelo Ingrassia
E-Mail: autoange@aol.com
Address:
550 Latona Rd. Bldg E, Suite 501
City/PO: Rochester
State: NY
Zip Code:14626
Page 1 of 13
B. Government Approvals
B. Government Approvals, Funding, or Sponsorship. ("Funding" includes grants, loans, tax relief, and any other forms of financial
assistance.)
Government Entity
If Yes: Identify Agency and Approval(s)
Application Date
Required
(Actual or projected)
a. City Counsel, Town Board, ®YesONo
City Counsel
9/21/2023
or Village Board of Trustees
b. City, Town or Village ®YesMNo
DRB/Planning
4/5/2023
Planning Board or Commission
c. City, Town or MYes®No
Village Zoning Board of Appeals
d. Other local agencies DYes®No
e. County agencies DYes®No
f. Regional agencies DYes®No
g. State agencies DYes®No
h. Federal agencies DYes®No
i. Coastal Resources.
i. Is the project site within a Coastal Area, or the waterfront area of a Designated Inland Waterway? ❑Yes ®No
ii. Is the project site located in a community with an approved Local Waterfront Revitalization Program? ❑ Yes®No
iii. Is the project site within a Coastal Erosion Hazard Area? ❑ Yes®No
C. Planning and Zoning
C.1. Planning and zoning actions.
Will administrative or legislative adoption, or amendment of a plan, local law, ordinance, rule or regulation be the
only approval(s) which must be granted to enable the proposed action to proceed?
• If Yes, complete sections C, F and G.
• If No, proceed to question C.2 and complete all remaining sections and questions in Part 1
❑Yes®No
C.2. Adopted land use plans.
a. Do any municipally- adopted (city, town, village or county) comprehensive land use plan(s) include the site
where the proposed action would be located?
If Yes, does the comprehensive plan include specific recommendations for the site where the proposed action
would be located?
❑Yes®No
❑Yes®No
b. Is the site of the proposed action within any local or regional special planning district (for example: Greenway;
Brownfield Opportunity Area (BOA); designated State or Federal heritage area; watershed management plan;
or other?)
If Yes, identify the plan(s):
NYS Heritage Areas:Mohawk Valley Heritage Corridor, NYS Heritage Areas:Saratoga
®Yes❑No
c. Is the proposed action located wholly or partially within an area listed in an adopted municipal open space plan,
or an adopted municipal farmland protection plan?
If Yes, identify the plan(s):
❑Yes®No
Page 2 of 13
C.3. Zoning
a. Is the site of the proposed action located in a municipality with an adopted zoning law or ordinance. ®YesE1No
If Yes, what is the zoning classification(s) including any applicable overlay district?
T-6 Mixed Use
b. Is the use permitted or allowed by a special or conditional use permit? ❑ Yes®No
c. Is a zoning change requested as part of the proposed action? ❑Yes®No
If Yes,
i. What is the proposed new zoning for the site?
CA. Existing community services.
a. In what school district is the project site located? Saratoga Springs City School District
b. What police or other public protection forces serve the project site?
Saratoga Springs Police Department
c. Which fire protection and emergency medical services serve the project site?
Saratoga Springs Fire Department
d. What parks serve the project site?
D. Project Details
D.I. Proposed and Potential Development
a. What is the general nature of the proposed action (e.g., residential, industrial, commercial, recreational; if mixed, include all
components)? Residential, commercial
b. a. Total acreage of the site of the proposed action? .286 acres
b. Total acreage to be physically disturbed? .0839 acres
c. Total acreage (project site and any contiguous properties) owned
or controlled by the applicant or project sponsor? .4025 acres
c. Is the proposed action an expansion of an existing project or use? ® YesE]No
i. If Yes, what is the approximate percentage of the proposed expansion and identify the units (e.g., acres, miles, housing units,
square feet)? % additional 17,535 sq Units: 15 apartments
d. Is the proposed action a subdivision, or does it include a subdivision? ❑Yes ®No
If Yes,
i. Purpose or type of subdivision? (e.g., residential, industrial, commercial; if mixed, specify types)
ii. Is a cluster/conservation layout proposed? ❑Yes ONo
iii. Number of lots proposed?
iv. Minimum and maximum proposed lot sizes? Minimum Maximum
e. Will the proposed action be constructed in multiple phases? ❑ Yes®No
i. If No, anticipated period of construction: months
ii. If Yes:
• Total number of phases anticipated
• Anticipated commencement date of phase 1 (including demolition) month year
• Anticipated completion date of final phase month year
• Generally describe connections or relationships among phases, including any contingencies where progress of one phase may
determine timing or duration of future phases:
Page 3 of 13
f. Does the project include new residential uses? ®YesF�No
If Yes, show numbers of units proposed.
One Family Two Family Three Family Multiple Family four or more
Initial Phase
At completion
of all phases 15
g. Does the proposed action include new non-residential construction (including expansions)? ❑Yes®No
If Yes,
i. Total number of structures 1
ii. Dimensions (in feet) of largest proposed structure: height; width; and length
iii. Approximate extent of building space to be heated or cooled: square feet
h. Does the proposed action include construction or other activities that will result in the impoundment of any ❑Yes®No
liquids, such as creation of a water supply, reservoir, pond, lake, waste lagoon or other storage?
If Yes,
i. Purpose of the impoundment:
ii. If a water impoundment, the principal source of the water: ❑ Ground water ❑ Surface water streams ❑Other specify:
iii. If other than water, identify the type of impounded/contained liquids and their source.
iv. Approximate size of the proposed impoundment. Volume: million gallons; surface area: acres
v. Dimensions of the proposed dam or impounding structure: height; length
vi. Construction method/materials for the proposed dam or impounding structure (e.g., earth fill, rock, wood, concrete):
D.2. Project Operations
a. Does the proposed action include any excavation, mining, or dredging, during construction, operations, or both? Yes®No
(Not including general site preparation, grading or installation of utilities or foundations where all excavated
materials will remain onsite)
If Yes:
i What is the purpose of the excavation or dredging?
ii. How much material (including rock, earth, sediments, etc.) is proposed to be removed from the site?
• Volume (specify tons or cubic yards):
• Over what duration of time?
iii. Describe nature and characteristics of materials to be excavated or dredged, and plans to use, manage or dispose of them.
iv. Will there be onsite dewatering or processing of excavated materials? RYesFJNo
If yes, describe.
v. What is the total area to be dredged or excavated? acres
vi. What is the maximum area to be worked at any one time? acres
vii. What would be the maximum depth of excavation or dredging? feet
viii. Will the excavation require blasting? QYesnNo
ix. Summarize site reclamation goals and plan:
b. Would the proposed action cause or result in alteration of, increase or decrease in size of, or encroachment Yes®No
into any existing wetland, waterbody, shoreline, beach or adjacent area?
If Yes:
i. Identify the wetland or waterbody which would be affected (by name, water index number, wetland map number or geographic
description):
Page 4 of 13
ii. Describe how the proposed action would affect that waterbody or wetland, e.g. excavation, fill, placement of structures, or
alteration of channels, banks and shorelines. Indicate extent of activities, alterations and additions in square feet or acres:
iii. Will the proposed action cause or result in disturbance to bottom sediments?
❑Yes ONo
If Yes, describe:
iv. Will the proposed action cause or result in the destruction or removal of aquatic vegetation?
❑ YesMNo
If Yes:
• acres of aquatic vegetation proposed to be removed:
• expected acreage of aquatic vegetation remaining after project completion:
• purpose of proposed removal (e.g. beach clearing, invasive species control, boat access):
• proposed method of plant removal:
• if chemical/herbicide treatment will be used, specify product(s):
v. Describe any proposed reclamation/mitigation following disturbance:
c. Will the proposed action use, or create a new demand for water?
®Yes E]No
If Yes:
i. Total anticipated water usage/demand per day: 3,300 gallons/day
ii. Will the proposed action obtain water from an existing public water supply?
®Yes []No
If Yes:
• Name of district or service area: City of Saratoga
• Does the existing public water supply have capacity to serve the proposal?
® Yes❑ No
• Is the project site in the existing district?
® Yes❑ No
• Is expansion of the district needed?
❑ Yes® No
• Do existing lines serve the project site?
® YesM No
iii. Will line extension within an existing district be necessary to supply the project?
❑Yes OTo
If Yes:
• Describe extensions or capacity expansions proposed to serve this project:
• Source(s) of supply for the district:
iv. Is a new water supply district or service area proposed to be formed to serve the project site?
❑ Yes®No
If, Yes:
• Applicant/sponsor for new district:
• Date application submitted or anticipated:
• Proposed source(s) of supply for new district:
v. If a public water supply will not be used, describe plans to provide water supply for the project:
vi. If water supply will be from wells (public or private), what is the maximum pumping capacity:
gallons/minute.
d. Will the proposed action generate liquid wastes?
® Yes E]No
If Yes:
i. Total anticipated liquid waste generation per day: 3300 gallons/day
ii. Nature of liquid wastes to be generated (e.g., sanitary wastewater, industrial, if combination, describe all components and
approximate volumes or proportions of each):
Sanitary Wastewater
iii. Will the proposed action use any existing public wastewater treatment facilities?
®YesE]No
If Yes:
• Name of wastewater treatment plant to be used:
• Name of district:
• Does the existing wastewater treatment plant have capacity to serve the project?
®YesQNo
• Is the project site in the existing district?
®YesQNo
• Is expansion of the district needed?
❑Yes ®No
Page 5 of 13
• Do existing sewer lines serve the project site?
®Yes❑No
• Will a line extension within an existing district be necessary to serve the project?
❑Yes®No
If Yes:
• Describe extensions or capacity expansions proposed to serve this project:
iv. Will a new wastewater (sewage) treatment district be formed to serve the project site?
❑Yes®No
If Yes:
• Applicant/sponsor for new district:
• Date application submitted or anticipated:
• What is the receiving water for the wastewater discharge?
v. If public facilities will not be used, describe plans to provide wastewater treatment for the project, including specifying
proposed
receiving water (name and classification if surface discharge or describe subsurface disposal plans):
vi. Describe any plans or designs to capture, recycle or reuse liquid waste:
e. Will the proposed action disturb more than one acre and create stormwater runoff, either from new point
❑Yes ®No
sources (i.e. ditches, pipes, swales, curbs, gutters or other concentrated flows of stormwater) or non -point
source (i.e. sheet flow) during construction or post construction?
If Yes:
i. How much impervious surface will the project create in relation to total size of project parcel?
Square feet or acres (impervious surface)
Square feet or acres (parcel size)
ii. Describe types of new point sources.
iii. Where will the stormwater runoff be directed (i.e. on -site stormwater management facility/structures, adjacent properties,
groundwater, on -site surface water or off -site surface waters)?
• If to surface waters, identify receiving water bodies or wetlands:
• Will stormwater runoff flow to adjacent properties?
iv. Does the proposed plan minimize impervious surfaces, use pervious materials or collect and re -use stormwater?
❑Yes❑No
❑Yes❑No
f. Does the proposed action include, or will it use on -site, one or more sources of air emissions, including fuel
❑Yes ®No
combustion, waste incineration, or other processes or operations?
If Yes, identify:
i. Mobile sources during project operations (e.g., heavy equipment, fleet or delivery vehicles)
ii. Stationary sources during construction (e.g., power generation, structural heating, batch plant, crushers)
iii. Stationary sources during operations (e.g., process emissions, large boilers, electric generation)
g. Will any air emission sources named in D.2.f (above), require a NY State Air Registration, Air Facility Permit,
❑Yes ®No
or Federal Clean Air Act Title IV or Title V Permit?
If Yes:
i. Is the project site located in an Air quality non -attainment area? (Area routinely or periodically fails to meet
ambient air quality standards for all or some parts of the year)
❑Yes®No
ii. In addition to emissions as calculated in the application, the project will generate:
• Tons/year (short tons) of Carbon Dioxide (CO2)
• Tons/year (short tons) of Nitrous Oxide (N20)
• Tons/year (short tons) of Perfluorocarbons (PFCs)
• Tons/year (short tons) of Sulfur Hexafluoride (SF6)
• Tons/year (short tons) of Carbon Dioxide equivalent of Hydroflourocarbons (HFCs)
• Tons/year (short tons) of Hazardous Air Pollutants (HAPs)
Page 6 of 13
h. Will the proposed action generate or emit methane (including, but not limited to, sewage treatment plants,
❑Yes®No
landfills, composting facilities)?
If Yes:
i. Estimate methane generation in tons/year (metric):
ii. Describe any methane capture, control or elimination measures included in project design (e.g., combustion to generate heat or
electricity, flaring):
i. Will the proposed action result in the release of air pollutants from open-air operations or processes, such as
❑Yes®No
quarry or landfill operations?
If Yes: Describe operations and nature of emissions (e.g., diesel exhaust, rock particulates/dust):
j. Will the proposed action result in a substantial increase in traffic above present levels or generate substantial
❑YesPINo
new demand for transportation facilities or services?
If Yes:
i. When is the peak traffic expected (Check all that apply): ❑ Morning ❑ Evening ❑Weekend
❑ Randomly between hours of to
ii. For commercial activities only, projected number of truck trips/day and type (e.g., semi trailers and dump trucks):
iii. Parking spaces: Existing Proposed Net increase/decrease
iv. Does the proposed action include any shared use parking?
RYes ONo
v. If the proposed action includes any modification of existing roads, creation of new roads or change in existing
access, describe:
vi. Are public/private transportation service(s) or facilities available within '/z mile of the proposed site?
vii Will the proposed action include access to public transportation or accommodations for use of hybrid, electric
nYesj;�No
nYesPINo
or other alternative fueled vehicles?
viii. Will the proposed action include plans for pedestrian or bicycle accommodations for connections to existing
❑Yes®No
pedestrian or bicycle routes?
k. Will the proposed action (for commercial or industrial projects only) generate new or additional demand
❑Yes®No
for energy?
If Yes:
i. Estimate annual electricity demand during operation of the proposed action:
ii. Anticipated sources/suppliers of electricity for the project (e.g., on -site combustion, on -site renewable, via grid/local
utility, or
other):
iii. Will the proposed action require a new, or an upgrade, to an existing substation?
❑YesPlNo
1. Hours of operation. Answer all items which apply.
i. During Construction: ii. During Operations:
• Monday - Friday: • Monday - Friday: 24hrs
• Saturday: 0 Saturday: 24hrs
• Sunday: • Sunday: 24hrs
• Holidays: • Holidays: 24hrs
Page 7 of 13
in. Will the proposed action produce noise that will exceed existing ambient noise levels during construction,
operation, or both?
If yes:
i. Provide details including sources, time of day and duration:
Construction related machinery only during construction
0 Yes ❑No
ii. Will the proposed action remove existing natural barriers that could act as a noise barrier or screen?
Describe:
❑ Yes ®No
n. Will the proposed action have outdoor lighting?
If yes:
i. Describe source(s), location(s), height of fixture(s), direction/aim, and proximity to nearest occupied structures:
Wall packs, pole mounted lighting and flag pole lighting will be dark sky compliant
0 Yes ❑No
ii. Will proposed action remove existing natural barriers that could act as a light barrier or screen?
Describe:
❑ Yes 0No
o. Does the proposed action have the potential to produce odors for more than one hour per day?
If Yes, describe possible sources, potential frequency and duration of odor emissions, and proximity to nearest
occupied structures:
❑ Yes 0No
p. Will the proposed action include any bulk storage of petroleum (combined capacity of over 1,100 gallons)
or chemical products 185 gallons in above ground storage or any amount in underground storage?
If Yes:
i. Product(s) to be stored
ii. Volume(s) per unit time (e.g., month, year)
iii. Generally, describe the proposed storage facilities:
❑ Yes 0No
q. Will the proposed action (commercial, industrial and recreational projects only) use pesticides (i.e., herbicides,
insecticides) during construction or operation?
If Yes:
i. Describe proposed treatment(s):
❑ Yes ®No
ii. Will the proposed action use Integrated Pest Management Practices?
❑ Yes [-]No
r. Will the proposed action (commercial or industrial projects only) involve or require the management or disposal
of solid waste (excluding hazardous materials)?
If Yes:
i. Describe any solid waste(s) to be generated during construction or operation of the facility:
• Construction: tons per month (unit of time)
• Operation : tons per year (unit of time)
ii. Describe any proposals for on -site minimization, recycling or reuse of materials to avoid disposal as solid waste:
• Construction:
0 Yes ❑No
• Operation:
iii. Proposed disposal methods/facilities for solid waste generated on -site:
• Construction: Waste removal to landfill by rubbish collector
• Operation: Local rubbish carrier
Page 8of13
s. Does the proposed action include construction or modification of a solid waste management facility? ❑ Yes ❑ No
If Yes:
i. Type of management or handling of waste proposed for the site (e.g., recycling or transfer station, composting, landfill, or
other disposal activities):
H. Anticipated rate of disposal/processing:
• Tons/month, if transfer or other non-combustion/thermal treatment, or
• Tons/hour, if combustion or thermal treatment
iii. If landfill, anticipated site life: years
t. Will the proposed action at the site involve the commercial generation, treatment, storage, or disposal of hazardous ❑Yes❑No
waste?
If Yes:
i. Name(s) of all hazardous wastes or constituents to be generated, handled or managed at facility:
ii. Generally describe processes or activities involving hazardous wastes or constituents:
iii. Specify amount to be handled or generated tons/month
iv. Describe any proposals for on -site minimization, recycling or reuse of hazardous constituents:
v. Will any hazardous wastes be disposed at an existing offsite hazardous waste facility? Yes No
If Yes: provide name and location of facility:
If No: describe proposed management of any hazardous wastes which will not be sent to a hazardous waste facility:
E. Site and Setting of Proposed Action
E.I. Land uses on and surrounding the project site
a. Existing land uses.
i. Check all uses that occur on, adjoining and near the project site.
❑ Urban ❑ Industrial ❑ Commercial ® Residential (suburban) ❑ Rural (non -farm)
❑ Forest ❑ Agriculture ❑ Aquatic ❑ Other (specify):
ii. If mix of uses, generally describe:
b. Land uses and covertypes on the project site.
Land use or
Covertype
Current
Acreage
Acreage After
Project Completion
Change
(Acres +/-)
• Roads, buildings, and other paved or impervious
surfaces
.4025
.4025
0
• Forested
• Meadows, grasslands or brushlands (non-
agricultural, including abandoned agricultural)
• Agricultural
(includes active orchards, field, greenhouse etc.)
• Surface water features
(lakes, ponds, streams, rivers, etc.)
• Wetlands (freshwater or tidal)
• Non -vegetated (bare rock, earth or fill)
• Other
Describe:
Page 9 of 13
c. Is the project site presently used by members of the community for public recreation?
❑YesE]No
i. If Yes: explain:
d. Are there any facilities serving children, the elderly, people with disabilities (e.g., schools, hospitals, licensed
❑YesPINo
day care centers, or group homes) within 1500 feet of the project site?
If Yes,
i. Identify Facilities:
e. Does the project site contain an existing dam?
❑Yes®No
If Yes:
i. Dimensions of the dam and impoundment:
• Dam height: feet
• Dam length: feet
• Surface area: acres
* Volume impounded: gallons OR acre-feet
ii. Dam's existing hazard classification:
W. Provide date and summarize results of last inspection:
f. Has the project site ever been used as a municipal, commercial or industrial solid waste management facility,
❑Yes❑No
or does the project site adjoin property which is now, or was at one time, used as a solid waste management facility?
If Yes:
i. Has the facility been formally closed?
❑ Yes❑ No
• If yes, cite sources/documentation:
ii. Describe the location of the project site relative to the boundaries of the solid waste management facility:
iii. Describe any development constraints due to the prior solid waste activities:
g. Have hazardous wastes been generated, treated and/or disposed of at the site, or does the project site adjoin
❑Yes®No
property which is now or was at one time used to commercially treat, store and/or dispose of hazardous waste?
If Yes:
i. Describe waste(s) handled and waste management activities, including approximate time when activities occurred:
h. Potential contamination history. Has there been a reported spill at the proposed project site, or have any
❑ Yes® No
remedial actions been conducted at or adjacent to the proposed site?
If Yes:
i. Is any portion of the site listed on the NYSDEC Spills Incidents database or Environmental Site
❑ YesElNo
Remediation database? Check all that apply:
❑ Yes — Spills Incidents database Provide DEC ID number(s):
❑ Yes — Environmental Site Remediation database Provide DEC ID number(s):
❑ Neither database
ii. If site has been subject of RCRA corrective activities, describe control measures:
iii. Is the project within 2000 feet of any site in the NYSDEC Environmental Site Remediation database?
®Yes❑No
If yes, provide DEC ID number(s): V00475, C546057A
iv. If yes to (i), (ii) or (iii) above, describe current status of site(s):
Page 10 of 13
v. Is the project site subject to an institutional control limiting property uses?
❑ Yes®No
• If yes, DEC site ID number:
• Describe the type of institutional control (e.g., deed restriction or easement):
• Describe any use limitations:
• Describe any engineering controls:
• Will the project affect the institutional or engineering controls in place?
❑Yes®No
• Explain:
E.2. Natural Resources On or Near Project Site
a. What is the average depth to bedrock on the project site? 77" feet
b. Are there bedrock outcroppings on the project site?
❑ Yes ®No
If Yes, what proportion of the site is comprised of bedrock outcroppings? %
c. Predominant soil type(s) present on project site: Sandy Subgrades 100 %
d. What is the average depth to the water table on the project site? Average: feet
e. Drainage status of project site soils:® Well Drained: 100 % of site
❑ Moderately Well Drained: % of site
❑ Poorly Drained % of site
f. Approximate proportion of proposed action site with slopes: ® 0-10%: 98 % of site
® 10-15%: 2 % of site
❑ 15% or greater: % of site
g. Are there any unique geologic features on the project site?
❑Yes®No
If Yes, describe:
h. Surface water features.
i. Does any portion of the project site contain wetlands or other waterbodies (including streams, rivers,
❑Yes®No
ponds or lakes)?
ii. Do any wetlands or other waterbodies adjoin the project site?
❑Yes®No
If Yes to either i or ii, continue. If No, skip to E.2.1.
iii. Are any of the wetlands or waterbodies within or adjoining the project site regulated by any federal,
state or local agency?
❑YesZNo
iv. For each identified regulated wetland and waterbody on the project site, provide the following information:
• Streams: Name Classification
Lakes or Ponds: Name Classification
• Wetlands: Name Approximate Size
• Wetland No. (if regulated by DEC)
v. Are any of the above water bodies listed in the most recent compilation of NYS water quality -impaired
waterbodies?
❑Yes ONo
If yes, name of impaired water body/bodies and basis for Listing as impaired:
i. Is the project site in a designated Floodway?
[JYes ®No
i. Is the project site in the 100-year Floodplain?
❑Yesolo
k. Is the project site in the 500-year Floodplain?
❑Yes®No
1. Is the project site located over, or immediately adjoining, a primary, principal or sole source aquifer?
®YesE]No
If Yes:
i. Name of aquifer: Principal Aquifer
Page 11 of 13
in. Identify the predominant wildlife species that occupy or use the project site:
n. Does the project site contain a designated significant natural community?
❑Yes®No
If Yes:
i. Describe the habitat/community (composition, function, and basis for designation):
ii. Source(s) of description or evaluation:
W. Extent of community/habitat:
• Currently: acres
• Following completion of project as proposed: acres
• Gain or loss (indicate + or -): acres
o. Does project site contain any species of plant or animal that is listed by the federal government or NYS as
❑ Yes®No
endangered or threatened, or does it contain any areas identified as habitat for an endangered or threatened species?
If Yes:
i. Species and listing (endangered or threatened):
p. Does the project site contain any species of plant or animal that is listed by NYS as rare, or as a species of
❑Yes®No
special concern?
If Yes:
i. Species and listing:
q. Is the project site or adjoining area currently used for hunting, trapping, fishing or shell fishing?
❑Yes®No
If yes, give a brief description of how the proposed action may affect that use:
E.3. Designated Public Resources On or Near Project Site
a. Is the project site, or any portion of it, located in a designated agricultural district certified pursuant to
❑YesR]No
Agriculture and Markets Law, Article 25-AA, Section 303 and 304?
If Yes, provide county plus district name/number:
b. Are agricultural lands consisting of highly productive soils present?
❑Yes oNo
i. If Yes: acreage(s) on project site?
ii. Source(s) of soil rating(s):
c. Does the project site contain all or part of, or is it substantially contiguous to, a registered National
❑Yes®No
Natural Landmark?
If Yes:
i. Nature of the natural landmark: ❑ Biological Community ❑ Geological Feature
ii. Provide brief description of landmark, including values behind designation and approximate size/extent:
d. Is the project site located in or does it adjoin a state listed Critical Environmental Area?
❑Yes®No
If Yes:
i. CEA name:
ii. Basis for designation:
iii. Designating agency and date:
Page 12 of 13
e. Does the project site contain, or is it substantially contiguous to, a building, archaeological site, or district
® YesElNo
which is listed on the National or State Register of Historic Places, or that has been determined by the Commissioner of the NYS
Office of Parks, Recreation and Historic Preservation to be eligible for listing on the State Register of Historic Places?
If Yes:
i. Nature of historic/archaeological resource: ®Archaeological Site ®Historic Building or District
ii. Name: Broadway Historic District, West Side Historic District, US Post Office --Saratoga Springs, Broadway Historic District...
iii. Brief description of attributes on which listing is based:
f. Is the project site, or any portion of it, located in or adjacent to an area designated as sensitive for
® Yes F-lNo
archaeological sites on the NY State Historic Preservation Office (SHPO) archaeological site inventory?
g. Have additional archaeological or historic site(s) or resources been identified on the project site?
❑YesoNo
If Yes:
i. Describe possible resource(s):
ii. Basis for identification:
h. Is the project site within fives miles of any officially designated and publicly accessible federal, state, or local
❑Yes®No
scenic or aesthetic resource?
If Yes:
i. Identify resource:
ii. Nature of, or basis for, designation (e.g., established highway overlook, state or local park, state historic trail or
scenic byway,
etc.):
iii. Distance between project and resource: miles.
i. Is the project site located within a designated river corridor under the Wild, Scenic and Recreational Rivers
Program 6 NYCRR 666?
❑ YesPINo
If Yes:
i. Identify the name of the river and its designation:
ii. Is the activity consistent with development restrictions contained in 6NYCRR Part 666?
❑ Yes RNo
F. Additional Information
Attach any additional information which may be needed to clarify your project.
If you have identified any adverse impacts which could be associated with your proposal, please describe those impacts plus any
measures which you propose to avoid or minimize them.
G. Verification
I certify that the information provided is true to the best of my knowledge.
Applicant/Sponsor Name Bob DeWeese
Date 9/19/2023
Signature Title Construction Manager
I PRINT FORM I Page 13 of 13
EAF Mapper Summary Report
Wednesday, September 13, 2023 8:40
AM
-------__ 165:5 1-3,=9:1 j 1 l f? j 165'51 ;3-22
-- �' _165.51-V. 5!1 r
r 1165.51-3=26 ! ;' 165.51-3-23 ?
65.59-1-92, �'1fi55.1.-3-+12 ?
+ 165.59-1-i6165.59-1-22.21.65.59-1-T5
165.5 9 -1 ;2 3
Disclaimer: The EAF Mapper is a screening tool intended to assist
project sponsors and reviewing agencies in preparing an environmental
assessment form (EAF). Not all questions asked in the EAF are
165.52-4-38
answered by the EAF Mapper. Additional information on any EAF
question can be obtained by consulting the EAF Workbooks. Although
the EAF Mapper provides the most up-to-date digital data available to
DEC, you may also need to contact local or other data sources in order
165.5 2-4-37 to obtain data not provided by the Mapper. Digital data is not a
substitute for agency determinations.
165.5 9-1-26.11 � G
-165.59=1-93--._ = _ - -_
�1 f 165.59-1-80?-1?6�59-2=1 - ._.. u Barre Err:.,.i��
165.59-1'= f - _J ;r r---r-_ Kines'ton Monlp
65.59-1-17 ? 1 1-65.59-2-2;t 65.s0;1-,4
f Saf,
165.59__2_5 r
Totanto
f+f
`- _
--` 165..59-1=32
- 11165..59-2=7;'�-- -� -_
f - -- '-
--L-
Namilion
Rod,ester
165.59-1-18 1�65.59-1-22.1 165.59-1-33�
C65. 60-1;.$2
t65.60-1 83% i '
on Buffalo
' a many
-------- _ r
16 5.59 -3 -1.1. -6_-1-�
i 165 _6_0-1.2 j1
'65.5Ia9`
.
,,�....• ` r ..
;65.59-1-34?
15f`6Q—
165.59-1=35 1
161i�, E i HE E, Gatmir_ r3-1 E
-16
178
65.64rt
T&
Br,H
F=:i, Esn Esn Ct)ir•_,
'Sit E,•i�
I-r..-.=trre�trrnart1!
Eti G�i,tr,rr, miri?,etr:lyl, 4�:Pr
^�
K_r•L'
Chna Hcrlq Ko gIEsri Korf!,'1'i
r I -�ti' at_tibutor3_kq
,r:-Ir 'I1
aFrc�E.~i,FI
165.59_ =381_
�691
y-
165.59-3I
��65.60-168,
�t
r4'EF. '
7'
ESr HER:
_-"3'.y
B.i.i [Coastal or Waterfront Area] No
B.i.ii [Local Waterfront Revitalization Area] No
C.2.b. [Special Planning District] Yes - Digital mapping data are not available for all Special Planning Districts.
Refer to EAF Workbook.
C.2.b. [Special Planning District - Name] NYS Heritage Areas:Mohawk Valley Heritage Corridor, NYS Heritage
Areas:Saratoga
E.1.h [DEC Spills or Remediation Site - Digital mapping data are not available or are incomplete. Refer to EAF
Potential Contamination History] Workbook.
E.1.h.i [DEC Spills or Remediation Site - Digital mapping data are not available or are incomplete. Refer to EAF
Listed] Workbook.
E.1.h.i [DEC Spills or Remediation Site - Digital mapping data are not available or are incomplete. Refer to EAF
Environmental Site Remediation Database] Workbook.
E.1.h.iii [Within 2,000' of DEC Remediation Yes
Site]
E.1.h.iii [Within 2,000' of DEC Remediation V00475, C546057A
Site - DEC ID]
E.2.g [Unique Geologic Features]
No
E.2.h.i [Surface Water Features]
No
E.2.h.ii [Surface Water Features]
No
E.2.h.iii [Surface Water Features]
No
E.2.h.v [Impaired Water Bodies]
No
E.2.i. [Floodway]
Digital mapping data are not available or are incomplete. Refer to EAF
Workbook.
E.2 J. [100 Year Floodplain]
Digital mapping data are not available or are incomplete. Refer to EAF
Workbook.
E.2.k. [500 Year Floodplain]
Digital mapping data are not available or are incomplete. Refer to EAF
Workbook.
Full Environmental Assessment Form - EAF Mapper Summary Report
E.2.1. [Aquifers]
Yes
E.2.1. [Aquifer Names]
'Principal Aquifer
E.2.o. [Endangered or Threatened Species]
No
E.2.p. [Rare Plants or Animals]
No
E.3.a. [Agricultural District]
No
E.3.c. [National Natural Landmark]
No
FuUEnvironnnenta|AeseaamentFonn-EAFMopporSummaryReport 2