PROJECT NARRATIVE
District @ 120 Multifamily Residential Community Revised Site Plan
DATE: March 4, 2024
APPLICANT: Strategies, LLC Performing Assets
120 South Broadway
Saratoga Springs, NY
Please find attached a revised plan for 120 South Broadway. The applicant received approval for
buildings 1 and 2 (the back buildings) at the DRB earlier this month. The applicant wishes to
proceed with obtaining a modified site plan approval without building 5 (formerly the community
center).
The applicant has decided to remove the building 5 from the project and expand the civic space in
this area instead, which now includes fireplaces and pickleball courts. Although the plans are
modified from the original approval, the site layout and integral aspects of the project remain
unchanged, including saving the Rosemary Spring and Gazebo.
The major changes to the Site Plans are as follows:
1. There are now 74 units, 23 each in the back buildings and 14 each in the front 2 buildings.
2. Removal of the Community Center and expanded Civic Space as mentioned above.
3. Added interior garage parking in buildings 1 and 2 and access from the western side of the
building to the parking garage in both buildings.
4. Added interior tandem parking behind buildings 3 and 4.
5. Removal of one row of exterior parking along building 1 to better accommodate the building
placement.
6. An increase in the number of parking spaces because of the addition of interior parking, the
total is now 155 spaces. This includes 53 exterior and 102 interior.