STORMWATER
POLLUTION PREVENTION PLAN
THBC NY, LLC
Proposed Microproduction Brewery
3376 South Broadway
City of Saratoga Springs,
Saratoga County,
State of New York
December 4, 2023
Prepared by:
17 Computer Drive West, Albany, NY 12205
Phone: (518) 438-9900
Fax: (518) 438-0900
www.bohlereng.com
No. NYB230191.00
PROGRESS PRINTSTATE O F NEW Y
ORKVIS H A L R
A
I
104 6 4 1LICENSE
D PROFESS I O N A L ENGINEER
1 | P a g e
Table of Contents
I. INTRODUCTION .............................................................................................................................. 2
II. BACKGROUND INFORMATION ........................................................................................................ 2
A. EXISTING CONDITIONS ............................................................................................................................ 2
B. PROPOSED CONDITIONS ......................................................................................................................... 2
III. CONSTRUCTION DRAWINGS: .......................................................................................................... 3
IV. SOIL DESCRIPTION: ......................................................................................................................... 3
V. CONSTRUCTION PHASING: .............................................................................................................. 4
VI. POLLUTION PREVENTION MEASURES: ............................................................................................ 4
VII. SOIL STABILIZATION MEASURES: .................................................................................................... 4
VIII. EROSION AND SEDIMENT CONTROL PRACTICES:............................................................................. 4
IX. MAINTENANCE SCHEDULE: ............................................................................................................. 4
X. RECEIVING WATERS: ....................................................................................................................... 5
XI. SWPPP IMPLEMENTATION AND PERMIT COVERAGE TERMINATION: .............................................. 5
XII. STORMWATER RUN-OFF CHARACTERISTICS: ................................................................................... 6
XIII. ARCHEOLOGICAL SENSITIVE AREA: ................................................................................................. 6
XIV. CONSTRUCTION ACTIVITIES MEETING CONDITIONS IN TABLE 2 OF APPENDIX B ............................. 6
XV. SWPPP DEVELOPMENT – 6 STEP PROCESS: ..................................................................................... 7
1. SITE PLANNING – GREEN INFRASTRUCTURE: ............................................................................................... 7
2. DETERMINING WATER QUALITY VOLUME: ................................................................................................. 8
3. RUNOFF REDUCTION: ............................................................................................................................. 8
4. MINIMUM RRV: ................................................................................................................................... 8
5. APPLY SMP’S TO ADDRESS REMAINING WQV: ............................................................................................ 9
6. APPLY VOLUME AND PEAK RATE CONTROL PRACTICES: .................................................................................. 9
XVI. APPENDICES .................................................................................................................................. 10
A. NYSDEC SPDES GENERAL PERMIT FOR STORMWATER DISCHARGES FROM CONSTRUCTION ACTIVITY PERMIT NO.
GP-0-20-001 ............................................................................................................................................. 10
B. NYSDEC NOTICE OF INTENT (NOI) AND NOTICE OF TERMINATION FORMS ................................................... 10
C. STORMWATER GENERAL OPERATION AND MAINTENANCE PLAN, CONSTRUCTION / OPERATION AND MAINTENANCE /
INSPECTION REPORT FORMS, INSPECTOR CERTIFICATION FORM, INSPECTION LOG & CONSTRUCTION SITE INSPECTION AND
MAINTENANCE LOG BOOK ............................................................................................................................. 10
D. CONTRACTOR/OWNER CERT. FORMS, CONSTRUCTION ACTIVITY FORM ......................................................... 10
E. CULTURAL RESOURCE INFORMATION SYSTEM – ARCHEOLOGICAL MAP AND NYSOPRHP LETTER OF NO EFFECT .. 10
F. STORMWATER MANAGEMENT REPORT ................................................................................................... 10
G. CONSTRUCTION DRAWINGS & PHASING PLANS ......................................................................................... 10
2 | P a g e
I. Introduction
THBC NY, LLC. is proposing to develop a ±10.7-acre site within the City
of Saratoga Springs, Saratoga County, New York. The project site is located at
3376 US Route 9 (South Broadway), approximately ±1,300 feet south of the
intersection with Crescent Ave and is currently with ±10,420 sf of paved parking.
A new 2-story, ±22,778 sf microproduction brewery and three pavilions are
proposed along with new patio seating, parking facilities, utility connections,
stormwater management facilities, and other appurtenances as depicted on the
Proposed Site Plan Documents prepared by Bohler, dated November 30, 2023, no
revisions listed.
This report will address the required components for a Stormwater
Pollution Prevention Plan (SWPPP) as specified by the New York State
Department of Environmental Conservation SPDES General Permit for
Stormwater Discharges from Construction Activity Permit No. GP-0-20-001.
II. Background Information
a. Existing Conditions
The overall property is approximately ±10.7 acres and is currently
developed with ±10,420 sf of paved parking and is comprised primarily of brush
and vegetation. The site is located along US Route 9 (South Broadway) (Tax Map
178.00-2-15) in the City of Saratoga Springs. The site is surrounded by a car
dealership to the north, wooded area and a mental health facility to the east,
wooded area and a hotel to the south, and US Route 9 to the west. The site
generally slopes in a southeasterly direction from US Route 9 towards the existing
wetlands located along the easterly property boundary and eventually discharges
into the Kayaderosseras Creek tributary to Saratoga Lake. Existing drainage
patterns are expected to remain after the proposed development.
b. Proposed Conditions
A new microproduction brewery and three pavilions are proposed to be
constructed along with associated patio seating, parking areas, access drives,
utilities, stormwater management facilities, and other appurtenances. An entrance-
only ingress curb cut and an exit-only egress curb cut are proposed on US Route
9. The northernmost egress is proposed to be in the same location as the existing
curb cut. The southernmost ingress proposes to relocate the existing curb cut.
Stormwater is proposed to be collected and treated onsite. New
stormwater management facilities are proposed to mitigate impacts of this
development project. These facilities adhere to the latest NYSDEC manual for
quality and quantity treatment while maintaining existing tributary flow patterns.
3 | P a g e
The proposed project is further depicted on the accompanying Proposed Site Plan
Documents prepared by Bohler, dated November 30, 2023, no revisions listed.
The property owner will be responsible for all construction activities, post
construction operations and maintenance of the facility and all responsibilities
specified in the SWPPP.
III. Construction Drawings:
Included in this report are the following drawings:
Site Survey – Existing condition for all parcels involved in this project
including all required existing information (watercourses, topography,
vegetation, utilities, property boundaries, etc.)
Site Plan – Comprehensive plan of all proposed improvements and limits of
disturbance.
Grading & Drainage Plan – Plan illustrates existing and proposed slopes,
proposed stormwater quantity and quality mitigation measures and limits of
disturbance.
Utility Plan – Plan includes detailed design information for the installation of
all proposed utilities resulting in the disturbance of soil for this project.
Erosion and Sediment Control Plan – Erosion and sediment control
measures to be in place and inspected, prior to commencement of
construction. The proposed measures were designed in accordance with the
current New York Standards and Specifications for Erosion and Control
Manual. Proposed measures include inlet protection, silt fence along the
project perimeter, temporary stone outlet sediment traps, stabilized
construction entrance and construction sequencing.
Erosion and Sediment Control Details – Plan contains all notes, details and
construction sequencing necessary for the construction of the erosion control
practices as shown on the Erosion and Sediment Control Plan.
Landscaping Plan – Included is all proposed landscaping for the project.
Construction Details – Included are all details associated with the post-
construction stormwater management system.
IV. Soil Description:
Data supplied by the USDA Natural Resources Conservation Service
(NRCS) indicates that site soils are primarily classified as Deerfield Loamy Fine
Sand (DeA and DeB) with a hydrologic soils group classification of “A” type soil
group. NRCS soil data can be found in the Stormwater Management Report
included in the appendices. Further on-site geotechnical evaluation was performed
to confirm soil characteristics and the findings may also be found in the
Stormwater Management Report included in the appendices.
4 | P a g e
V. Construction Phasing:
Limits of clearing and grading, utility and infrastructure installation and
all other associated activities resulting in soil disturbance are detailed on the
Erosion and Sediment Control, Grading and Drainage and Utility Plans.
Construction sequencing is listed on the General Notes Sheet.
VI. Pollution Prevention Measures:
Pollution Prevention measures during construction are detailed on the
SWPPP / Erosion and Sediment Control Plan. Construction waste will be
disposed in on-site construction dumpsters immediately. The dumpsters shall be
located such that any stormwater run-off will be directed to a sediment trap. Any
materials or chemicals considered to be hazardous shall be covered or stored in
construction trailers to ensure no discharge to stormwater will occur.
VII. Soil Stabilization Measures:
Initial clearing and grading will commence once the proposed erosion and
sediment control practices are in place as detailed on the erosion and sediment
control plan and approved by the SWPPP Monitoring Professional. All grading
and excavation will be conducted such that associated stormwater run-off is
directed to the temporary sediment trap. The trap will be abandoned once the
drainage structures are in place with proper inlet protection installed and all
disturbed areas are stabilized.
VIII. Erosion and Sediment Control Practices:
Specific types, sizes, lengths and dimensions for all erosion control
practices and sizing for temporary sediment basins are detailed on the Erosion and
Sediment Control Plan and Detail Sheet. All temporary erosion control practices
shall be in place prior to construction and shall remain until the limits of disturbed
areas are stabilized.
IX. Maintenance Schedule:
Maintenance of the proposed erosion and sediment control practices are
detailed on the Erosion and Sediment Control Plan. Included in this report are
Construction Inspection and Operations and Maintenance Checklists. The
operator is ultimately responsible for inspection and maintenance during
construction. Stabilization must be achieved prior to removal of temporary
erosion and sediment control devices and filing of the NYSDEC Notice of
Termination (NOT). The SWPPP Monitoring Professional must inspect and
approve final stabilization prior to filing of the NOT. Following the NOT filing,
which terminates permit coverage, the Property Owner or any subsequent owner
5 | P a g e
shall follow the guidelines set forth in this report and will be responsible for
operations and maintenance over the lifetime of the facility.
Operations and Maintenance of this facility is the responsibility of THBC
NY, LLC. A designated representative shall conduct bi-annual inspections and
keep a log of results and mitigation measures taken. This log shall be made
available to the City of Saratoga Springs at their request. Maintenance shall
depend mainly on inspection observations. Any deficiencies in the facility shall
be corrected immediately upon discovery. Sediment removal shall occur on an as
needed basis but at minimum twice yearly (if applicable). A qualified hauler,
familiar in the proper disposal of waste, shall dispose of sediment. All parking
lots shall be swept two (2) times per year, between the dates of October 1 and
June 1 of each year. Cleaning of structures shall include the removal, and proper
disposal, of all sand and debris from the sumps. Inspection forms and/or
checklists in addition to maintenance procedures have been provided for use as
part of this document.
X. Receiving Waters:
The proposed drainage system is designed to treat and release stormwater
below the pre-development flow rate for all subject storm events. Stormwater is
discharged to the existing wetlands along the eastern property line where it
eventually discharges to Kayaderosseras Creek, mimicking existing conditions.
XI. SWPPP Implementation and Permit Coverage Termination:
THBC NY, LLC, as the operator, shall have each contractor and sub-
contractors identify at least one (1) person responsible for SWPPP
Implementation. This person must be trained and certified by the NYSDEC as
stated on Page 19, Part III.A.6 of the NYSDEC General Permit GP-0-20-001
included in the appendix of this report. THBC NY, LLC, as the operator, shall
designate an inspector meeting the qualifications as set forth on page 24, Part IV
of the General Permit. The inspector shall be responsible for the construction
phase of the project and the implementation of the pollution prevention measures
set forth in this report. The designated individual shall have a complete
understanding of all components of the stormwater management system.
Delineation of SWPPP implementation responsibilities for the construction phase
of the project are detailed in the Erosion and Sediment Control Plan. The plan
details structural practices proposed to divert flows from exposed soils, store
flows, and limit run-off and discharge of pollutants from exposed areas of the site
during construction. THBC NY, LLC, shall also designate a qualified
representative for the post development inspection and monitoring. The inspector
shall follow the guidelines of the Operations and Maintenance Checklists included
in this report. The inspector shall keep a continuous record of all inspection
checklists, maintenance and repairs and shall make them available to the City and
the NYSDEC at their request.
6 | P a g e
An owner or operator that is eligible to terminate coverage must submit a
completed NOT form to the address in Part II.A.1 of the NYSDEC General
Permit GP-0-20-001 included in the appendix of this report. The NOT form shall
be one which is associated with the general permit, signed in accordance with Part
VII.H. An owner or operator may terminate coverage when one or more of the
conditions in Parts V.A.1 thru V.A.5 have been met.
XII. Stormwater Run-off Characteristics:
Existing and proposed data describing stormwater run-off characteristics
are included in the Stormwater Management Report, prepared by Bohler
Engineering. This report is included in the Appendix.
XIII. Archeological Sensitive Area:
The project site lies within an archeologically sensitive area per CRIS
mapping (map included in the Appendix). Application has been made to the State
Historic Preservation Office and the project site has been determined to have no
significant archeological sensitivity; no further investigation is required.
XIV. Construction Activities Meeting Conditions in Table 2 of
Appendix B
This project will generate site run-off from construction activity that
involves soil disturbance of one (1) or more acres, described in the permit section
referenced above. Therefore, the following information is provided:
1. Descriptions of each post-construction stormwater control practice are
included in the Stormwater Management Report and are detailed on
the Grading and Drainage Plan included in the Appendix of this report.
2. Hydrologic and hydraulic analyses for all structural components of the
stormwater control system, for all applicable design storms, are
included in the Stormwater Management Report.
3. Comparison of pre and post development stormwater run-off
conditions is included in the Stormwater Management Report.
4. Dimensions, materials and installation details for all post construction
strormwater control practices are specified on the enclosed Grading
and Drainage Plan.
5. A maintenance schedule is detailed on the Erosion and Sediment
Control Plan and in the Operations and Maintenance Checklists
included in this report.
7 | P a g e
XV. SWPPP Development – 6 Step Process:
1. Site Planning - Green Infrastructure
2. WQv Determination
3. Apply GI Practices and Standard SMP’s with RRv Capacity
4. Determine minimum RRv
5. Apply Standard SMP’s to address remaining WQv, if required
6. Apply volume and peak control
1. Site Planning – Green Infrastructure:
a) Preservation of Natural Resources:
o Preservation of Undisturbed Areas:
Construction and/or silt fence shall be constructed along the
perimeter of the limits of disturbance of the site. The operator and
contractors shall be instructed not to disturb any soil or vegetation
beyond the limits of construction as noted on the plans. The size of
the site and undisturbed area does not justify the delineation of
permanent conservation easements.
o Preservation of Buffers:
The project does not impact any natural buffers. Therefore,
delineation of permanent conservation easements is not warranted.
o Reduction of Clearing and Grading:
The limits of clearing and grading have been proposed at a
minimum needed to construct the proposed facility.
o Locating Development in Less Sensitive Areas:
The proposed development will not result in adverse impact to
sensitive resource areas such as floodplains, erodible soils, wetlands,
mature forests and critical habitats.
o Open Space Design:
The proposed layout of this facility has been designed as
conservatively as practical to reduce impervious coverage, preserve
open space and protect water resources, while maintaining adequate
space for access, parking and building area needed for the proposed
use.
o Soil Restoration / Preservation:
The greenspace areas will have fresh topsoil and seed/sod added to
establish turf and increase the porosity of the soils, in addition to
application of NYSDEC mandated soil restoration practices.
8 | P a g e
b) Reduction of Impervious Cover
o Roadway Reduction:
Roadway reduction is not applicable to this project.
o Sidewalk Reduction:
The sidewalks have been designed at a minimum width and length
to provide safe access through and around the facilities.
o Driveway Reduction:
The access drives have been designed at a minimum width and
length to provide safe access through the site.
o Cul-de-sac Reduction:
Cul-de-sac reduction is not applicable to this project.
o Building Footprint Reduction:
The building footprints have been designed at a minimum footprint
to meet the needs of the intended use.
o Parking Reduction:
The parking areas have been designed to provide the minimum
number of spaces needed for the intended uses.
2. Determining Water Quality Volume:
The Water Quality Volume (WQv) has been calculated and is shown in
the details section of the Storm Water Management Report.
3. Runoff Reduction:
Standard SMP Infiltration Basin and Dry Swale practices have been
applied to provide runoff reduction. Volume Reduction Porous Pavement
practices have also been applied to further reduce runoff volume. GI worksheets
and calculations are included within the Stormwater Management Report
prepared by Bohler, dated December 4, 2023, no revisions listed.
4. Minimum RRv:
The Minimum Runoff Reduction Volume Criteria has been calculated and
is shown in the details section of the Storm Water Management Report.
9 | P a g e
5. Apply SMP’s to address remaining WQv:
The required WQv is treated through several standard treatment practices
–Infiltration Basins and Dry Swales, as outlined within the Stormwater
Management Report.
6. Apply volume and peak rate control practices:
The stormwater management facilities have been designed to detain
tributary stormwater on site to control the volume and peak rate for the 1, 10 and
100 year storm events, as shown in the Drainage Report, included as an appendix
to this document.
10 | P a g e
XVI. Appendices
A. NYSDEC SPDES General Permit for Stormwater Discharges from
Construction Activity Permit No. GP-0-20-001
B. NYSDEC Notice of Intent (NOI) and Notice of Termination Forms
C. Stormwater General Operation and Maintenance Plan, Construction /
Operation and Maintenance / Inspection Report Forms, Inspector
Certification Form, Inspection Log & Construction Site Inspection and
Maintenance Log Book
D. Contractor/Owner Cert. Forms, Construction Activity Form
E. Cultural Resource Information System – Archeological Map and
NYSOPRHP Letter of No Effect
F. Stormwater Management Report
G. Construction Drawings & Phasing Plans
A. NYSDEC SPEDES GENERAL PERMIT
FOR STORMWATER DISCHARGES
FROM CONSTRUCTION ACTIVITY
PERMIT NO GP‐0‐20‐001
þ{ËìûtYsËK$TÅTåOTTPPO&TIJNITYÐepartnnent *fHnvlranmantattsnseruatiðnNEW YORK STATEDEPARTMENT OF ENVI RONMENTAL CONSERVATIONSPDES GENERAL PERMITFOR STORMWATER D¡SCHARGESFromCONSTRUCTION ACTIVITYPermit No. GP- 0-20-001lssued Pursuant to Article 17, Titles 7, I and Article 70of the Environmental Conservation LawEffective Date: January 29,2020Expiration Date: January 28,2025John J. FergusonChief Permit Administrator/^ zZ -Z-öuthorized SignatureDateAddress: NYS DECDivision of Environmental Permits625 Broadway, 4th FloorAlbany, N.Y. 12233-1750
I
PREFACE
Pursuant to Section 402 of the Clean Water Act (“CWA”), stormwater discharges
from certain construction activities are unlawful unless they are authorized by a National
Pollutant Discharge Elimination System (“NPDES”) permit or by a state permit program.
New York administers the approved State Pollutant Discharge Elimination System
(SPDES) program with permits issued in accordance with the New York State
Environmental Conservation Law (ECL) Article 17, Titles 7, 8 and Article 70.
An owner or operator of a construction activity that is eligible for coverage under
this permit must obtain coverage prior to the commencement of construction activity.
Activities that fit the definition of “construction activity”, as defined under 40 CFR
122.26(b)(14)(x), (15)(i), and (15)(ii), constitute construction of a point source and
therefore, pursuant to ECL section 17-0505 and 17-0701, the owner or operator must
have coverage under a SPDES permit prior to commencing construction activity. The
owner or operator cannot wait until there is an actual discharge from the construction site
to obtain permit coverage.
*Note: The italicized words/phrases within this permit are defined in Appendix A.
I
NEW YORK STATE DEPARTMENT OF ENVIRONMENTAL CONSERVATION
SPDES GENERAL PERMIT FOR STORMWATER DISCHARGES FROM
CONSTRUCTION ACTIVITIES
Table of Contents
Part 1. PERMIT COVERAGE AND LIMITATIONS ............................................................. 1
A. Permit Application ................................................................................................. 1
B. Effluent Limitations Applicable to Discharges from Construction Activities ........... 1
C. Post-construction Stormwater Management Practice Requirements .................... 4
D. Maintaining Water Quality ..................................................................................... 8
E. Eligibility Under This General Permit ..................................................................... 9
F. Activities Which Are Ineligible for Coverage Under This General Permit .............. 9
Part II. PERMIT COVERAGE ........................................................................................... 12
A. How to Obtain Coverage ..................................................................................... 12
B. Notice of Intent (NOI) Submittal .......................................................................... 13
C. Permit Authorization ............................................................................................ 13
D. General Requirements For Owners or Operators With Permit Coverage ........... 15
E. Permit Coverage for Discharges Authorized Under GP-0-15-002 ....................... 17
F. Change of Owner or Operator ............................................................................. 17
Part III. STORMWATER POLLUTION PREVENTION PLAN (SWPPP) ........................... 18
A. General SWPPP Requirements .......................................................................... 18
B. Required SWPPP Contents ................................................................................ 20
C. Required SWPPP Components by Project Type ................................................. 24
Part IV. INSPECTION AND MAINTENANCE REQUIREMENTS ..................................... 24
A. General Construction Site Inspection and Maintenance Requirements .............. 24
B. Contractor Maintenance Inspection Requirements ............................................. 24
C. Qualified Inspector Inspection Requirements ...................................................... 25
Part V. TERMINATION OF PERMIT COVERAGE ........................................................... 29
A. Termination of Permit Coverage ......................................................................... 29
Part VI. REPORTING AND RETENTION RECORDS ...................................................... 31
A. Record Retention ................................................................................................ 31
B. Addresses ........................................................................................................... 31
Part VII. STANDARD PERMIT CONDITIONS .................................................................. 31
A. Duty to Comply .................................................................................................... 31
B. Continuation of the Expired General Permit ........................................................ 32
C. Enforcement ........................................................................................................ 32
D. Need to Halt or Reduce Activity Not a Defense................................................... 32
E. Duty to Mitigate ................................................................................................... 33
F. Duty to Provide Information ................................................................................. 33
G. Other Information ................................................................................................ 33
H. Signatory Requirements ...................................................................................... 33
I. Property Rights ................................................................................................... 35
J. Severability.......................................................................................................... 35
K. Requirement to Obtain Coverage Under an Alternative Permit ........................... 35
L. Proper Operation and Maintenance .................................................................... 36
M. Inspection and Entry ........................................................................................... 36
N. Permit Actions ..................................................................................................... 37
O. Definitions ........................................................................................................... 37
P. Re-Opener Clause .............................................................................................. 37
Q. Penalties for Falsification of Forms and Reports ................................................. 37
R. Other Permits ...................................................................................................... 38
APPENDIX A – Acronyms and Definitions ....................................................................... 39
Acronyms ...................................................................................................................... 39
Definitions ..................................................................................................................... 40
APPENDIX B – Required SWPPP Components by Project Type .................................... 48
Table 1.......................................................................................................................... 48
Table 2.......................................................................................................................... 50
APPENDIX C – Watersheds Requiring Enhanced Phosphorus Removal ........................ 52
APPENDIX D – Watersheds with Lower Disturbance Threshold ..................................... 58
APPENDIX E – 303(d) Segments Impaired by Construction Related Pollutant(s) ........... 59
APPENDIX F – List of NYS DEC Regional Offices .......................................................... 65
(Part I)
1
Part 1. PERMIT COVERAGE AND LIMITATIONS
A. Permit Application
This permit authorizes stormwater discharges to surface waters of the State from
the following construction activities identified within 40 CFR Parts 122.26(b)(14)(x),
122.26(b)(15)(i) and 122.26(b)(15)(ii), provided all of the eligibility provisions of this
permit are met:
1. Construction activities involving soil disturbances of one (1) or more acres;
including disturbances of less than one acre that are part of a larger common
plan of development or sale that will ultimately disturb one or more acres of
land; excluding routine maintenance activity that is performed to maintain the
original line and grade, hydraulic capacity or original purpose of a facility;
2. Construction activities involving soil disturbances of less than one (1) acre
where the Department has determined that a SPDES permit is required for
stormwater discharges based on the potential for contribution to a violation of a
water quality standard or for significant contribution of pollutants to surface
waters of the State.
3. Construction activities located in the watershed(s) identified in Appendix D that
involve soil disturbances between five thousand (5,000) square feet and one
(1) acre of land.
B. Effluent Limitations Applicable to Discharges from Construction Activities
Discharges authorized by this permit must achieve, at a minimum, the effluent
limitations in Part I.B.1. (a) – (f) of this permit. These limitations represent the degree of
effluent reduction attainable by the application of best practicable technology currently
available.
1. Erosion and Sediment Control Requirements - The owner or operator must
select, design, install, implement and maintain control measures to minimize
the discharge of pollutants and prevent a violation of the water quality
standards. The selection, design, installation, implementation, and
maintenance of these control measures must meet the non-numeric effluent
limitations in Part I.B.1.(a) – (f) of this permit and be in accordance with the
New York State Standards and Specifications for Erosion and Sediment
Control, dated November 2016, using sound engineering judgment. Where
control measures are not designed in conformance with the design criteria
included in the technical standard, the owner or operator must include in the
Stormwater Pollution Prevention Plan (“SWPPP”) the reason(s) for the
(Part I.B.1)
2
deviation or alternative design and provide information which demonstrates that
the deviation or alternative design is equivalent to the technical standard.
a. Erosion and Sediment Controls. Design, install and maintain effective
erosion and sediment controls to minimize the discharge of pollutants and
prevent a violation of the water quality standards. At a minimum, such
controls must be designed, installed and maintained to:
(i) Minimize soil erosion through application of runoff control and soil
stabilization control measure to minimize pollutant discharges;
(ii) Control stormwater discharges, including both peak flowrates and total
stormwater volume, to minimize channel and streambank erosion and
scour in the immediate vicinity of the discharge points;
(iii) Minimize the amount of soil exposed during construction activity;
(iv) Minimize the disturbance of steep slopes;
(v) Minimize sediment discharges from the site;
(vi) Provide and maintain natural buffers around surface waters, direct
stormwater to vegetated areas and maximize stormwater infiltration to
reduce pollutant discharges, unless infeasible;
(vii) Minimize soil compaction. Minimizing soil compaction is not required
where the intended function of a specific area of the site dictates that it
be compacted;
(viii) Unless infeasible, preserve a sufficient amount of topsoil to complete
soil restoration and establish a uniform, dense vegetative cover; and
(ix) Minimize dust. On areas of exposed soil, minimize dust through the
appropriate application of water or other dust suppression techniques
to control the generation of pollutants that could be discharged from
the site.
b. Soil Stabilization. In areas where soil disturbance activity has temporarily
or permanently ceased, the application of soil stabilization measures must
be initiated by the end of the next business day and completed within
fourteen (14) days from the date the current soil disturbance activity ceased.
For construction sites that directly discharge to one of the 303(d) segments
(Part I.B.1.b)
3
listed in Appendix E or is located in one of the watersheds listed in
Appendix C, the application of soil stabilization measures must be initiated
by the end of the next business day and completed within seven (7) days
from the date the current soil disturbance activity ceased. See Appendix A
for definition of Temporarily Ceased.
c. Dewatering. Discharges from dewatering activities, including discharges
from dewatering of trenches and excavations, must be managed by
appropriate control measures.
d. Pollution Prevention Measures. Design, install, implement, and maintain
effective pollution prevention measures to minimize the discharge of
pollutants and prevent a violation of the water quality standards. At a
minimum, such measures must be designed, installed, implemented and
maintained to:
(i) Minimize the discharge of pollutants from equipment and vehicle
washing, wheel wash water, and other wash waters. This applies to
washing operations that use clean water only. Soaps, detergents and
solvents cannot be used;
(ii) Minimize the exposure of building materials, building products,
construction wastes, trash, landscape materials, fertilizers, pesticides,
herbicides, detergents, sanitary waste, hazardous and toxic waste, and
other materials present on the site to precipitation and to stormwater.
Minimization of exposure is not required in cases where the exposure
to precipitation and to stormwater will not result in a discharge of
pollutants, or where exposure of a specific material or product poses
little risk of stormwater contamination (such as final products and
materials intended for outdoor use) ; and
(iii) Prevent the discharge of pollutants from spills and leaks and
implement chemical spill and leak prevention and response
procedures.
e. Prohibited Discharges. The following discharges are prohibited:
(i) Wastewater from washout of concrete;
(ii) Wastewater from washout and cleanout of stucco, paint, form release
oils, curing compounds and other construction materials;
(Part I.B.1.e.iii)
4
(iii) Fuels, oils, or other pollutants used in vehicle and equipment operation
and maintenance;
(iv) Soaps or solvents used in vehicle and equipment washing; and
(v) Toxic or hazardous substances from a spill or other release.
f. Surface Outlets. When discharging from basins and impoundments, the
outlets shall be designed, constructed and maintained in such a manner
that sediment does not leave the basin or impoundment and that erosion at
or below the outlet does not occur.
C. Post-construction Stormwater Management Practice Requirements
1. The owner or operator of a construction activity that requires post-construction
stormwater management practices pursuant to Part III.C. of this permit must
select, design, install, and maintain the practices to meet the performance
criteria in the New York State Stormwater Management Design Manual
(“Design Manual”), dated January 2015, using sound engineering judgment.
Where post-construction stormwater management practices (“SMPs”) are not
designed in conformance with the performance criteria in the Design Manual,
the owner or operator must include in the SWPPP the reason(s) for the
deviation or alternative design and provide information which demonstrates that
the deviation or alternative design is equivalent to the technical standard.
2. The owner or operator of a construction activity that requires post-construction
stormwater management practices pursuant to Part III.C. of this permit must
design the practices to meet the applicable sizing criteria in Part I.C.2.a., b., c.
or d. of this permit.
a. Sizing Criteria for New Development
(i) Runoff Reduction Volume (“RRv”): Reduce the total Water Quality
Volume (“WQv”) by application of RR techniques and standard SMPs
with RRv capacity. The total WQv shall be calculated in accordance
with the criteria in Section 4.2 of the Design Manual.
(ii) Minimum RRv and Treatment of Remaining Total WQv: Construction
activities that cannot meet the criteria in Part I.C.2.a.(i) of this permit
due to site limitations shall direct runoff from all newly constructed
impervious areas to a RR technique or standard SMP with RRv
capacity unless infeasible. The specific site limitations that prevent the
reduction of 100% of the WQv shall be documented in the SWPPP.
(Part I.C.2.a.ii)
5
For each impervious area that is not directed to a RR technique or
standard SMP with RRv capacity, the SWPPP must include
documentation which demonstrates that all options were considered
and for each option explains why it is considered infeasible.
In no case shall the runoff reduction achieved from the newly
constructed impervious areas be less than the Minimum RRv as
calculated using the criteria in Section 4.3 of the Design Manual.
The remaining portion of the total WQv that cannot be reduced shal l be
treated by application of standard SMPs.
(iii) Channel Protection Volume (“Cpv”): Provide 24 hour extended
detention of the post-developed 1-year, 24-hour storm event;
remaining after runoff reduction. The Cpv requirement does not apply
when:
(1) Reduction of the entire Cpv is achieved by application of runoff
reduction techniques or infiltration systems, or
(2) The site discharges directly to tidal waters, or fifth order or larger
streams.
(iv) Overbank Flood Control Criteria (“Qp”): Requires storage to attenuate
the post-development 10-year, 24-hour peak discharge rate (Qp) to
predevelopment rates. The Qp requirement does not apply when:
(1) the site discharges directly to tidal waters or fifth order or larger
streams, or
(2) A downstream analysis reveals that overbank control is not
required.
(v) Extreme Flood Control Criteria (“Qf”): Requires storage to attenuate
the post-development 100-year, 24-hour peak discharge rate (Qf) to
predevelopment rates. The Qf requirement does not apply when:
(1) the site discharges directly to tidal waters or fifth order or larger
streams, or
(2) A downstream analysis reveals that overbank control is not
required.
b. Sizing Criteria for New Development in Enhanced Phosphorus
Removal Watershed
(i) Runoff Reduction Volume (RRv): Reduce the total Water Quality
Volume (WQv) by application of RR techniques and standard SMPs
with RRv capacity. The total WQv is the runoff volume from the 1 -year,
24 hour design storm over the post-developed watershed and shall be
(Part I.C.2.b.i)
6
calculated in accordance with the criteria in Section 10.3 of the Design
Manual.
(ii) Minimum RRv and Treatment of Remaining Total WQv: Construction
activities that cannot meet the criteria in Part I.C.2.b.(i) of this permit
due to site limitations shall direct runoff from all newly constructed
impervious areas to a RR technique or standard SMP with RRv
capacity unless infeasible. The specific site limitations that prevent the
reduction of 100% of the WQv shall be documented in the SWPPP.
For each impervious area that is not directed to a RR technique or
standard SMP with RRv capacity, the SWPPP must include
documentation which demonstrates that all options were considered
and for each option explains why it is considered infeasible.
In no case shall the runoff reduction achieved from the newly
constructed impervious areas be less than the Minimum RRv as
calculated using the criteria in Section 10.3 of the Design Manual.
The remaining portion of the total WQv that cannot be reduced shall be
treated by application of standard SMPs.
(iii) Channel Protection Volume (Cpv): Provide 24 hour extended detention
of the post-developed 1-year, 24-hour storm event; remaining after
runoff reduction. The Cpv requirement does not apply when:
(1) Reduction of the entire Cpv is achieved by application of runoff
reduction techniques or infiltration systems, or
(2) The site discharges directly to tidal waters, or fifth order or larger
streams.
(iv) Overbank Flood Control Criteria (Qp): Requires storage to attenuate
the post-development 10-year, 24-hour peak discharge rate (Qp) to
predevelopment rates. The Qp requirement does not apply when:
(1) the site discharges directly to tidal waters or fifth order or larger
streams, or
(2) A downstream analysis reveals that overbank control is not
required.
(v) Extreme Flood Control Criteria (Qf): Requires storage to attenuate the
post-development 100-year, 24-hour peak discharge rate (Qf) to
predevelopment rates. The Qf requirement does not apply when:
(1) the site discharges directly to tidal waters or fifth order or larger
streams, or
(2) A downstream analysis reveals that overbank control is not
required.
(Part I.C.2.c)
7
c. Sizing Criteria for Redevelopment Activity
(i) Water Quality Volume (WQv): The WQv treatment objective for
redevelopment activity shall be addressed by one of the following
options. Redevelopment activities located in an Enhanced Phosphorus
Removal Watershed (see Part III.B.3. and Appendix C of this permit)
shall calculate the WQv in accordance with Section 10.3 of the Design
Manual. All other redevelopment activities shall calculate the WQv in
accordance with Section 4.2 of the Design Manual.
(1) Reduce the existing impervious cover by a minimum of 25% of the
total disturbed, impervious area. The Soil Restoration criteria in
Section 5.1.6 of the Design Manual must be applied to all newly
created pervious areas, or
(2) Capture and treat a minimum of 25% of the WQv from the disturbed,
impervious area by the application of standard SMPs; or reduce 25%
of the WQv from the disturbed, impervious area by the application of
RR techniques or standard SMPs with RRv capacity., or
(3) Capture and treat a minimum of 75% of the WQv from the disturbed,
impervious area as well as any additional runoff from tributary areas
by application of the alternative practices discussed in Sections 9.3
and 9.4 of the Design Manual., or
(4) Application of a combination of 1, 2 and 3 above that provide a
weighted average of at least two of the above methods. Application
of this method shall be in accordance with the criteria in Section
9.2.1(B) (IV) of the Design Manual.
If there is an existing post-construction stormwater management
practice located on the site that captures and treats runoff from the
impervious area that is being disturbed, the WQv treatment option
selected must, at a minimum, provide treatment equal to the treatment
that was being provided by the existing practice(s) if that treatment is
greater than the treatment required by options 1 – 4 above.
(ii) Channel Protection Volume (Cpv): Not required if there are n o
changes to hydrology that increase the discharge rate from the project
site.
(iii) Overbank Flood Control Criteria (Qp): Not required if there are no
changes to hydrology that increase the discharge rate from the project
site.
(iv) Extreme Flood Control Criteria (Qf): Not required if there are no
changes to hydrology that increase the discharge rate from the project
site
(Part I.C.2.d)
8
d. Sizing Criteria for Combination of Redevelopment Activity and New
Development
Construction projects that include both New Development and Redevelopment
Activity shall provide post-construction stormwater management controls that
meet the sizing criteria calculated as an aggregate of the Sizing Criteria in Part
I.C.2.a. or b. of this permit for the New Development portion of the project and
Part I.C.2.c of this permit for Redevelopment Activity portion of the project.
D. Maintaining Water Quality
The Department expects that compliance with the conditions of this permit will control
discharges necessary to meet applicable water quality standards. It shall be a violation
of the ECL for any discharge to either cause or contribute to a violation of water quality
standards as contained in Parts 700 through 705 of Title 6 of the Official Comp ilation of
Codes, Rules and Regulations of the State of New York, such as:
1. There shall be no increase in turbidity that will cause a substantial visible contrast
to natural conditions;
2. There shall be no increase in suspended, colloidal or settleable solids that will
cause deposition or impair the waters for their best usages; and
3. There shall be no residue from oil and floating substances, nor visible oil film, nor
globules of grease.
If there is evidence indicating that the stormwater discharges authorized by this permit
are causing, have the reasonable potential to cause, or are contributing to a violation of
the water quality standards; the owner or operator must take appropriate corrective
action in accordance with Part IV.C.5. of this general permit and document in
accordance with Part IV.C.4. of this general permit. To address the water quality
standard violation the owner or operator may need to provide additional information,
include and implement appropriate controls in the SWPPP to correct the problem, or
obtain an individual SPDES permit.
If there is evidence indicating that despite compliance with the terms and conditions of
this general permit it is demonstrated that the stormwater discharges authorized by this
permit are causing or contributing to a violation of water quality standards, or if the
Department determines that a modification of the permit is necessary to prevent a
violation of water quality standards, the authorized discharges will no longer be eligible
for coverage under this permit. The Department may require the owner or operator to
obtain an individual SPDES permit to continue discharging.
(Part I.E)
9
E. Eligibility Under This General Permit
1. This permit may authorize all discharges of stormwater from construction
activity to surface waters of the State and groundwaters except for ineligible
discharges identified under subparagraph F. of this Part.
2. Except for non-stormwater discharges explicitly listed in the next paragraph,
this permit only authorizes stormwater discharges; including stormwater runoff,
snowmelt runoff, and surface runoff and drainage, from construction activities.
3. Notwithstanding paragraphs E.1 and E.2 above, the following non-stormwater
discharges are authorized by this permit: those listed in 6 NYCRR 750-
1.2(a)(29)(vi), with the following exception: “Discharges from firefighting
activities are authorized only when the firefighting activities are
emergencies/unplanned”; waters to which other components have not been
added that are used to control dust in accordance with the SWPPP ; and
uncontaminated discharges from construction site de-watering operations. All
non-stormwater discharges must be identified in the SWPPP. Under all
circumstances, the owner or operator must still comply with water quality
standards in Part I.D of this permit.
4. The owner or operator must maintain permit eligibility to discharge under this
permit. Any discharges that are not compliant with the eligibility conditions of
this permit are not authorized by the permit and the owner or operator must
either apply for a separate permit to cover those ineligible discharges or take
steps necessary to make the discharge eligible for coverage.
F. Activities Which Are Ineligible for Coverage Under This General Permit
All of the following are not authorized by this permit:
1. Discharges after construction activities have been completed and the site has
undergone final stabilization;
2. Discharges that are mixed with sources of non-stormwater other than those
expressly authorized under subsection E.3. of this Part and identified in the
SWPPP required by this permit;
3. Discharges that are required to obtain an individual SPDES permit or another
SPDES general permit pursuant to Part VII.K. of this permit;
4. Construction activities or discharges from construction activities that may
adversely affect an endangered or threatened species unless the owner or
(Part I.F.4)
10
operator has obtained a permit issued pursuant to 6 NYCRR Part 182 for the
project or the Department has issued a letter of non -jurisdiction for the project.
All documentation necessary to demonstrate eligibility shall be maintained on
site in accordance with Part II.D.2 of this permit;
5. Discharges which either cause or contribute to a violation of water quality
standards adopted pursuant to the ECL and its accompanying regulations;
6. Construction activities for residential, commercial and institutional projects:
a. Where the discharges from the construction activities are tributary to waters
of the state classified as AA or AA-s; and
b. Which are undertaken on land with no existing impervious cover; and
c. Which disturb one (1) or more acres of land designated on the current
United States Department of Agriculture (“USDA”) Soil Survey as Soil
Slope Phase “D”, (provided the map unit name is inclusive of slopes greater
than 25%), or Soil Slope Phase “E” or “F” (regardless of the map unit
name), or a combination of the three designations.
7. Construction activities for linear transportation projects and linear utility
projects:
a. Where the discharges from the construction activities are tributary to waters
of the state classified as AA or AA-s; and
b. Which are undertaken on land with no existing impervious cover; and
c. Which disturb two (2) or more acres of land designated on the current USDA
Soil Survey as Soil Slope Phase “D” (provided the map unit name is inclusive of
slopes greater than 25%), or Soil Slope Phase “E” or “F” (regardless of the map
unit name), or a combination of the three designations.
(Part I.F.8)
11
8. Construction activities that have the potential to affect an historic property,
unless there is documentation that such impacts have been resolved. The
following documentation necessary to demonstrate eligibility with this
requirement shall be maintained on site in accordance with Part II.D.2 of this
permit and made available to the Department in accordance with Part VII.F of
this permit:
a. Documentation that the construction activity is not within an archeologically
sensitive area indicated on the sensitivity map, and that the construction
activity is not located on or immediately adjacent to a property listed or
determined to be eligible for listing on the National or State Registers of
Historic Places, and that there is no new permanent building on the
construction site within the following distances from a building, structure, or
object that is more than 50 years old, or if there is such a new permanent
building on the construction site within those parameters that NYS Office of
Parks, Recreation and Historic Preservation (OPRHP), a Historic
Preservation Commission of a Certified Local Government, or a qualified
preservation professional has determined that the building, structure, or
object more than 50 years old is not historically/archeologically significant.
▪ 1-5 acres of disturbance - 20 feet
▪ 5-20 acres of disturbance - 50 feet
▪ 20+ acres of disturbance - 100 feet, or
b. DEC consultation form sent to OPRHP, and copied to the NYS DEC Agency
Historic Preservation Officer (APO), and
(i) the State Environmental Quality Review (SEQR) Environmental
Assessment Form (EAF) with a negative declaration or the Findings
Statement, with documentation of OPRHP’s agreement with the
resolution; or
(ii) documentation from OPRHP that the construction activity will result in
No Impact; or
(iii) documentation from OPRHP providing a determination of No Adverse
Impact; or
(iv) a Letter of Resolution signed by the owner/operator, OPRHP and the
DEC APO which allows for this construction activity to be eligible for
coverage under the general permit in terms of the State Historic
Preservation Act (SHPA); or
c. Documentation of satisfactory compliance with Section 106 of the National
Historic Preservation Act for a coterminous project area:
(Part I.F.8.c)
12
(i) No Affect
(ii) No Adverse Affect
(iii) Executed Memorandum of Agreement, or
d. Documentation that:
(i) SHPA Section 14.09 has been completed by NYS DEC or another state
agency.
9. Discharges from construction activities that are subject to an existing SPDES
individual or general permit where a SPDES permit for construction activity has
been terminated or denied; or where the owner or operator has failed to renew
an expired individual permit.
Part II. PERMIT COVERAGE
A. How to Obtain Coverage
1. An owner or operator of a construction activity that is not subject to the
requirements of a regulated, traditional land use control MS4 must first prepare
a SWPPP in accordance with all applicable requirements of this permit and
then submit a completed Notice of Intent (NOI) to the Department to be
authorized to discharge under this permit.
2. An owner or operator of a construction activity that is subject to the
requirements of a regulated, traditional land use control MS4 must first prepare
a SWPPP in accordance with all applicable requirements of this permit and
then have the SWPPP reviewed and accepted by the regulated, traditional land
use control MS4 prior to submitting the NOI to the Department. The owner or
operator shall have the “MS4 SWPPP Acceptance” form signed in accordance
with Part VII.H., and then submit that form along with a completed NOI to the
Department.
3. The requirement for an owner or operator to have its SWPPP reviewed and
accepted by the regulated, traditional land use control MS4 prior to submitting
the NOI to the Department does not apply to an owner or operator that is
obtaining permit coverage in accordance with the requirements in Part II.F.
(Change of Owner or Operator) or where the owner or operator of the
construction activity is the regulated, traditional land use control MS4 . This
exemption does not apply to construction activities subject to the New York City
Administrative Code.
(Part II.B)
13
B. Notice of Intent (NOI) Submittal
1. Prior to December 21, 2020, an owner or operator shall use either the
electronic (eNOI) or paper version of the NOI that the Department prepared.
Both versions of the NOI are located on the Department’s website
(http://www.dec.ny.gov/ ). The paper version of the NOI shall be signed in
accordance with Part VII.H. of this permit and submitted to the following
address:
NOTICE OF INTENT
NYS DEC, Bureau of Water Permits
625 Broadway, 4th Floor
Albany, New York 12233-3505
2. Beginning December 21, 2020 and in accordance with EPA’s 2015 NPDES
Electronic Reporting Rule (40 CFR Part 127), the owner or operator must submit
the NOI electronically using the Department’s online NOI.
3. The owner or operator shall have the SWPPP preparer sign the “SWPPP
Preparer Certification” statement on the NOI prior to submitting the form to the
Department.
4. As of the date the NOI is submitted to the Department, the owner or operator
shall make the NOI and SWPPP available for review and copying in accordance
with the requirements in Part VII.F. of this permit.
C. Permit Authorization
1. An owner or operator shall not commence construction activity until their
authorization to discharge under this permit goes into effect.
2. Authorization to discharge under this permit will be effective when the owner or
operator has satisfied all of the following criteria:
a. project review pursuant to the State Environmental Quality Review Act
(“SEQRA”) have been satisfied, when SEQRA is applicable. See the
Department’s website (http://www.dec.ny.gov/) for more information,
b. where required, all necessary Department permits subject to the Uniform
Procedures Act (“UPA”) (see 6 NYCRR Part 621), or the equivalent from
another New York State agency, have been obtained, unless otherwise
notified by the Department pursuant to 6 NYCRR 621.3(a)(4). Owners or
operators of construction activities that are required to obtain UPA permits
(Part II.C.2.b)
14
must submit a preliminary SWPPP to the appropriate DEC Permit
Administrator at the Regional Office listed in Appendix F at the time all other
necessary UPA permit applications are submitted. The preliminary SWPPP
must include sufficient information to demonstrate that the construction
activity qualifies for authorization under this permit,
c. the final SWPPP has been prepared, and
d. a complete NOI has been submitted to the Department in accordance with
the requirements of this permit.
3. An owner or operator that has satisfied the requirements of Part II.C.2 above
will be authorized to discharge stormwater from their construction activity in
accordance with the following schedule:
a. For construction activities that are not subject to the requirements of a
regulated, traditional land use control MS4:
(i) Five (5) business days from the date the Department receives a
complete electronic version of the NOI (eNOI) for construction activities
with a SWPPP that has been prepared in conformance with the design
criteria in the technical standard referenced in Part III.B.1 and the
performance criteria in the technical standard referenced in Parts III.B.,
2 or 3, for construction activities that require post-construction
stormwater management practices pursuant to Part III.C.; or
(ii) Sixty (60) business days from the date the Department receives a
complete NOI (electronic or paper version) for construction activities
with a SWPPP that has not been prepared in conformance with the
design criteria in technical standard referenced in Part III.B.1. or, for
construction activities that require post-construction stormwater
management practices pursuant to Part III.C., the performance criteria
in the technical standard referenced in Parts III.B., 2 or 3, or;
(iii) Ten (10) business days from the date the Department receives a
complete paper version of the NOI for construction activities with a
SWPPP that has been prepared in conformance with the design
criteria in the technical standard referenced in Part III.B.1 and the
performance criteria in the technical standard referenced in Parts III.B.,
2 or 3, for construction activities that require post-construction
stormwater management practices pursuant to Part III.C.
(Part II.C.3.b)
15
b. For construction activities that are subject to the requirements of a
regulated, traditional land use control MS4:
(i) Five (5) business days from the date the Department receives both a
complete electronic version of the NOI (eNOI) and signed “MS4
SWPPP Acceptance” form, or
(ii) Ten (10) business days from the date the Department receives both a
complete paper version of the NOI and signed “MS4 SWPPP
Acceptance” form.
4. Coverage under this permit authorizes stormwater discharges from only those
areas of disturbance that are identified in the NOI. If an owner or operator
wishes to have stormwater discharges from future or additional areas of
disturbance authorized, they must submit a new NOI that addresses that phase
of the development, unless otherwise notified by the Department. The owner or
operator shall not commence construction activity on the future or additional
areas until their authorization to discharge under this permit goes into effect in
accordance with Part II.C. of this permit.
D. General Requirements For Owners or Operators With Permit Coverage
1. The owner or operator shall ensure that the provisions of the SWPPP are
implemented from the commencement of construction activity until all areas of
disturbance have achieved final stabilization and the Notice of Termination
(“NOT”) has been submitted to the Department in accordance with Part V. of
this permit. This includes any changes made to the SWPPP pursuant to Part
III.A.4. of this permit.
2. The owner or operator shall maintain a copy of the General Permit (GP-0-20-
001), NOI, NOI Acknowledgment Letter, SWPPP, MS4 SWPPP Acceptance
form, inspection reports, responsible contractor’s or subcontractor’s certification
statement (see Part III.A.6.), and all documentation necessary to demonstrate
eligibility with this permit at the construction site until all disturbed areas have
achieved final stabilization and the NOT has been submitted to the Department.
The documents must be maintained in a secure location, such as a job trailer,
on-site construction office, or mailbox with lock. The secure location must be
accessible during normal business hours to an individual performing a
compliance inspection.
3. The owner or operator of a construction activity shall not disturb greater than
five (5) acres of soil at any one time without prior written authorization from the
Department or, in areas under the jurisdiction of a regulated, traditional land
(Part II.D.3)
16
use control MS4, the regulated, traditional land use control MS4 (provided the
regulated, traditional land use control MS4 is not the owner or operator of the
construction activity). At a minimum, the owner or operator must comply with
the following requirements in order to be authorized to disturb greater than fi ve
(5) acres of soil at any one time:
a. The owner or operator shall have a qualified inspector conduct at least two
(2) site inspections in accordance with Part IV.C. of this permit every seven
(7) calendar days, for as long as greater than five (5) acres of soil remain
disturbed. The two (2) inspections shall be separated by a minimum of two
(2) full calendar days.
b. In areas where soil disturbance activity has temporarily or permanently
ceased, the application of soil stabilization measures must be initiated by
the end of the next business day and completed within seven (7) days from
the date the current soil disturbance activity ceased. The soil stabilization
measures selected shall be in conformance with the technical standard,
New York State Standards and Specifications for Erosion and Sediment
Control, dated November 2016.
c. The owner or operator shall prepare a phasing plan that defines maximum
disturbed area per phase and shows required cuts and fills.
d. The owner or operator shall install any additional site-specific practices
needed to protect water quality.
e. The owner or operator shall include the requirements above in their
SWPPP.
4. In accordance with statute, regulations, and the terms and conditions of this
permit, the Department may suspend or revoke an owner’s or operator’s
coverage under this permit at any time if the Department determines that the
SWPPP does not meet the permit requirements or consistent with Part VII.K..
5. Upon a finding of significant non-compliance with the practices described in the
SWPPP or violation of this permit, the Department may order an immediate
stop to all activity at the site until the non-compliance is remedied. The stop
work order shall be in writing, describe the non-compliance in detail, and be
sent to the owner or operator.
6. For construction activities that are subject to the requirements of a regulated,
traditional land use control MS4, the owner or operator shall notify the
(Part II.D.6)
17
regulated, traditional land use control MS4 in writing of any planned
amendments or modifications to the post-construction stormwater management
practice component of the SWPPP required by Part III.A. 4. and 5. of this
permit. Unless otherwise notified by the regulated, traditional land use control
MS4, the owner or operator shall have the SWPPP amendments or
modifications reviewed and accepted by the regulated, traditional land use
control MS4 prior to commencing construction of the post-construction
stormwater management practice.
E. Permit Coverage for Discharges Authorized Under GP-0-15-002
1. Upon renewal of SPDES General Permit for Stormwater Discharges from
Construction Activity (Permit No. GP-0-15-002), an owner or operator of a
construction activity with coverage under GP-0-15-002, as of the effective date
of GP- 0-20-001, shall be authorized to discharge in accordance with GP- 0-20-
001, unless otherwise notified by the Department.
An owner or operator may continue to implement the technical/design
components of the post-construction stormwater management controls
provided that such design was done in conformance with the technical
standards in place at the time of initial project authorization. However, they
must comply with the other, non-design provisions of GP-0-20-001.
F. Change of Owner or Operator
1. When property ownership changes or when there is a change in operational
control over the construction plans and specifications, the original owner or
operator must notify the new owner or operator, in writing, of the requirement to
obtain permit coverage by submitting a NOI with the Department. For
construction activities subject to the requirements of a regulated, traditional
land use control MS4, the original owner or operator must also notify the MS4,
in writing, of the change in ownership at least 30 calendar days prior to the
change in ownership.
2. Once the new owner or operator obtains permit coverage, the original owner or
operator shall then submit a completed NOT with the name and permit
identification number of the new owner or operator to the Department at the
address in Part II.B.1. of this permit. If the original owner or operator maintains
ownership of a portion of the construction activity and will disturb soil, they must
maintain their coverage under the permit.
3. Permit coverage for the new owner or operator will be effective as of the date
the Department receives a complete NOI, provided the original owner or
(Part II.F.3)
18
operator was not subject to a sixty (60) business day authorization period that
has not expired as of the date the Department receives the NOI from the new
owner or operator.
Part III. STORMWATER POLLUTION PREVENTION PLAN (SWPPP)
A. General SWPPP Requirements
1. A SWPPP shall be prepared and implemented by the owner or operator of
each construction activity covered by this permit. The SWPPP must document
the selection, design, installation, implementation and maintenance of the
control measures and practices that will be used to meet the effluent limitations
in Part I.B. of this permit and where applicable, the post-construction
stormwater management practice requirements in Part I.C. of this permit. The
SWPPP shall be prepared prior to the submittal of the NOI. The NOI shall be
submitted to the Department prior to the commencement of construction
activity. A copy of the completed, final NOI shall be included in the SWPPP.
2. The SWPPP shall describe the erosion and sediment control practices and
where required, post-construction stormwater management practices that will
be used and/or constructed to reduce the pollutants in stormwater discharges
and to assure compliance with the terms and conditions of this permit. In
addition, the SWPPP shall identify potential sources of pollution which may
reasonably be expected to affect the quality of stormwater discharges.
3. All SWPPPs that require the post-construction stormwater management
practice component shall be prepared by a qualified professional that is
knowledgeable in the principles and practices of stormwater management and
treatment.
4. The owner or operator must keep the SWPPP current so that it at all times
accurately documents the erosion and sediment controls practices that are
being used or will be used during construction, and all post-construction
stormwater management practices that will be constructed on the site. At a
minimum, the owner or operator shall amend the SWPPP, including
construction drawings:
a. whenever the current provisions prove to be ineffective in minimizing
pollutants in stormwater discharges from the site;
(Part III.A.4.b)
19
b. whenever there is a change in design, construction, or operation at the
construction site that has or could have an effect on the discharge of
pollutants;
c. to address issues or deficiencies identified during an inspection by the
qualified inspector, the Department or other regulatory authority; and
d. to document the final construction conditions.
5. The Department may notify the owner or operator at any time that the SWPPP
does not meet one or more of the minimum requirements of this permit. The
notification shall be in writing and identify the provisions of the SWPPP that
require modification. Within fourteen (14) calendar days of such notificati on, or
as otherwise indicated by the Department, the owner or operator shall make
the required changes to the SWPPP and submit written notification to the
Department that the changes have been made. If the owner or operator does
not respond to the Department’s comments in the specified time frame, the
Department may suspend the owner’s or operator’s coverage under this permit
or require the owner or operator to obtain coverage under an individual SPDES
permit in accordance with Part II.D.4. of this permit.
6. Prior to the commencement of construction activity, the owner or operator must
identify the contractor(s) and subcontractor(s) that will be responsible for
installing, constructing, repairing, replacing, inspecting and maintaining the
erosion and sediment control practices included in the SWPPP; and the
contractor(s) and subcontractor(s) that will be responsible for constructing the
post-construction stormwater management practices included in the SWPPP.
The owner or operator shall have each of the contractors and subcontractors
identify at least one person from their company that will be responsible for
implementation of the SWPPP. This person shall be known as the trained
contractor. The owner or operator shall ensure that at least one trained
contractor is on site on a daily basis when soil disturbance activities are being
performed.
The owner or operator shall have each of the contractors and subcontractors
identified above sign a copy of the following certification statement below
before they commence any construction activity:
"I hereby certify under penalty of law that I understand and agree to comply
with the terms and conditions of the SWPPP and agree to implement any
corrective actions identified by the qualified inspector during a site
inspection. I also understand that the owner or operator must comply with
(Part III.A.6)
20
the terms and conditions of the most current version of the New York State
Pollutant Discharge Elimination System ("SPDES") general permit for
stormwater discharges from construction activities and that it is unlawful for
any person to cause or contribute to a violation of water quality standards.
Furthermore, I am aware that there are significant penalties for submitting
false information, that I do not believe to be true, including the possibility of
fine and imprisonment for knowing violations"
In addition to providing the certification statement above, the certification page
must also identify the specific elements of the SWPPP that each contractor and
subcontractor will be responsible for and include the name and title of the
person providing the signature; the name and title of the trained contractor
responsible for SWPPP implementation; the name, address and telephone
number of the contracting firm; the address (or other identifying description) of
the site; and the date the certification statement is signed. The owner or
operator shall attach the certification statement(s) to the copy of the SWPPP
that is maintained at the construction site. If new or additional contractors are
hired to implement measures identified in the SWPPP after construction has
commenced, they must also sign the certification statement and provide the
information listed above.
7. For projects where the Department requests a copy of the SWPPP or
inspection reports, the owner or operator shall submit the documents in both
electronic (PDF only) and paper format within five (5) business days, unless
otherwise notified by the Department.
B. Required SWPPP Contents
1. Erosion and sediment control component - All SWPPPs prepared pursuant to
this permit shall include erosion and sediment control practices designed in
conformance with the technical standard, New York State Standards and
Specifications for Erosion and Sediment Control, dated November 2016. Where
erosion and sediment control practices are not designed in conformance with
the design criteria included in the technical standard, the owner or operator
must demonstrate equivalence to the technical standard. At a minimum, the
erosion and sediment control component of the SWPPP shall include the
following:
a. Background information about the scope of the project, including the
location, type and size of project
(Part III.B.1.b)
21
b. A site map/construction drawing(s) for the project, including a general
location map. At a minimum, the site map shall show the total site area; all
improvements; areas of disturbance; areas that will not be disturbed;
existing vegetation; on-site and adjacent off-site surface water(s);
floodplain/floodway boundaries; wetlands and drainage patterns that could
be affected by the construction activity; existing and final contours ;
locations of different soil types with boundaries; material, waste, borrow or
equipment storage areas located on adjacent properties; and location(s) of
the stormwater discharge(s);
c. A description of the soil(s) present at the site, including an identification of
the Hydrologic Soil Group (HSG);
d. A construction phasing plan and sequence of operations describing the
intended order of construction activities, including clearing and grubbing,
excavation and grading, utility and infrastructure installation and any other
activity at the site that results in soil disturbance;
e. A description of the minimum erosion and sediment control practices to be
installed or implemented for each construction activity that will result in soil
disturbance. Include a schedule that identifies the timing of initial placement
or implementation of each erosion and sediment control practice and the
minimum time frames that each practice should remain in place or be
implemented;
f. A temporary and permanent soil stabilization plan that meets the
requirements of this general permit and the technical standard, New York
State Standards and Specifications for Erosion and Sediment Control, dated
November 2016, for each stage of the project, including initial land clearing
and grubbing to project completion and achievement of final stabilization;
g. A site map/construction drawing(s) showing the specific location(s), size(s),
and length(s) of each erosion and sediment control practice;
h. The dimensions, material specifications, installation details, and operation
and maintenance requirements for all erosion and sediment control
practices. Include the location and sizing of any temporary sediment basins
and structural practices that will be used to divert flows from exposed soils;
i. A maintenance inspection schedule for the contractor(s) identified in Part
III.A.6. of this permit, to ensure continuous and effective operation of the
erosion and sediment control practices. The maintenance inspection
(Part III.B.1.i)
22
schedule shall be in accordance with the requirements in the technical
standard, New York State Standards and Specifications for Erosion and
Sediment Control, dated November 2016;
j. A description of the pollution prevention measures that will be used to
control litter, construction chemicals and construction debris from becoming
a pollutant source in the stormwater discharges;
k. A description and location of any stormwater discharges associated with
industrial activity other than construction at the site, including, but not limited
to, stormwater discharges from asphalt plants and concrete plants located
on the construction site; and
l. Identification of any elements of the design that are not in conformance with
the design criteria in the technical standard, New York State Standards and
Specifications for Erosion and Sediment Control, dated November 2016.
Include the reason for the deviation or alternative design and provide
information which demonstrates that the deviation or alternative design is
equivalent to the technical standard.
2. Post-construction stormwater management practice component – The owner or
operator of any construction project identified in Table 2 of Appendix B as
needing post-construction stormwater management practices shall prepare a
SWPPP that includes practices designed in conformance with the applicable
sizing criteria in Part I.C.2.a., c. or d. of this permit and the performance criteria
in the technical standard, New York State Stormwater Management Design
Manual dated January 2015
Where post-construction stormwater management practices are not designed
in conformance with the performance criteria in the technical standard, the
owner or operator must include in the SWPPP the reason(s) for the deviation or
alternative design and provide information which demonstrates that the
deviation or alternative design is equivalent to the technical standard.
The post-construction stormwater management practice component of the
SWPPP shall include the following:
a. Identification of all post-construction stormwater management practices to
be constructed as part of the project. Include the dimensions, material
specifications and installation details for each post-construction stormwater
management practice;
(Part III.B.2.b)
23
b. A site map/construction drawing(s) showing the specific location and size of
each post-construction stormwater management practice;
c. A Stormwater Modeling and Analysis Report that includes:
(i) Map(s) showing pre-development conditions, including
watershed/subcatchments boundaries, flow paths/routing, and design
points;
(ii) Map(s) showing post-development conditions, including
watershed/subcatchments boundaries, flow paths/routing, design
points and post-construction stormwater management practices;
(iii) Results of stormwater modeling (i.e. hydrology and hydraulic analysis)
for the required storm events. Include supporting calculations (model
runs), methodology, and a summary table that compares pre and post -
development runoff rates and volumes for the different storm events;
(iv) Summary table, with supporting calculations, which demonstrates that
each post-construction stormwater management practice has been
designed in conformance with the sizing criteria included in the Design
Manual;
(v) Identification of any sizing criteria that is not required based on the
requirements included in Part I.C. of this permit; and
(vi) Identification of any elements of the design that are not in conformance
with the performance criteria in the Design Manual. Include the
reason(s) for the deviation or alternative design and provide
information which demonstrates that the deviation or alt ernative design
is equivalent to the Design Manual;
d. Soil testing results and locations (test pits, borings);
e. Infiltration test results, when required; and
f. An operations and maintenance plan that includes inspection and
maintenance schedules and actions to ensure continuous and effective
operation of each post-construction stormwater management practice. The
plan shall identify the entity that will be responsible for the long term
operation and maintenance of each practice.
(Part III.B.3)
24
3. Enhanced Phosphorus Removal Standards - All construction projects identified
in Table 2 of Appendix B that are located in the watersheds identified in
Appendix C shall prepare a SWPPP that includes post -construction stormwater
management practices designed in conformance with the applicable sizing
criteria in Part I.C.2. b., c. or d. of this permit and the performance criteria,
Enhanced Phosphorus Removal Standards included in the Design Manual. At a
minimum, the post-construction stormwater management practice component
of the SWPPP shall include items 2.a - 2.f. above.
C. Required SWPPP Components by Project Type
Unless otherwise notified by the Department, owners or operators of construction
activities identified in Table 1 of Appendix B are required to prepare a SWPPP that only
includes erosion and sediment control practices designed in conformance with Part
III.B.1 of this permit. Owners or operators of the construction activities identified in Table
2 of Appendix B shall prepare a SWPPP that also includes post-construction stormwater
management practices designed in conformance with Part III.B.2 or 3 of this permit.
Part IV. INSPECTION AND MAINTENANCE REQUIREMENTS
A. General Construction Site Inspection and Maintenance Requirements
1. The owner or operator must ensure that all erosion and sediment control
practices (including pollution prevention measures) and all post-construction
stormwater management practices identified in the SWPPP are inspected and
maintained in accordance with Part IV.B. and C. of this permit.
2. The terms of this permit shall not be construed to prohibit the State of New
York from exercising any authority pursuant to the ECL, common law or federal
law, or prohibit New York State from taking any measures, whether civil or
criminal, to prevent violations of the laws of the State of New York or protect
the public health and safety and/or the environment.
B. Contractor Maintenance Inspection Requirements
1. The owner or operator of each construction activity identified in Tables 1 and 2
of Appendix B shall have a trained contractor inspect the erosion and sediment
control practices and pollution prevention measures being implemented within
the active work area daily to ensure that they are being maintained in effective
operating condition at all times. If deficiencies are identified, the contractor shall
(Part IV.B.1)
25
begin implementing corrective actions within one business day and shall
complete the corrective actions in a reasonable time frame.
2. For construction sites where soil disturbance activities have been temporarily
suspended (e.g. winter shutdown) and temporary stabilization measures have
been applied to all disturbed areas, the trained contractor can stop conducting
the maintenance inspections. The trained contractor shall begin conducting the
maintenance inspections in accordance with Part IV.B.1. of this permit as soon
as soil disturbance activities resume.
3. For construction sites where soil disturbance activities have been shut down
with partial project completion, the trained contractor can stop conducting the
maintenance inspections if all areas disturbed as of the project shutdown date
have achieved final stabilization and all post-construction stormwater
management practices required for the completed portion of the project have
been constructed in conformance with the SWPPP and are operational.
C. Qualified Inspector Inspection Requirements
The owner or operator shall have a qualified inspector conduct site inspections in
conformance with the following requirements:
[Note: The trained contractor identified in Part III.A.6. and IV.B. of this permit cannot
conduct the qualified inspector site inspections unless they meet the qualified inspector
qualifications included in Appendix A. In order to perform these inspections, the trained
contractor would have to be a:
▪ licensed Professional Engineer,
▪ Certified Professional in Erosion and Sediment Control (CPESC),
▪ New York State Erosion and Sediment Control Certificate Program holder
▪ Registered Landscape Architect, or
▪ someone working under the direct supervision of, and at the same company as,
the licensed Professional Engineer or Registered Landscape Architect, provided
they have received four (4) hours of Department endorsed training in proper
erosion and sediment control principles from a Soil and Water Conservation
District, or other Department endorsed entity].
1. A qualified inspector shall conduct site inspections for all construction activities
identified in Tables 1 and 2 of Appendix B, with the exception of:
a. the construction of a single family residential subdivision with 25% or less
impervious cover at total site build-out that involves a soil disturbance of
one (1) or more acres of land but less than five (5) acres and is not located
(Part IV.C.1.a)
26
in one of the watersheds listed in Appendix C and not directly discharging to
one of the 303(d) segments listed in Appendix E;
b. the construction of a single family home that involves a soil disturbance of
one (1) or more acres of land but less than five (5) acres and is not located
in one of the watersheds listed in Appendix C and not directly discharging to
one of the 303(d) segments listed in Appendix E;
c. construction on agricultural property that involves a soil disturbance of one
(1) or more acres of land but less than five (5) acres; and
d. construction activities located in the watersheds identified in Appendix D
that involve soil disturbances between five thousand (5,000) square feet
and one (1) acre of land.
2. Unless otherwise notified by the Department, the qualified inspector shall
conduct site inspections in accordance with the following timetable:
a. For construction sites where soil disturbance activities are on-going, the
qualified inspector shall conduct a site inspection at least once every seven
(7) calendar days.
b. For construction sites where soil disturbance activities are on-going and the
owner or operator has received authorization in accordance with Part II.D.3
to disturb greater than five (5) acres of soil at any one time, the qualified
inspector shall conduct at least two (2) site inspections every seven (7)
calendar days. The two (2) inspections shall be separated by a minimum of
two (2) full calendar days.
c. For construction sites where soil disturbance activities have been
temporarily suspended (e.g. winter shutdown) and temporary stabilization
measures have been applied to all disturbed areas, the qualified inspector
shall conduct a site inspection at least once every thirty (30) calendar days.
The owner or operator shall notify the DOW Water (SPDES) Program
contact at the Regional Office (see contact information in Appendix F) or, in
areas under the jurisdiction of a regulated, traditional land use control MS4,
the regulated, traditional land use control MS4 (provided the regulated,
traditional land use control MS4 is not the owner or operator of the
construction activity) in writing prior to reducing the frequency of
inspections.
(Part IV.C.2.d)
27
d. For construction sites where soil disturbance activities have been shut down
with partial project completion, the qualified inspector can stop conducting
inspections if all areas disturbed as of the project shutdown date have
achieved final stabilization and all post-construction stormwater
management practices required for the completed portion of the project
have been constructed in conformance with the SWPPP and are
operational. The owner or operator shall notify the DOW Water (SPDES)
Program contact at the Regional Office (see contact information in Appendix
F) or, in areas under the jurisdiction of a regulated, traditional land use
control MS4, the regulated, traditional land use control MS4 (provided the
regulated, traditional land use control MS4 is not the owner or operator of
the construction activity) in writing prior to the shutdown. If soil disturbance
activities are not resumed within 2 years from the date of shutdown, the
owner or operator shall have the qualified inspector perform a final
inspection and certify that all disturbed areas have achieved final
stabilization, and all temporary, structural erosion and sediment control
measures have been removed; and that all post-construction stormwater
management practices have been constructed in conformance with the
SWPPP by signing the “Final Stabilization” and “Post-Construction
Stormwater Management Practice” certification statements on the NOT. The
owner or operator shall then submit the completed NOT form to the address
in Part II.B.1 of this permit.
e. For construction sites that directly discharge to one of the 303(d) segments
listed in Appendix E or is located in one of the watersheds listed in
Appendix C, the qualified inspector shall conduct at least two (2) site
inspections every seven (7) calendar days. The two (2) inspections shall be
separated by a minimum of two (2) full calendar days.
3. At a minimum, the qualified inspector shall inspect all erosion and sediment
control practices and pollution prevention measures to ensure integrity and
effectiveness, all post-construction stormwater management practices under
construction to ensure that they are constructed in conformance with the
SWPPP, all areas of disturbance that have not achieved final stabilization, all
points of discharge to natural surface waterbodies located within, or
immediately adjacent to, the property boundaries of the construction site, and
all points of discharge from the construction site.
4. The qualified inspector shall prepare an inspection report subsequent to each
and every inspection. At a minimum, the inspection report shall includ e and/or
address the following:
(Part IV.C.4.a)
28
a. Date and time of inspection;
b. Name and title of person(s) performing inspection;
c. A description of the weather and soil conditions (e.g. dry, wet, saturated) at
the time of the inspection;
d. A description of the condition of the runoff at all points of discharge from the
construction site. This shall include identification of any discharges of
sediment from the construction site. Include discharges from conveyance
systems (i.e. pipes, culverts, ditches, etc.) and overland flow;
e. A description of the condition of all natural surface waterbodies located
within, or immediately adjacent to, the property boundaries of the
construction site which receive runoff from disturbed areas. This shall
include identification of any discharges of sediment to the surface
waterbody;
f. Identification of all erosion and sediment control practices and pollution
prevention measures that need repair or maintenance;
g. Identification of all erosion and sediment control practices and pollution
prevention measures that were not installed properly or are not functioning
as designed and need to be reinstalled or replaced;
h. Description and sketch of areas with active soil disturbance activity, areas
that have been disturbed but are inactive at the time of the inspection, and
areas that have been stabilized (temporary and/or final) since the last
inspection;
i. Current phase of construction of all post-construction stormwater
management practices and identification of all construction that is not in
conformance with the SWPPP and technical standards;
j. Corrective action(s) that must be taken to install, repair, replace or maintain
erosion and sediment control practices and pollution prevention measures;
and to correct deficiencies identified with the construction of the post-
construction stormwater management practice(s);
k. Identification and status of all corrective actions that were required by
previous inspection; and
(Part IV.C.4.l)
29
l. Digital photographs, with date stamp, that clearly show the condition of all
practices that have been identified as needing corrective actions. The
qualified inspector shall attach paper color copies of the digital photographs
to the inspection report being maintained onsite within seven (7) calendar
days of the date of the inspection. The qualified inspector shall also take
digital photographs, with date stamp, that clearly show the condition of the
practice(s) after the corrective action has been completed. The qualified
inspector shall attach paper color copies of the digital photographs to the
inspection report that documents the completion of the corrective action
work within seven (7) calendar days of that inspection.
5. Within one business day of the completion of an inspection, the qualified
inspector shall notify the owner or operator and appropriate contractor or
subcontractor identified in Part III.A.6. of this permit of any corrective actions
that need to be taken. The contractor or subcontractor shall begin implementing
the corrective actions within one business day of this notification and shall
complete the corrective actions in a reasonable time frame.
6. All inspection reports shall be signed by the qualified inspector. Pursuant to
Part II.D.2. of this permit, the inspection reports shall be maintained on site with
the SWPPP.
Part V. TERMINATION OF PERMIT COVERAGE
A. Termination of Permit Coverage
1. An owner or operator that is eligible to terminate coverage under this permit
must submit a completed NOT form to the address in Part II.B.1 of this permit.
The NOT form shall be one which is associated with this permit, signed in
accordance with Part VII.H of this permit.
2. An owner or operator may terminate coverage when one or more the following
conditions have been met:
a. Total project completion - All construction activity identified in the SWPPP
has been completed; and all areas of disturbance have achieved final
stabilization; and all temporary, structural erosion and sediment control
measures have been removed; and all post-construction stormwater
management practices have been constructed in conformance with the
SWPPP and are operational;
(Part V.A.2.b)
30
b. Planned shutdown with partial project completion - All soil disturbance
activities have ceased; and all areas disturbed as of the project shutdown
date have achieved final stabilization; and all temporary, structural erosion
and sediment control measures have been removed; and all post-
construction stormwater management practices required for the completed
portion of the project have been constructed in conformance with the
SWPPP and are operational;
c. A new owner or operator has obtained coverage under this permit in
accordance with Part II.F. of this permit.
d. The owner or operator obtains coverage under an alternative SPDES
general permit or an individual SPDES permit.
3. For construction activities meeting subdivision 2a. or 2b. of this Part, the owner
or operator shall have the qualified inspector perform a final site inspection
prior to submitting the NOT. The qualified inspector shall, by signing the “Final
Stabilization” and “Post-Construction Stormwater Management Practice
certification statements on the NOT, certify that all the requirements in Part
V.A.2.a. or b. of this permit have been achieved.
4. For construction activities that are subject to the requirements of a regulated,
traditional land use control MS4 and meet subdivision 2a. or 2b. of this Part, the
owner or operator shall have the regulated, traditional land use control MS4
sign the “MS4 Acceptance” statement on the NOT in accordance with the
requirements in Part VII.H. of this permit. The regulated, traditional land use
control MS4 official, by signing this statement, has determined that it is
acceptable for the owner or operator to submit the NOT in accordance with the
requirements of this Part. The regulated, traditional land use control MS4 can
make this determination by performing a final site inspection themselves or by
accepting the qualified inspector’s final site inspection certification(s) required
in Part V.A.3. of this permit.
5. For construction activities that require post-construction stormwater
management practices and meet subdivision 2a. of this Part, the owner or
operator must, prior to submitting the NOT, ensure one of the following:
a. the post-construction stormwater management practice(s) and any right-of-
way(s) needed to maintain such practice(s) have been deeded to the
municipality in which the practice(s) is located,
(Part V.A.5.b)
31
b. an executed maintenance agreement is in place with the municipality that
will maintain the post-construction stormwater management practice(s),
c. for post-construction stormwater management practices that are privately
owned, the owner or operator has a mechanism in place that requires
operation and maintenance of the practice(s) in accordance with the
operation and maintenance plan, such as a deed covenant in the owner or
operator’s deed of record,
d. for post-construction stormwater management practices that are owned by
a public or private institution (e.g. school, university, hospital), government
agency or authority, or public utility; the owner or operator has policy and
procedures in place that ensures operation and maintenance of the
practices in accordance with the operation and maintenance plan.
Part VI. REPORTING AND RETENTION RECORDS
A. Record Retention
The owner or operator shall retain a copy of the NOI, NOI
Acknowledgment Letter, SWPPP, MS4 SWPPP Acceptance form and any inspection
reports that were prepared in conjunction with this permit for a period of at least five (5)
years from the date that the Department receives a complete NOT sub mitted in
accordance with Part V. of this general permit.
B. Addresses
With the exception of the NOI, NOT, and MS4 SWPPP Acceptance form (which must
be submitted to the address referenced in Part II.B.1 of this permit), all written
correspondence requested by the Department, including individual permit applications,
shall be sent to the address of the appropriate DOW Water (SPDES) Program contact
at the Regional Office listed in Appendix F.
Part VII. STANDARD PERMIT CONDITIONS
A. Duty to Comply
The owner or operator must comply with all conditions of this permit. All contractors
and subcontractors associated with the project must comply with the terms of the
SWPPP. Any non-compliance with this permit constitutes a violation of the Clean Water
(Part VII.A)
32
Act (CWA) and the ECL and is grounds for an enforcement action against the owner or
operator and/or the contractor/subcontractor; permit revocation, suspension or
modification; or denial of a permit renewal application. Upon a finding of significant non -
compliance with this permit or the applicable SWPPP, the Department may order an
immediate stop to all construction activity at the site until the non-compliance is
remedied. The stop work order shall be in writing, shall describe the non -compliance in
detail, and shall be sent to the owner or operator.
If any human remains or archaeological remains are encountered during excavation,
the owner or operator must immediately cease, or cause to cease, all construction
activity in the area of the remains and notify the appropriate Reg ional Water Engineer
(RWE). Construction activity shall not resume until written permission to do so has been
received from the RWE.
B. Continuation of the Expired General Permit
This permit expires five (5) years from the effective date. If a new general permit is not
issued prior to the expiration of this general permit, an owner or operator with coverage
under this permit may continue to operate and discharge in accordance with the terms
and conditions of this general permit, if it is extended pursuant to the State
Administrative Procedure Act and 6 NYCRR Part 621, until a new general permit is
issued.
C. Enforcement
Failure of the owner or operator, its contractors, subcontractors, agents and/or assigns
to strictly adhere to any of the permit requirements contained herein shall constitute a
violation of this permit. There are substantial criminal, civil, and administrative penalties
associated with violating the provisions of this permit. Fines of up to $37,500 per day
for each violation and imprisonment for up to fifteen (15) years may be assessed
depending upon the nature and degree of the offense.
D. Need to Halt or Reduce Activity Not a Defense
It shall not be a defense for an owner or operator in an enforcement action that it would
have been necessary to halt or reduce the construction activity in order to maintain
compliance with the conditions of this permit.
(Part VII.E)
33
E. Duty to Mitigate
The owner or operator and its contractors and subcontractors shall take all reasonable
steps to minimize or prevent any discharge in violation of this permit which has a
reasonable likelihood of adversely affecting human health or the environment.
F. Duty to Provide Information
The owner or operator shall furnish to the Department, within a reasonable specified
time period of a written request, all documentation necessary to demonstrate eligibility
and any information to determine compliance with this permit or to determine whether
cause exists for modifying or revoking this permit, or suspending or denying coverage
under this permit, in accordance with the terms and conditions of this permit. The NOI,
SWPPP and inspection reports required by this permit are public documents that the
owner or operator must make available for review and copying by any person within five
(5) business days of the owner or operator receiving a written request by any such
person to review these documents. Copying of documents will be done at the
requester’s expense.
G. Other Information
When the owner or operator becomes aware that they failed to submit any relevant
facts, or submitted incorrect information in the NOI or in any of the documents required
by this permit , or have made substantive revisions to the SWPPP (e.g. th e scope of the
project changes significantly, the type of post-construction stormwater management
practice(s) changes, there is a reduction in the sizing of the post-construction
stormwater management practice, or there is an increase in the disturbance ar ea or
impervious area), which were not reflected in the original NOI submitted to the
Department, they shall promptly submit such facts or information to the Department
using the contact information in Part II.A. of this permit. Failure of the owner or operator
to correct or supplement any relevant facts within five (5) business days of becoming
aware of the deficiency shall constitute a violation of this permit.
H. Signatory Requirements
1. All NOIs and NOTs shall be signed as follows:
a. For a corporation these forms shall be signed by a responsible corporate
officer. For the purpose of this section, a responsible corporate officer
means:
(Part VII.H.1.a)
34
(i) a president, secretary, treasurer, or vice-president of the corporation in
charge of a principal business function, or any other person who
performs similar policy or decision-making functions for the
corporation; or
(ii) the manager of one or more manufacturing, production or operating
facilities, provided the manager is authorized to make management
decisions which govern the operation of the regulated facility including
having the explicit or implicit duty of making major capital investment
recommendations, and initiating and directing other comprehensive
measures to assure long term environmental compliance with
environmental laws and regulations; the manager can ensure that the
necessary systems are established or actions taken to gather complete
and accurate information for permit application requirements; and
where authority to sign documents has been assigned or delegated to
the manager in accordance with corporate procedures;
b. For a partnership or sole proprietorship these forms shall be signed by a
general partner or the proprietor, respectively; or
c. For a municipality, State, Federal, or other public agency these forms shall
be signed by either a principal executive officer or ranking elected official.
For purposes of this section, a principal executive officer of a Federal
agency includes:
(i) the chief executive officer of the agency, or
(ii) a senior executive officer having responsibility for the overall
operations of a principal geographic unit of the agency (e.g., Regional
Administrators of EPA).
2. The SWPPP and other information requested by the Department shall be
signed by a person described in Part VII.H.1. of this permit or by a duly
authorized representative of that person. A person is a duly authorized
representative only if:
a. The authorization is made in writing by a person described in Part VII.H.1.
of this permit;
b. The authorization specifies either an individual or a position having
responsibility for the overall operation of the regulated facility or activity,
such as the position of plant manager, operator of a well or a well field,
(Part VII.H.2.b)
35
superintendent, position of equivalent responsibility, or an individual or
position having overall responsibility for environmental matters for the
company. (A duly authorized representative may thus be either a named
individual or any individual occupying a named position) and,
c. The written authorization shall include the name, title and signature of the
authorized representative and be attached to the SWPPP.
3. All inspection reports shall be signed by the qualified inspector that performs
the inspection.
4. The MS4 SWPPP Acceptance form shall be signed by the principal executive
officer or ranking elected official from the regulated, traditional land use control
MS4, or by a duly authorized representative of that person.
It shall constitute a permit violation if an incorrect and/or improper signatory
authorizes any required forms, SWPPP and/or inspection reports.
I. Property Rights
The issuance of this permit does not convey any property rights of any sort, nor any
exclusive privileges, nor does it authorize any injury to private property nor any invasion
of personal rights, nor any infringement of Federal, State or local laws or reg ulations.
Owners or operators must obtain any applicable conveyances, easements, licenses
and/or access to real property prior to commencing construction activity.
J. Severability
The provisions of this permit are severable, and if any provision of this permit, or the
application of any provision of this permit to any circumstance, is held invalid, the
application of such provision to other circumstances, and the remainder of this permit
shall not be affected thereby.
K. Requirement to Obtain Coverage Under an Alternative Permit
1. The Department may require any owner or operator authorized by this permit to
apply for and/or obtain either an individual SPDES permit or another SPDES
general permit. When the Department requires any discharger authorized by a
general permit to apply for an individual SPDES permit, it shall notify the
discharger in writing that a permit application is required. This notice shall
(Part VII.K.1)
36
include a brief statement of the reasons for this decision, an application form,
a statement setting a time frame for the owner or operator to file the
application for an individual SPDES permit, and a deadline, not sooner than
180 days from owner or operator receipt of the notification letter, whereby the
authorization to discharge under this general permit shall be terminated.
Applications must be submitted to the appropriate Permit Administrator at the
Regional Office. The Department may grant additional time upon
demonstration, to the satisfaction of the Department, that additional time to
apply for an alternative authorization is necessary or where the Department
has not provided a permit determination in accordance with Part 621 of this
Title.
2. When an individual SPDES permit is issued to a discharger authorized to
discharge under a general SPDES permit for the same discharge(s), the
general permit authorization for outfalls authorized under the individual
SPDES permit is automatically terminated on the effective date of the
individual permit unless termination is earlier in accordance with 6 NYCRR
Part 750.
L. Proper Operation and Maintenance
The owner or operator shall at all times properly operate and maintain all facilities and
systems of treatment and control (and related appurtenances) which are installed or
used by the owner or operator to achieve compliance with the conditions of this permit
and with the requirements of the SW PPP.
M. Inspection and Entry
The owner or operator shall allow an authorized representative of the Department,
EPA, applicable county health department, or, in the case of a construction site which
discharges through an MS4, an authorized representative of the MS4 receiving the
discharge, upon the presentation of credentials and other documents as may be
required by law, to:
1. Enter upon the owner’s or operator's premises where a regulated facility or
activity is located or conducted or where records must be k ept under the
conditions of this permit;
2. Have access to and copy at reasonable times, any records that must be kept
under the conditions of this permit; and
(Part VII.M.3)
37
3. Inspect at reasonable times any facilities or equipment (including monitoring
and control equipment), practices or operations regulated or required by this
permit.
4. Sample or monitor at reasonable times, for purposes of assuring permit
compliance or as otherwise authorized by the Act or ECL, any substances or
parameters at any location.
N. Permit Actions
This permit may, at any time, be modified, suspended, revoked, or renewed by the
Department in accordance with 6 NYCRR Part 621. The filing of a request by the
owner or operator for a permit modification, revocation and reissuance, termination, a
notification of planned changes or anticipated noncompliance does not limit, diminish
and/or stay compliance with any terms of this permit.
O. Definitions
Definitions of key terms are included in Appendix A of this permit.
P. Re-Opener Clause
1. If there is evidence indicating potential or realized impacts on water quality
due to any stormwater discharge associated with construction activity covered
by this permit, the owner or operator of such discharge may be required to
obtain an individual permit or alternative general permit in accordance with
Part VII.K. of this permit or the permit may be modified to include different
limitations and/or requirements.
2. Any Department initiated permit modification, suspension or revocation will be
conducted in accordance with 6 NYCRR Part 621, 6 NYCRR 750 -1.18, and 6
NYCRR 750-1.20.
Q. Penalties for Falsification of Forms and Reports
In accordance with 6NYCRR Part 750-2.4 and 750-2.5, any person who knowingly
makes any false material statement, representation, or certification in any application,
record, report or other document filed or required to be maintained under this permit,
including reports of compliance or noncompliance shall, upon conviction, be punished
in accordance with ECL §71-1933 and or Articles 175 and 210 of the New York State
Penal Law.
(Part VII.R)
38
R. Other Permits
Nothing in this permit relieves the owner or operator from a requirement to obtain any
other permits required by law.
39
APPENDIX A – Acronyms and Definitions
Acronyms
APO – Agency Preservation Officer
BMP – Best Management Practice
CPESC – Certified Professional in Erosion and Sediment Control
Cpv – Channel Protection Volume
CWA – Clean Water Act (or the Federal Water Pollution Control Act, 33 U.S.C. §1251 et
seq)
DOW – Division of Water
EAF – Environmental Assessment Form
ECL - Environmental Conservation Law
EPA – U. S. Environmental Protection Agency
HSG – Hydrologic Soil Group
MS4 – Municipal Separate Storm Sewer System
NOI – Notice of Intent
NOT – Notice of Termination
NPDES – National Pollutant Discharge Elimination System
OPRHP – Office of Parks, Recreation and Historic Places
Qf – Extreme Flood
Qp – Overbank Flood
RRv – Runoff Reduction Volume
RWE – Regional Water Engineer
SEQR – State Environmental Quality Review
SEQRA - State Environmental Quality Review Act
SHPA – State Historic Preservation Act
SPDES – State Pollutant Discharge Elimination System
SWPPP – Stormwater Pollution Prevention Plan
TMDL – Total Maximum Daily Load
UPA – Uniform Procedures Act
USDA – United States Department of Agriculture
WQv – Water Quality Volume
Appendix A
40
Definitions
All definitions in this section are solely for the purposes of this permit.
Agricultural Building – a structure designed and constructed to house farm
implements, hay, grain, poultry, livestock or other horticultural products; excluding any
structure designed, constructed or used, in whole or in part, for human habitation, as a
place of employment where agricultural products are processed, treated or packaged,
or as a place used by the public.
Agricultural Property –means the land for construction of a barn, agricultural building,
silo, stockyard, pen or other structural practices identified in Table II in the “Agricultural
Management Practices Catalog for Nonpoint Source Pollution in New York State”
prepared by the Department in cooperation with agencies of New York Nonpoint Source
Coordinating Committee (dated June 2007).
Alter Hydrology from Pre to Post-Development Conditions - means the post-
development peak flow rate(s) has increased by more than 5% of the pre-developed
condition for the design storm of interest (e.g. 10 yr and 100 yr).
Combined Sewer - means a sewer that is designed to collect and convey both
“sewage” and “stormwater”.
Commence (Commencement of) Construction Activities - means the initial
disturbance of soils associated with clearing, grading or excavation activit ies; or other
construction related activities that disturb or expose soils such as demolition, stockpiling
of fill material, and the initial installation of erosion and sediment control practices
required in the SWPPP. See definition for “Construction Activity(ies)” also.
Construction Activity(ies) - means any clearing, grading, excavation, filling, demolition
or stockpiling activities that result in soil disturbance. Clearing activities can include, but
are not limited to, logging equipment operation, the cutting and skidding of trees, stump
removal and/or brush root removal. Construction activity does not include routine
maintenance that is performed to maintain the original line and grade, hydraulic
capacity, or original purpose of a facility.
Construction Site – means the land area where construction activity(ies) will occur.
See definition for “Commence (Commencement of) Construction Activities” and “Larger
Common Plan of Development or Sale” also.
Dewatering – means the act of draining rainwater and/or groundwater from building
foundations, vaults or excavations/trenches.
Direct Discharge (to a specific surface waterbody) - means that runoff flows from a
construction site by overland flow and the first point of discharge is the specific surface
waterbody, or runoff flows from a construction site to a separate storm sewer system
Appendix A
41
and the first point of discharge from the separate storm sewer system is the specific
surface waterbody.
Discharge(s) - means any addition of any pollutant to waters of the State through an
outlet or point source.
Embankment –means an earthen or rock slope that supports a road/highway.
Endangered or Threatened Species – see 6 NYCRR Part 182 of the Department’s
rules and regulations for definition of terms and requirements.
Environmental Conservation Law (ECL) - means chapter 43-B of the Consolidated
Laws of the State of New York, entitled the Environmental Conservation Law.
Equivalent (Equivalence) – means that the practice or measure meets all the
performance, longevity, maintenance, and safety objectives of the technical standard
and will provide an equal or greater degree of water quality protection.
Final Stabilization - means that all soil disturbance activities have ceased and a
uniform, perennial vegetative cover with a density of eighty (80) percent over the entire
pervious surface has been established; or other equivalent stabilization measures, such
as permanent landscape mulches, rock rip-rap or washed/crushed stone have been
applied on all disturbed areas that are not covered by permanent structures, concrete or
pavement.
General SPDES permit - means a SPDES permit issued pursuant to 6 NYCRR Part
750-1.21 and Section 70-0117 of the ECL authorizing a category of discharges.
Groundwater(s) - means waters in the saturated zone. The saturated zone is a
subsurface zone in which all the interstices are filled with water under pressure greater
than that of the atmosphere. Although the zone may contain gas-filled interstices or
interstices filled with fluids other than water, it is still considered saturated.
Historic Property – means any building, structure, site, object or district that is listed on
the State or National Registers of Historic Places or is determined to be eligible for
listing on the State or National Registers of Historic Places.
Impervious Area (Cover) - means all impermeable surfaces that cannot effectively
infiltrate rainfall. This includes paved, concrete and gravel surfaces (i.e. parking lots,
driveways, roads, runways and sidewalks); building rooftops and miscellaneous
impermeable structures such as patios, pools, and sheds.
Infeasible – means not technologically possible, or not economically practicable and
achievable in light of best industry practices.
Appendix A
42
Larger Common Plan of Development or Sale - means a contiguous area where
multiple separate and distinct construction activities are occurring, or will occur, under
one plan. The term “plan” in “larger common plan of development or sale” is broadly
defined as any announcement or piece of documentation (including a sign, public notice
or hearing, marketing plan, advertisement, drawing, permit application, State
Environmental Quality Review Act (SEQRA) environmental assessment form or other
documents, zoning request, computer design, etc.) or physical demarcation (including
boundary signs, lot stakes, surveyor markings, etc.) indicating that construction
activities may occur on a specific plot.
For discrete construction projects that are located within a larger common plan of
development or sale that are at least 1/4 mile apart, each project can be treated as a
separate plan of development or sale provided any interconnecting road, pipeline or
utility project that is part of the same “common plan” is not concurrently being disturbed.
Minimize – means reduce and/or eliminate to the extent achievable using control
measures (including best management practices) that are technologically available and
economically practicable and achievable in light of best industry practices.
Municipal Separate Storm Sewer (MS4) - a conveyance or system of conveyances
(including roads with drainage systems, municipal streets, catch basins, curbs, gutters,
ditches, man-made channels, or storm drains):
(i) Owned or operated by a State, city, town, borough, county, parish, district,
association, or other public body (created by or pursuant to State law) having
jurisdiction over disposal of sewage, industrial wastes, stormwater, or other
wastes, including special districts under State law such as a sewer district,
flood control district or drainage district, or similar entity, or an Indian tribe or
an authorized Indian tribal organization, or a designated and approved
management agency under section 208 of the CWA that discharges to
surface waters of the State;
(ii) Designed or used for collecting or conveying stormwater;
(iii) Which is not a combined sewer; and
(iv) Which is not part of a Publicly Owned Treatment Works (POTW) as defined
at 40 CFR 122.2.
National Pollutant Discharge Elimination System (NPDES) - means the national
system for the issuance of wastewater and stormwater permits under the Federal Water
Pollution Control Act (Clean Water Act).
Natural Buffer –means an undisturbed area with natural cover running along a surface
water (e.g. wetland, stream, river, lake, etc.).
New Development – means any land disturbance that does not meet the definition of
Redevelopment Activity included in this appendix.
Appendix A
43
New York State Erosion and Sediment Control Certificate Program – a certificate
program that establishes and maintains a process to identify and recognize individuals
who are capable of developing, designing, inspecting and maintaining erosion and
sediment control plans on projects that disturb soils in New York State. The certificate
program is administered by the New York State Conservation District Employees
Association.
NOI Acknowledgment Letter - means the letter that the Department sends to an
owner or operator to acknowledge the Department’s receipt and acceptance of a
complete Notice of Intent. This letter documents the owner’s or operator’s authorization
to discharge in accordance with the general permit for stormwater discharges from
construction activity.
Nonpoint Source - means any source of water pollution or pollutants which is not a
discrete conveyance or point source permitted pursuant to Title 7 or 8 of Article 17 of
the Environmental Conservation Law (see ECL Section 17-1403).
Overbank –means flow events that exceed the capacity of the stream channel and spill
out into the adjacent floodplain.
Owner or Operator - means the person, persons or legal entity which owns or leases
the property on which the construction activity is occurring; an entity that has
operational control over the construction plans and specifications, including the ability to
make modifications to the plans and specifications; and/or an entity that has day-to-day
operational control of those activities at a project that are necessary to ensure
compliance with the permit conditions.
Performance Criteria – means the design criteria listed under the “Required Elements”
sections in Chapters 5, 6 and 10 of the technical standard, New York State Stormwater
Management Design Manual, dated January 2015. It does not include the Sizing
Criteria (i.e. WQv, RRv, Cpv, Qp and Qf ) in Part I.C.2. of the permit.
Point Source - means any discernible, confined and discrete conveyance, including but
not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container,
rolling stock, concentrated animal feeding operation, vessel or other floating craft, or
landfill leachate collection system from which pollutants are or may be discharged.
Pollutant - means dredged spoil, filter backwash, solid waste, incinerator residue,
sewage, garbage, sewage sludge, munitions, chemical wastes, biological materials,
radioactive materials, heat, wrecked or discarded equipment, rock, sand and industrial,
municipal, agricultural waste and ballast discharged into water; which may cause or
might reasonably be expected to cause pollution of the waters of the state in
contravention of the standards or guidance values adopted as provided in 6 NYCRR
Parts 700 et seq .
Appendix A
44
Qualified Inspector - means a person that is knowledgeable in the principles and
practices of erosion and sediment control, such as a licensed Professional Engineer,
Certified Professional in Erosion and Sediment Control (CPESC), Registered
Landscape Architect, New York State Erosion and Sediment Control Certificate
Program holder or other Department endorsed individual(s).
It can also mean someone working under the direct supervision of, and at the same
company as, the licensed Professional Engineer or Registered Landscape Architect,
provided that person has training in the principles and practices of erosion and sediment
control. Training in the principles and practices of erosion and sediment control means
that the individual working under the direct supervision of the licensed Professional
Engineer or Registered Landscape Architect has received four (4) hours of Department
endorsed training in proper erosion and sediment control principles from a Soil and
Water Conservation District, or other Department en dorsed entity. After receiving the
initial training, the individual working under the direct supervision of the licensed
Professional Engineer or Registered Landscape Architect shall receive four (4) hours of
training every three (3) years.
It can also mean a person that meets the Qualified Professional qualifications in
addition to the Qualified Inspector qualifications.
Note: Inspections of any post-construction stormwater management practices that
include structural components, such as a dam for an impoundment, shall be performed
by a licensed Professional Engineer.
Qualified Professional - means a person that is knowledgeable in the principles and
practices of stormwater management and treatment, such as a licensed Professional
Engineer, Registered Landscape Architect or other Department endorsed individual(s).
Individuals preparing SWPPPs that require the post-construction stormwater
management practice component must have an understanding of the principles of
hydrology, water quality management practice design, water quantity control design,
and, in many cases, the principles of hydraulics. All components of the SWPPP that
involve the practice of engineering, as defined by the NYS Education Law (see Article
145), shall be prepared by, or under the direct supervision of, a professional engineer
licensed to practice in the State of New York.
Redevelopment Activity(ies) – means the disturbance and reconstruction of existing
impervious area, including impervious areas that were removed from a project site within
five (5) years of preliminary project plan submission to the local government (i.e. site plan,
subdivision, etc.).
Regulated, Traditional Land Use Control MS4 - means a city, town or village with
land use control authority that is authorized to discharge under New York State DEC’s
Appendix A
45
SPDES General Permit For Stormwater Discharges from Municipal Separate
Stormwater Sewer Systems (MS4s) or the City of New York’s Individual SPDES Permit
for their Municipal Separate Storm Sewer Systems (NY-0287890).
Routine Maintenance Activity - means construction activity that is performed to
maintain the original line and grade, hydraulic capacity, or original purpose of a facility,
including, but not limited to:
▪ Re-grading of gravel roads or parking lots,
▪ Cleaning and shaping of existing roadside ditches and culverts that maintains
the approximate original line and grade, and hydraulic capacity of the ditch,
▪ Cleaning and shaping of existing roadside ditches that does not maintain the
approximate original grade, hydraulic capacity and purpose of the ditch if the
changes to the line and grade, hydraulic capacity or purpose of the ditch are
installed to improve water quality and quantity controls (e.g. installing grass
lined ditch),
▪ Placement of aggregate shoulder backing that stabilizes the transition between
the road shoulder and the ditch or embankment,
▪ Full depth milling and filling of existing asphalt pavements, replacement of
concrete pavement slabs, and similar work that does not expose soil or disturb
the bottom six (6) inches of subbase material,
▪ Long-term use of equipment storage areas at or near highway maintenance
facilities,
▪ Removal of sediment from the edge of the highway to restore a previously
existing sheet-flow drainage connection from the highway surface to the
highway ditch or embankment,
▪ Existing use of Canal Corp owned upland disposal sites for the canal, and
▪ Replacement of curbs, gutters, sidewalks and guide rail posts.
Site limitations – means site conditions that prevent the use of an infiltration technique
and or infiltration of the total WQv. Typical site limitations include: seasonal high
groundwater, shallow depth to bedrock, and soils with an infiltration rate less than 0.5
inches/hour. The existence of site limitations shall be confirmed and documented using
actual field testing (i.e. test pits, soil borings, and infiltration test) or using information
from the most current United States Department of Agriculture (USDA) Soil Survey for
the County where the project is located.
Sizing Criteria – means the criteria included in Part I.C.2 of the permit that are used to
size post-construction stormwater management control practices. The criteria include;
Water Quality Volume (WQv), Runoff Reduction Volume (RRv), Channel Protection
Volume (Cpv), Overbank Flood (Qp), and Extreme Flood (Qf).
State Pollutant Discharge Elimination System (SPDES) - means the system
established pursuant to Article 17 of the ECL and 6 NYCRR Part 750 for issuance of
permits authorizing discharges to the waters of the state.
Appendix A
46
Steep Slope – means land area designated on the current United States Department of
Agriculture (“USDA”) Soil Survey as Soil Slope Phase “D”, (provided the map unit name
is inclusive of slopes greater than 25%) , or Soil Slope Phase E or F, (regardless of the
map unit name), or a combination of the three designations.
Streambank – as used in this permit, means the terrain alongside the bed of a creek or
stream. The bank consists of the sides of the channel, between which the flow is confined.
Stormwater Pollution Prevention Plan (SWPPP) – means a project specific report,
including construction drawings, that among other things: describes the construction
activity(ies), identifies the potential sources of pollution at the construction site; describes
and shows the stormwater controls that will be used to control the pollutants (i.e. erosion
and sediment controls; for many projects, includes post-construction stormwater
management controls); and identifies procedures the owner or operator will implement to
comply with the terms and conditions of the permit. See Part III of the permit for a
complete description of the information that must be included in the SWPPP.
Surface Waters of the State - shall be construed to include lakes, bays, sounds,
ponds, impounding reservoirs, springs, rivers, streams, creeks, estuaries, marshes,
inlets, canals, the Atlantic ocean within the territorial seas of the state of New York and
all other bodies of surface water, natural or artificial, inland or coastal, fresh or salt,
public or private (except those private waters that do not combine or effect a junction
with natural surface waters), which are wholly or partially within or bordering the state
or within its jurisdiction. Waters of the state are further defined in 6 NYCRR Parts 800 to
941.
Temporarily Ceased – means that an existing disturbed area will not be disturbed
again within 14 calendar days of the previous soil disturbance.
Temporary Stabilization - means that exposed soil has been covered with material(s)
as set forth in the technical standard, New York Standards and Specifications for
Erosion and Sediment Control, to prevent the exposed soil from eroding. The materials
can include, but are not limited to, mulch, seed and mulch, and erosion control mats
(e.g. jute twisted yarn, excelsior wood fiber mats).
Total Maximum Daily Loads (TMDLs) - A TMDL is the sum of the allowable loads of a
single pollutant from all contributing point and nonpoint sources. It is a calculation of the
maximum amount of a pollutant that a waterbody can receive on a daily basis and still
meet water quality standards, and an allocation of that amount to the pollutant's
sources. A TMDL stipulates wasteload allocations (WLAs) for point source discharges,
load allocations (LAs) for nonpoint sources, and a margin of safety (MOS).
Trained Contractor - means an employee from the contracting (construction) company,
identified in Part III.A.6., that has received four (4) hours of Department endorsed
Appendix A
47
training in proper erosion and sediment control principles from a Soil and Water
Conservation District, or other Department endorsed entity. After receiving the initial
training, the trained contractor shall receive four (4) hours of training every three (3)
years.
It can also mean an employee from the contracting (construction) company, identified in
Part III.A.6., that meets the qualified inspector qualifications (e.g. licensed Professional
Engineer, Certified Professional in Erosion and Sediment Control (CPESC), Registered
Landscape Architect, New York State Erosion and Sediment Control Certificate
Program holder, or someone working under the direct supervision of, and at the same
company as, the licensed Professional Engineer or Registered Landscape Architect,
provided they have received four (4) hours of Department endorsed training in proper
erosion and sediment control principles from a Soil and Water Conservation District, or
other Department endorsed entity).
The trained contractor is responsible for the day to day implementation of the SWPPP.
Uniform Procedures Act (UPA) Permit - means a permit required under 6 NYCRR
Part 621 of the Environmental Conservation Law (ECL), Article 70.
Water Quality Standard - means such measures of purity or quality for any waters in
relation to their reasonable and necessary use as promulgated in 6 NYCRR Part 700 et
seq.
48
APPENDIX B – Required SWPPP Components by Project Type
Table 1
Construction Activities that Require the Preparation of a SWPPP That Only
Includes Erosion and Sediment Controls
The following construction activities that involve soil disturbances of one (1) or more acres of
land, but less than five (5) acres:
• Single family home not located in one of the watersheds listed in Appendix C or not directly
discharging to one of the 303(d) segments listed in Appendix E
• Single family residential subdivisions with 25% or less impervious cover at total site build-out and
not located in one of the watersheds listed in Appendix C and not directly discharging to one of the
303(d) segments listed in Appendix E
• Construction of a barn or other agricultural building, silo, stock yard or pen.
The following construction activities that involve soil disturbances between five thousand (5000)
square feet and one (1) acre of land:
All construction activities located in the watersheds identified in Appendix D that involve soil
disturbances between five thousand (5,000) square feet and one (1) acre of land.
The following construction activities that involve soil disturbances of one (1) or more acres of
land:
• Installation of underground, linear utilities; such as gas lines, fiber -optic cable, cable TV,
electric, telephone, sewer mains, and water mains
• Environmental enhancement projects, such as wetland mitigation projects, stormwater retrofits and
stream restoration projects
• Pond construction
• Linear bike paths running through areas with vegetative cover, including bike paths surfaced with an
impervious cover
• Cross-country ski trails and walking/hiking trails
• Sidewalk, bike path or walking path projects, surfaced with an impervious cover, that are not part of
residential, commercial or institutional development;
• Sidewalk, bike path or walking path projects, surfaced with an impervious cover, that include
incidental shoulder or curb work along an existing highway to support construction of the sidewalk,
bike path or walking path.
• Slope stabilization projects
• Slope flattening that changes the grade of the site, but does not significantly change the runoff
characteristics
Appendix B
49
Table 1 (Continued) CONSTRUCTION ACTIVITIES THAT REQUIRE THE PREPARATION OF A
SWPPP
THAT ONLY INCLUDES EROSION AND SEDIMENT CONTROLS
The following construction activities that involve soil disturbances of one (1) or more acres of
land:
• Spoil areas that will be covered with vegetation
• Vegetated open space projects (i.e. recreational parks, lawns, meadows, fields, downhill ski trails)
excluding projects that alter hydrology from pre to post development conditions,
• Athletic fields (natural grass) that do not include the construction or reconstruction of impervious
area and do not alter hydrology from pre to post development conditions
• Demolition project where vegetation will be established, and no redevelopment is planned
• Overhead electric transmission line project that does not include the construction of permanent
access roads or parking areas surfaced with impervious cover
• Structural practices as identified in Table II in the “Agricultural Management Practices Catalog f or
Nonpoint Source Pollution in New York State”, excluding projects that involve soil disturbances of
greater than five acres and construction activities that include the construction or reconstruction of
impervious area
• Temporary access roads, median crossovers, detour roads, lanes, or other temporary impervious
areas that will be restored to pre-construction conditions once the construction activit y is complete
Appendix B
50
Table 2
CONSTRUCTION ACTIVITIES THAT REQUIRE THE PREPARATION OF A SWPPP THAT INCLUDES
POST-CONSTRUCTION STORMWATER MANAGEMENT PRACTICES
The following construction activities that involve soil disturbances of one (1) or more acres of
land:
• Single family home located in one of the watersheds listed in Appendix C or directly discharging to
one of the 303(d) segments listed in Appendix E
• Single family home that disturbs five (5) or more acres of land
• Single family residential subdivisions located in one of the watersheds listed in Appendix C or
directly discharging to one of the 303(d) segments listed in Appendix E
• Single family residential subdivisions that involve soil disturbances of between one (1) and five (5)
acres of land with greater than 25% impervious cover at total site build-out
• Single family residential subdivisions that involve soil disturbances of five (5) or more acres of land,
and single family residential subdivisions that involve soil disturbances of less than five (5) acres
that are part of a larger common plan of development or sale that will ultimately disturb five or more
acres of land
• Multi-family residential developments; includes duplexes, townhomes, condominiums, senior
housing complexes, apartment complexes, and mobile home parks
• Airports
• Amusement parks
• Breweries, cideries, and wineries, including establishments constructed on agricultural land
• Campgrounds
• Cemeteries that include the construction or reconstruction of impervious area (>5% of disturbed
area) or alter the hydrology from pre to post development conditions
• Commercial developments
• Churches and other places of worship
• Construction of a barn or other agricultural building (e.g. silo) and structural practices as identified in
Table II in the “Agricultural Management Practices Catalog for Nonpoint Source Pollution in New
York State” that include the construction or reconstruction of impervious area, excluding projects
that involve soil disturbances of less than five acres.
• Golf courses
• Institutional development; includes hospitals, prisons, schools and colleges
• Industrial facilities; includes industrial parks
• Landfills
• Municipal facilities; includes highway garages, transfer stations, office buildings, POTW’s, water
treatment plants, and water storage tanks
• Office complexes
• Playgrounds that include the construction or reconstruction of impervious area
• Sports complexes
• Racetracks; includes racetracks with earthen (dirt) surface
• Road construction or reconstruction, including roads constructed as part of the construction
activities listed in Table 1
Appendix B
51
Table 2 (Continued)
CONSTRUCTION ACTIVITIES THAT REQUIRE THE PREPARATION OF A SWPPP THAT INCLUDES
POST-CONSTRUCTION STORMWATER MANAGEMENT PRACTICES
The following construction activities that involve soil disturbances of one (1) or more acres of
land:
• Parking lot construction or reconstruction, including parking lots constructed as part of the
construction activities listed in Table 1
• Athletic fields (natural grass) that include the construction or reconstruction of impervious area (>5%
of disturbed area) or alter the hydrology from pre to post development conditions
• Athletic fields with artificial turf
• Permanent access roads, parking areas, substations, compressor stations and well drilling pads,
surfaced with impervious cover, and constructed as part of an over-head electric transmission line
project, wind-power project, cell tower project, oil or gas well drilling project, sewer or water main
project or other linear utility project
• Sidewalk, bike path or walking path projects, surfaced with an impervious cover, that are part of a
residential, commercial or institutional development
• Sidewalk, bike path or walking path projects, surfaced with an impervious cover, that are part of a
highway construction or reconstruction project
• All other construction activities that include the construction or reconstruction of impervious area or
alter the hydrology from pre to post development conditions, and are not listed in Table 1
52
APPENDIX C – Watersheds Requiring Enhanced Phosphorus Removal
Watersheds where owners or operators of construction activities identified in
Table 2 of Appendix B must prepare a SWPPP that includes post-construction
stormwater management practices designed in conformance with the Enhanced
Phosphorus Removal Standards included in the technical standard, New York
State Stormwater Management Design Manual (“Design Manual”).
• Entire New York City Watershed located east of the Hudson River - Figure 1
• Onondaga Lake Watershed - Figure 2
• Greenwood Lake Watershed -Figure 3
• Oscawana Lake Watershed – Figure 4
• Kinderhook Lake Watershed – Figure 5
Appendix C
53
Figure 1 - New York City Watershed East of the Hudson
Appendix C
54
Figure 2 - Onondaga Lake Watershed
Appendix C
55
Figure 3 - Greenwood Lake Watershed
Appendix C
56
Figure 4 - Oscawana Lake Watershed
Appendix C
57
Figure 5 - Kinderhook Lake Watershed
58
APPENDIX D – Watersheds with Lower Disturbance Threshold
Watersheds where owners or operators of construction activities that involve soil
disturbances between five thousand (5000) square feet and one (1) acre of land
must obtain coverage under this permit.
Entire New York City Watershed that is located east of the Hudson River - See Figure
1 in Appendix C
59
APPENDIX E – 303(d) Segments Impaired by Construction Related Pollutant(s)
List of 303(d) segments impaired by pollutants related to construction activity (e.g. silt, sediment
or nutrients). The list was developed using ”The Final New York State 2016 Section 303(d) List
of Impaired Waters Requiring a TMDL/Other Strategy” dated November 2016. Owners or
operators of single family home and single family residential subdivisions with 25% or less total
impervious cover at total site build-out that involve soil disturbances of one or more acres of
land, but less than 5 acres, and directly discharge to one of the listed segments below shall
prepare a SWPPP that includes post-construction stormwater management practices designed
in conformance with the New York State Stormwater Management Design Manual (“Design
Manual”), dated January 2015.
COUNTY WATERBODY POLLUTANT
Albany Ann Lee (Shakers) Pond, Stump Pond Nutrients
Albany Basic Creek Reservoir Nutrients
Allegany Amity Lake, Saunders Pond Nutrients
Bronx Long Island Sound, Bronx Nutrients
Bronx Van Cortlandt Lake Nutrients
Broome Fly Pond, Deer Lake, Sky Lake Nutrients
Broome Minor Tribs to Lower Susquehanna (north) Nutrients
Broome Whitney Point Lake/Reservoir Nutrients
Cattaraugus Allegheny River/Reservoir Nutrients
Cattaraugus Beaver (Alma) Lake Nutrients
Cattaraugus Case Lake Nutrients
Cattaraugus Linlyco/Club Pond Nutrients
Cayuga Duck Lake Nutrients
Cayuga Little Sodus Bay Nutrients
Chautauqua Bear Lake Nutrients
Chautauqua Chadakoin River and tribs Nutrients
Chautauqua Chautauqua Lake, North Nutrients
Chautauqua Chautauqua Lake, South Nutrients
Chautauqua Findley Lake Nutrients
Chautauqua Hulburt/Clymer Pond Nutrients
Clinton Great Chazy River, Lower, Main Stem Silt/Sediment
Clinton Lake Champlain, Main Lake, Middle Nutrients
Clinton Lake Champlain, Main Lake, North Nutrients
Columbia Kinderhook Lake Nutrients
Columbia Robinson Pond Nutrients
Cortland Dean Pond Nutrients
303(d) Segments Impaired by Construction Related Pollutant(s)
60
Dutchess Fall Kill and tribs Nutrients
Dutchess Hillside Lake Nutrients
Dutchess Wappingers Lake Nutrients
Dutchess Wappingers Lake Silt/Sediment
Erie Beeman Creek and tribs Nutrients
Erie Ellicott Creek, Lower, and tribs Silt/Sediment
Erie Ellicott Creek, Lower, and tribs Nutrients
Erie Green Lake Nutrients
Erie Little Sister Creek, Lower, and tribs Nutrients
Erie Murder Creek, Lower, and tribs Nutrients
Erie Rush Creek and tribs Nutrients
Erie Scajaquada Creek, Lower, and tribs Nutrients
Erie Scajaquada Creek, Middle, and tribs Nutrients
Erie Scajaquada Creek, Upper, and tribs Nutrients
Erie South Branch Smoke Cr, Lower, and tribs Silt/Sediment
Erie South Branch Smoke Cr, Lower, and tribs Nutrients
Essex Lake Champlain, Main Lake, South Nutrients
Essex Lake Champlain, South Lake Nutrients
Essex Willsboro Bay Nutrients
Genesee Bigelow Creek and tribs Nutrients
Genesee Black Creek, Middle, and minor tribs Nutrients
Genesee Black Creek, Upper, and minor tribs Nutrients
Genesee Bowen Brook and tribs Nutrients
Genesee LeRoy Reservoir Nutrients
Genesee Oak Orchard Cr, Upper, and tribs Nutrients
Genesee Tonawanda Creek, Middle, Main Stem Nutrients
Greene Schoharie Reservoir Silt/Sediment
Greene Sleepy Hollow Lake Silt/Sediment
Herkimer Steele Creek tribs Silt/Sediment
Herkimer Steele Creek tribs Nutrients
Jefferson Moon Lake Nutrients
Kings Hendrix Creek Nutrients
Kings Prospect Park Lake Nutrients
Lewis Mill Creek/South Branch, and tribs Nutrients
Livingston Christie Creek and tribs Nutrients
Livingston Conesus Lake Nutrients
Livingston Mill Creek and minor tribs Silt/Sediment
Monroe Black Creek, Lower, and minor tribs Nutrients
Monroe Buck Pond Nutrients
Monroe Cranberry Pond Nutrients
303(d) Segments Impaired by Construction Related Pollutant(s)
61
Monroe Lake Ontario Shoreline, Western Nutrients
Monroe Long Pond Nutrients
Monroe Mill Creek and tribs Nutrients
Monroe Mill Creek/Blue Pond Outlet and tribs Nutrients
Monroe Minor Tribs to Irondequoit Bay Nutrients
Monroe Rochester Embayment - East Nutrients
Monroe Rochester Embayment - West Nutrients
Monroe Shipbuilders Creek and tribs Nutrients
Monroe Thomas Creek/White Brook and tribs Nutrients
Nassau Beaver Lake Nutrients
Nassau Camaans Pond Nutrients
Nassau East Meadow Brook, Upper, and tribs Silt/Sediment
Nassau East Rockaway Channel Nutrients
Nassau Grant Park Pond Nutrients
Nassau Hempstead Bay Nutrients
Nassau Hempstead Lake Nutrients
Nassau Hewlett Bay Nutrients
Nassau Hog Island Channel Nutrients
Nassau Long Island Sound, Nassau County Waters Nutrients
Nassau Massapequa Creek and tribs Nutrients
Nassau Milburn/Parsonage Creeks, Upp, and tribs Nutrients
Nassau Reynolds Channel, west Nutrients
Nassau Tidal Tribs to Hempstead Bay Nutrients
Nassau Tribs (fresh) to East Bay Nutrients
Nassau Tribs (fresh) to East Bay Silt/Sediment
Nassau Tribs to Smith/Halls Ponds Nutrients
Nassau Woodmere Channel Nutrients
New York Harlem Meer Nutrients
New York The Lake in Central Park Nutrients
Niagara Bergholtz Creek and tribs Nutrients
Niagara Hyde Park Lake Nutrients
Niagara Lake Ontario Shoreline, Western Nutrients
Niagara Lake Ontario Shoreline, Western Nutrients
Oneida Ballou, Nail Creeks and tribs Nutrients
Onondaga Harbor Brook, Lower, and tribs Nutrients
Onondaga Ley Creek and tribs Nutrients
Onondaga Minor Tribs to Onondaga Lake Nutrients
Onondaga Ninemile Creek, Lower, and tribs Nutrients
Onondaga Onondaga Creek, Lower, and tribs Nutrients
Onondaga Onondaga Creek, Middle, and tribs Nutrients
303(d) Segments Impaired by Construction Related Pollutant(s)
62
Onondaga Onondaga Lake, northern end Nutrients
Onondaga Onondaga Lake, southern end Nutrients
Ontario Great Brook and minor tribs Silt/Sediment
Ontario Great Brook and minor tribs Nutrients
Ontario Hemlock Lake Outlet and minor tribs Nutrients
Ontario Honeoye Lake Nutrients
Orange Greenwood Lake Nutrients
Orange Monhagen Brook and tribs Nutrients
Orange Orange Lake Nutrients
Orleans Lake Ontario Shoreline, Western Nutrients
Orleans Lake Ontario Shoreline, Western Nutrients
Oswego Lake Neatahwanta Nutrients
Oswego Pleasant Lake Nutrients
Putnam Bog Brook Reservoir Nutrients
Putnam Boyd Corners Reservoir Nutrients
Putnam Croton Falls Reservoir Nutrients
Putnam Diverting Reservoir Nutrients
Putnam East Branch Reservoir Nutrients
Putnam Lake Carmel Nutrients
Putnam Middle Branch Reservoir Nutrients
Putnam Oscawana Lake Nutrients
Putnam Palmer Lake Nutrients
Putnam West Branch Reservoir Nutrients
Queens Bergen Basin Nutrients
Queens Flushing Creek/Bay Nutrients
Queens Jamaica Bay, Eastern, and tribs (Queens) Nutrients
Queens Kissena Lake Nutrients
Queens Meadow Lake Nutrients
Queens Willow Lake Nutrients
Rensselaer Nassau Lake Nutrients
Rensselaer Snyders Lake Nutrients
Richmond Grasmere Lake/Bradys Pond Nutrients
Rockland Congers Lake, Swartout Lake Nutrients
Rockland Rockland Lake Nutrients
Saratoga Ballston Lake Nutrients
Saratoga Dwaas Kill and tribs Silt/Sediment
Saratoga Dwaas Kill and tribs Nutrients
Saratoga Lake Lonely Nutrients
Saratoga Round Lake Nutrients
Saratoga Tribs to Lake Lonely Nutrients
303(d) Segments Impaired by Construction Related Pollutant(s)
63
Schenectady Collins Lake Nutrients
Schenectady Duane Lake Nutrients
Schenectady Mariaville Lake Nutrients
Schoharie Engleville Pond Nutrients
Schoharie Summit Lake Nutrients
Seneca Reeder Creek and tribs Nutrients
St.Lawrence Black Lake Outlet/Black Lake Nutrients
St.Lawrence Fish Creek and minor tribs Nutrients
Steuben Smith Pond Nutrients
Suffolk Agawam Lake Nutrients
Suffolk Big/Little Fresh Ponds Nutrients
Suffolk Canaan Lake Silt/Sediment
Suffolk Canaan Lake Nutrients
Suffolk Flanders Bay, West/Lower Sawmill Creek Nutrients
Suffolk Fresh Pond Nutrients
Suffolk Great South Bay, East Nutrients
Suffolk Great South Bay, Middle Nutrients
Suffolk Great South Bay, West Nutrients
Suffolk Lake Ronkonkoma Nutrients
Suffolk Long Island Sound, Suffolk County, West Nutrients
Suffolk Mattituck (Marratooka) Pond Nutrients
Suffolk Meetinghouse/Terrys Creeks and tribs Nutrients
Suffolk Mill and Seven Ponds Nutrients
Suffolk Millers Pond Nutrients
Suffolk Moriches Bay, East Nutrients
Suffolk Moriches Bay, West Nutrients
Suffolk Peconic River, Lower, and tidal tribs Nutrients
Suffolk Quantuck Bay Nutrients
Suffolk Shinnecock Bay and Inlet Nutrients
Suffolk Tidal tribs to West Moriches Bay Nutrients
Sullivan Bodine, Montgomery Lakes Nutrients
Sullivan Davies Lake Nutrients
Sullivan Evens Lake Nutrients
Sullivan Pleasure Lake Nutrients
Tompkins Cayuga Lake, Southern End Nutrients
Tompkins Cayuga Lake, Southern End Silt/Sediment
Tompkins Owasco Inlet, Upper, and tribs Nutrients
Ulster Ashokan Reservoir Silt/Sediment
Ulster Esopus Creek, Upper, and minor tribs Silt/Sediment
Warren Hague Brook and tribs Silt/Sediment
303(d) Segments Impaired by Construction Related Pollutant(s)
64
Warren Huddle/Finkle Brooks and tribs Silt/Sediment
Warren Indian Brook and tribs Silt/Sediment
Warren Lake George Silt/Sediment
Warren Tribs to L.George, Village of L George Silt/Sediment
Washington Cossayuna Lake Nutrients
Washington Lake Champlain, South Bay Nutrients
Washington Tribs to L.George, East Shore Silt/Sediment
Washington Wood Cr/Champlain Canal and minor tribs Nutrients
Wayne Port Bay Nutrients
Westchester Amawalk Reservoir Nutrients
Westchester Blind Brook, Upper, and tribs Silt/Sediment
Westchester Cross River Reservoir Nutrients
Westchester Lake Katonah Nutrients
Westchester Lake Lincolndale Nutrients
Westchester Lake Meahagh Nutrients
Westchester Lake Mohegan Nutrients
Westchester Lake Shenorock Nutrients
Westchester Long Island Sound, Westchester (East) Nutrients
Westchester Mamaroneck River, Lower Silt/Sediment
Westchester Mamaroneck River, Upper, and minor tribs Silt/Sediment
Westchester Muscoot/Upper New Croton Reservoir Nutrients
Westchester New Croton Reservoir Nutrients
Westchester Peach Lake Nutrients
Westchester Reservoir No.1 (Lake Isle) Nutrients
Westchester Saw Mill River, Lower, and tribs Nutrients
Westchester Saw Mill River, Middle, and tribs Nutrients
Westchester Sheldrake River and tribs Silt/Sediment
Westchester Sheldrake River and tribs Nutrients
Westchester Silver Lake Nutrients
Westchester Teatown Lake Nutrients
Westchester Titicus Reservoir Nutrients
Westchester Truesdale Lake Nutrients
Westchester Wallace Pond Nutrients
Wyoming Java Lake Nutrients
Wyoming Silver Lake Nutrients
65
APPENDIX F – List of NYS DEC Regional Offices
Region COVERING THE
FOLLOWING COUNTIES:
DIVISION OF
ENVIRONMENTAL
PERMITS (DEP)
PERMIT ADMINISTRATORS
DIVISION OF WATER
(DOW)
WATER (SPDES) PROGRAM
1 NASSAU AND SUFFOLK
50 CIRCLE ROAD
STONY BROOK, NY 11790
TEL. (631) 444-0365
50 CIRCLE ROAD
STONY BROOK, NY 11790-3409
TEL. (631) 444-0405
2 BRONX, KINGS, NEW YORK,
QUEENS AND RICHMOND
1 HUNTERS POINT PLAZA,
47-40 21ST ST.
LONG ISLAND CITY, NY 11101-5407
TEL. (718) 482-4997
1 HUNTERS POINT PLAZA,
47-40 21ST ST.
LONG ISLAND CITY, NY 11101-5407
TEL. (718) 482-4933
3 DUTCHESS, ORANGE, PUTNAM,
ROCKLAND, SULLIVAN, ULSTER
AND WESTCHESTER
21 SOUTH PUTT CORNERS ROAD
NEW PALTZ, NY 12561-1696
TEL. (845) 256-3059
100 HILLSIDE AVENUE, SUITE 1W
WHITE PLAINS, NY 10603
TEL. (914) 428 - 2505
4
ALBANY, COLUMBIA,
DELAWARE, GREENE,
MONTGOMERY, OTSEGO,
RENSSELAER, SCHENECTADY
AND SCHOHARIE
1150 NORTH WESTCOTT ROAD
SCHENECTADY, NY 12306-2014
TEL. (518) 357-2069
1130 NORTH WESTCOTT ROAD
SCHENECTADY, NY 12306-2014
TEL. (518) 357-2045
5
CLINTON, ESSEX, FRANKLIN,
FULTON, HAMILTON,
SARATOGA, WARREN AND
WASHINGTON
1115 STATE ROUTE 86, PO BOX 296
RAY BROOK, NY 12977-0296
TEL. (518) 897-1234
232 GOLF COURSE ROAD
WARRENSBURG, NY 12885-1172 TEL.
(518) 623-1200
6 HERKIMER, JEFFERSON,
LEWIS, ONEIDA AND
ST. LAWRENCE
STATE OFFICE BUILDING
317 WASHINGTON STREET
WATERTOWN, NY 13601-3787
TEL. (315) 785-2245
STATE OFFICE BUILDING
207 GENESEE STREET
UTICA, NY 13501-2885 TEL. (315)
793-2554
7
BROOME, CAYUGA,
CHENANGO, CORTLAND,
MADISON, ONONDAGA,
OSWEGO, TIOGA AND
TOMPKINS
615 ERIE BLVD. WEST
SYRACUSE, NY 13204-2400
TEL. (315) 426-7438
615 ERIE BLVD. WEST
SYRACUSE, NY 13204-2400
TEL. (315) 426-7500
8
CHEMUNG, GENESEE,
LIVINGSTON, MONROE,
ONTARIO, ORLEANS,
SCHUYLER, SENECA,
STEUBEN, WAYNE AND
YATES
6274 EAST AVON-LIMA
ROADAVON, NY 14414-9519
TEL. (585) 226-2466
6274 EAST AVON-LIMA RD.
AVON, NY 14414-9519
TEL. (585) 226-2466
9
ALLEGANY,
CATTARAUGUS,
CHAUTAUQUA, ERIE,
NIAGARA AND WYOMING
270 MICHIGAN AVENUE
BUFFALO, NY 14203-2999
TEL. (716) 851-7165
270 MICHIGAN AVENUE
BUFFALO, NY 14203-2999
TEL. (716) 851-7070
B. NYSDEC NOTICE OF INTENT (NOI),
NOTICE OF TERMINATION AND
SWPPP ACCEPTANCE FORMS
NOI for coverage under Stormwater General
Permi t for Constructi on Acti vi ty
version 1.37
(Submission #: HPZ-BH6H-HY9YM, version 1)
Details
Originally Started By Bohler Engineering
Alternate Identifier Proposed Microproduction Brewery
Submission ID HPZ-BH6H-HY9YM
Submission Reason New
Status Draft
Form Input
Owner/Operator Information
Owner/Operator Name (Company/Private Owner/Municipality/Agency/Institution, etc.)
THBC NY, LLC
Owner/Operator Contact Person Last Name (NOT CONSULTANT)
Lanier
Owner/Operator Contact Person First Name
Nathan
Owner/Operator Mailing Address
129 Sturbridge ROad
City
Charlton
State
MA
Zip
01507
Phone
413-523-2367
Email
nate@treehousebrew.com
Federal Tax ID
N/A
If the owner/operator is an organization, provide the Federal Tax ID number, or Employer Identification Number (EIN), in the format xx-xxxxxxx. If
the owner/operator is an individual and not an organization, enter "Not Applicable" or "N/A" and do not provide the individual’s social security
number.
Project Location
Project/Site Name
Proposed Microproduction Brewery
Street Address (Not P.O. Box)
3376 South Broadway
East
City/Town/Village (THAT ISSUES BUILDING PERMIT)
Saratoga Springs
NY
Zip
12866
5
The DEC Region must be provided. Please use the NYSDEC Stormwater Interactive Map (https://gisservices.dec.ny.gov/gis/stormwater/) to
confirm which DEC Region this site is located in. To view the DEC Regions, click on “Other Useful Reference Layers” on the left side of the map,
then click on “DEC Administrative Boundary.” Zoom out as needed to see the Region boundaries.
For projects that span multiple Regions, please select a primary Region and then provide the additional Regions as a note in Question 39.
SARATOGA
Name of Nearest Cross Street
Crescent Ave
Distance to Nearest Cross Street (Feet)
1300
South
Tax Map Numbers Section-Block-Parcel
178.00-2-15
Tax Map Numbers
NONE PROVIDED
If the project does not have tax map numbers (e.g. linear projects), enter “Not Applicable” or "N/A".
1. Coordinates
Provide the Geographic Coordinates for the project site. The two methods are:
- Navigate to the project location on the map (below) and click to place a marker and obtain the XY coordinates.
- The "Find Me" button will provide the lat/long for the person filling out this form. Then pan the map to the correct location and click the map to
place a marker and obtain the XY coordinates.
Navigate to your location and click on the map to get the X,Y coordinates
43.0547105,-73.7879983
Project Details
Redevelopment with increase in impervious area
For the purposes of this eNOI, “New Construction” refers to any project that does not involve the disturbance of existing impervious area (i.e. 0
acres). If existing impervious area will be disturbed on the project site, it is considered redevelopment with either increase in impervious area or
no increase in impervious area.
3. Select the predominant land use for both pre and post development conditions.
Pasture/Open Land
Other: Brewery, Eating + Drinking establishment
3a. If Single Family Subdivision was selected in question 3, enter the number of subdivision lots.
NONE PROVIDED
Side of Street
State
DEC Region
County
Project In Relation to Cross Street
2. What is the nature of this project?
Pre-Development Existing Landuse
Post-Development Future Land Use
4. In accordance with the larger common plan of development or sale, enter the total project site acreage, the acreage to be disturbed and the
future impervious area (acreage)within the disturbed area.
*** ROUND TO THE NEAREST TENTH OF AN ACRE. ***
Total Site Area (acres)
10.7
Total Area to be Disturbed (acres)
11.1
Existing Impervious Area to be Disturbed (acres)
0.4
Future Impervious Area Within Disturbed Area (acres)
4.9
No
6. Indicate the percentage (%) of each Hydrologic Soil Group(HSG) at the site.
A (%)
100
B (%)
0
C (%)
0
D (%)
0
No
8. Enter the planned start and end dates of the disturbance activities.
Start Date
01/01/2024
End Date
06/30/2024
9. Identify the nearest surface waterbody(ies) to which construction site runoff w ill discharge.
Wetland
Drainage ditches and storm sewer systems are not considered surface waterbodies. Please identify the surface waterbody that they
discharge to. If the nearest surface waterbody is unnamed, provide a description of the waterbody, such as, “Unnamed tributary to Niagara River.”
Wetland/State Jurisdiction On Site (Answer 9b)
Other Waterbody Type Off Site Description
NONE PROVIDED
Delineated by Consultant
No
No
No
Please use the DEC Stormwater Interactive Map (https://gisservices.dec.ny.gov/gis/stormwater/) to confirm if this site is located in one of the
watersheds of an AA or AA-S classified water. To view the watershed areas, click on “Permit Related Layers” on the left side of the map, then
click on “Class AA AAS Watersheds.”
5. Do you plan to disturb more than 5 acres of soil at any one time?
7. Is this a phased project?
9a. Type of waterbody identified in question 9?
9b. If "wetland" was selected in 9A, how w as the w etland identified?
10. Has the surface waterbody(ies) in question 9 been identified as a 303(d) segment in Appendix E of GP-0-20-001?
11. Is this project located in one of the Watersheds identified in Appendix C of GP-0-20-001?
12. Is the project located in one of the watershed areas associated with AA and AA-S classified waters?
If No, skip question 13.
NONE PROVIDED
If Yes, what is the acreage to be disturbed?
NONE PROVIDED
No
No
16. What is the name of the municipality/entity that owns the separate storm sewer system?
NONE PROVIDED
No
No
No
No
Required SWPPP Components
Yes
Yes
If you answered No in question 22, skip question 23 and the Post-construction Criteria and Post-construction SMP Identification
sections.
Yes
Professional Engineer (P.E.)
SWPPP Preparer
Bohler Engineering and Landscape Architecture NY, LLC
Contact Name (Last, First)
Wilson, Steven
Mailing Address
17 Computer Drive West
City
Albany
State
NY
Zip
12205
Phone
518-438-9900
13. Does this construction activity disturb land with no existing impervious cover and where the Soil Slope Phase is identified as D
(provided the map unit name is inclusive of slopes greater than 25%), E or F on the USDA Soil Survey?
14. Will the project disturb soils within a State regulated wetland or the protected 100 foot adjacent area?
15. Does the site runoff enter a separate storm sew er system (including roadside drains, swales, ditches, culverts, etc)?
17. Does any runoff from the site enter a sewer classified as a Combined Sewer?
18. Will future use of this site be an agricultural property as defined by the NYS Agriculture and Markets Law?
19. Is this property owned by a state authority, state agency, federal government or local government?
20. Is this a remediation project being done under a Department approved w ork plan? (i.e. CERCLA, RCRA, Voluntary Cleanup
Agreement, etc.)
21. Has the required Erosion and Sediment Control component of the SWPPP been developed in conformance with the current NYS
Standards and Specifications for Erosion and Sediment Control (aka Blue Book)?
22. Does this construction activity require the development of a SWPPP that includes the post-construction stormwater
management practice component (i.e. Runoff Reduction, Water Quality and Quantity Control practices/techniques)?
23. Has the post-construction stormwater management practice component of the SWPPP been developed in conformance with the
current NYS Stormwater Management Design Manual?
24. The Stormwater Pollution Prevention Plan (SWPPP) was prepared by:
Email
steven.wilson@bohlereng.com
Download SWPPP Preparer Certification Form
Please take the following steps to prepare and upload your preparer certification form:
1) Click on the link below to download a blank certification form
2) The certified SWPPP preparer should sign this form
3) Scan the signed form
4) Upload the scanned document
Download SWPPP Preparer Certification Form
Please upload the SWPPP Preparer Certification
SWPPP Preparer Cert.pdf - 11/22/2023 01:43 PM
Comment
NONE PROVIDED
Erosion & Sediment Control Criteria
Yes
26. Select all of the erosion and sediment control practices that will be employed on the project site:
Sediment Basin
Silt Fence
Stabilized Construction Entrance
Temporary Swale
None
Seeding
Sodding
Topsoiling
Mulching
Land Grading
Other
NONE PROVIDED
Post-Construction Criteria
* IMPORTANT: Completion of Questions 27-39 is not required if response to Question 22 is No.
Preservation of Undisturbed Area
Reduction of Clearing and Grading
Locating Development in Less Sensitive Areas
Sidewalk Reduction
Driveway Reduction
Building Footprint Reduction
Parking Reduction
All disturbed areas will be restored in accordance with the Soil Restoration requirements in Table 5.3 of the Design Manual (see page 5-22).
28. Provide the total Water Quality Volume (WQv) required for this project (based on final site plan/layout). (Acre-feet)
0.426
29. Post-construction SMP Identification
Use the Post-construction SMP Identification section to identify the RR techniques (Area Reduction), RR techniques(Volume Reduction) and
Standard SMPs with RRv Capacity that were used to reduce the Total WQv Required (#28).
Identify the SMPs to be used by providing the total impervious area that contributes runoff to each technique/practice selected. For the Area
25. Has a construction sequence schedule for the planned management practices been prepared?
Temporary Structural
Biotechnical
Vegetative Measures
Permanent Structural
27. Identify all site planning practices that were used to prepare the final site plan/layout for the project.
27a. Indicate which of the following soil restoration criteria was used to address the requirements in Section 5.1.6("Soil
Restoration") of the Design Manual (2010 version).
Reduction Techniques, provide the total contributing area (includes pervious area) and, if applicable, the total impervious area that contributes
runoff to the technique/practice.
Note: Redevelopment projects shall use the Post-Construction SMP Identification section to identify the SMPs used to treat and/or reduce the
WQv required. If runoff reduction techniques will not be used to reduce the required WQv, skip to question 33a after identifying the SMPs.
30. Indicate the Total RRv provided by the RR techniques (Area/Volume Reduction) and Standard SMPs with RRv capacity identified
in question 29. (acre-feet)
0.426
Yes
If Yes, go to question 36. If No, go to question 32.
32. Provide the Minimum RRv required based on HSG. [Minimum RRv Required = (P) (0.95) (Ai) / 12, Ai=(s) (Aic)] (acre-feet)
0.225
Yes
If Yes, go to question 33.
Note: Use the space provided in question #39 to summarize the specific site limitations and justification for not reducing 100% of WQv required
(#28). A detailed evaluation of the specific site limitations and justification for not reducing 100% of the WQv required (#28) must also be included
in the SWPPP.
If No, sizing criteria has not been met; therefore, NOI can not be processed. SWPPP preparer must modify design to meet sizing criteria.
33. SMPs
Use the Post-construction SMP Identification section to identify the Standard SMPs and, if applicable, the Alternative SMPs to be used to treat
the remaining total WQv (=Total WQv Required in #28 - Total RRv Provided in #30).
Also, provide the total impervious area that contributes runoff to each practice selected.
NOTE: Use the Post-construction SMP Identification section to identify the SMPs used on Redevelopment projects.
33a. Indicate the Total WQv provided (i.e. WQv treated) by the SMPs identified in question #33 and Standard SMPs with RRv
Capacity identified in question #29. (acre-feet)
NONE PROVIDED
Note: For the standard SMPs with RRv capacity, the WQv provided by each practice = the WQv calculated using the contributing drainage area to
the practice - provided by the practice. (See Table 3.5 in Design Manual)
34. Provide the sum of the Total RRv provided (#30) and the WQv provided (#33a).
NONE PROVIDED
Yes
If Yes, go to question 36.
If No, sizing criteria has not been met; therefore, NOI can not be processed. SWPPP preparer must modify design to meet sizing criteria.
36. Provide the total Channel Protection Storage Volume (CPv required and provided or select waiver (#36a), if applicable.
CPv Required (acre-feet)
NONE PROVIDED
CPv Provided (acre-feet)
NONE PROVIDED
Reduction of the total CPv is achieved on site through runoff reduction techniques or infiltration systems.
37. Provide the Overbank Flood (Qp) and Extreme Flood (Qf) control criteria or select waiver (#37a), if applicable.
Overbank Flood Control Criteria (Qp)
Pre-Development (CFS)
0.49
Post-Development (CFS)
0.03
31. Is the Total RRv provided (#30) greater than or equal to the total WQv required (#28)?
32a. Is the Total RRv provided (#30) greater than or equal to the Minimum RRv Required (#32)?
35. Is the sum of the RRv provided (#30) and the WQv provided (#33a) greater than or equal to the total WQv required (#28)?
36a. The need to provide channel protection has been waived because:
Total Extreme Flood Control Criteria (Qf)
Pre-Development (CFS)
5.90
Post-Development (CFS)
2.80
NONE PROVIDED
Yes
If Yes, Identify the entity responsible for the long term Operation and Maintenance
THBC NY, LLC
39. Use this space to summariz e the specific site limitations and justification for not reducing 100% of WQv required (#28). (See
question #32a) This space can also be used for other pertinent project information.
NONE PROVIDED
Post-Construction SMP Identification
Runoff Reduction (RR) Techniques, Standard Stormwater Management Practices (SMPs) and Alternative SMPs
Identify the Post-construction SMPs to be used by providing the total impervious area that contributes runoff to each technique/practice selected.
For the Area Reduction Techniques, provide the total contributing area (includes pervious area) and, if applicable, the total impervious area that
contributes runoff to the technique/practice.
RR Techniques (Area Reduction)
Round to the nearest tenth
Total Contributing Acres for Conservation of Natural Area (RR-1)
NONE PROVIDED
Total Contributing Impervious Acres for Conservation of Natural Area (RR-1)
NONE PROVIDED
Total Contributing Acres for Sheetflow to Riparian Buffers/Filter Strips (RR-2)
NONE PROVIDED
Total Contributing Impervious Acres for Sheetflow to Riparian Buffers/Filter Strips (RR-2)
NONE PROVIDED
Total Contributing Acres for Tree Planting/Tree Pit (RR-3)
NONE PROVIDED
Total Contributing Impervious Acres for Tree Planting/Tree Pit (RR-3)
NONE PROVIDED
Total Contributing Acres for Disconnection of Rooftop Runoff (RR-4)
NONE PROVIDED
RR Techniques (Volume Reduction)
Total Contributing Impervious Acres for Disconnection of Rooftop Runoff (RR-4)
NONE PROVIDED
Total Contributing Impervious Acres for Vegetated Swale (RR-5)
NONE PROVIDED
Total Contributing Impervious Acres for Rain Garden (RR-6)
NONE PROVIDED
Total Contributing Impervious Acres for Stormwater Planter (RR-7)
NONE PROVIDED
Total Contributing Impervious Acres for Rain Barrel/Cistern (RR-8)
NONE PROVIDED
37a. The need to meet the Qp and Qf criteria has been waived because:
38. Has a long term Operation and Maintenance Plan for the post-construction stormwater management practice(s) been
developed?
Total Contributing Impervious Acres for Porous Pavement (RR-9)
1.82
Total Contributing Impervious Acres for Green Roof (RR-10)
NONE PROVIDED
Standard SMPs with RRv Capacity
Total Contributing Impervious Acres for Infiltration Trench (I-1)
NONE PROVIDED
Total Contributing Impervious Acres for Infiltration Basin (I-2)
2.65
Total Contributing Impervious Acres for Dry Well (I-3)
NONE PROVIDED
Total Contributing Impervious Acres for Underground Infiltration System (I-4)
NONE PROVIDED
Total Contributing Impervious Acres for Bioretention (F-5)
NONE PROVIDED
Total Contributing Impervious Acres for Dry Swale (O-1)
0.24
Standard SMPs
Total Contributing Impervious Acres for Micropool Extended Detention (P-1)
NONE PROVIDED
Total Contributing Impervious Acres for Wet Pond (P-2)
NONE PROVIDED
Total Contributing Impervious Acres for Wet Extended Detention (P-3)
NONE PROVIDED
Total Contributing Impervious Acres for Multiple Pond System (P-4)
NONE PROVIDED
Total Contributing Impervious Acres for Pocket Pond (P-5)
NONE PROVIDED
Total Contributing Impervious Acres for Surface Sand Filter (F-1)
NONE PROVIDED
Total Contributing Impervious Acres for Underground Sand Filter (F-2)
NONE PROVIDED
Total Contributing Impervious Acres for Perimeter Sand Filter (F-3)
NONE PROVIDED
Total Contributing Impervious Acres for Organic Filter (F-4)
NONE PROVIDED
Total Contributing Impervious Acres for Shallow Wetland (W-1)
NONE PROVIDED
Total Contributing Impervious Acres for Extended Detention Wetland (W-2)
NONE PROVIDED
Total Contributing Impervious Acres for Pond/Wetland System (W-3)
NONE PROVIDED
Total Contributing Impervious Acres for Pocket Wetland (W-4)
NONE PROVIDED
Total Contributing Impervious Acres for Wet Swale (O-2)
NONE PROVIDED
Alternative SMPs (DO NOT INCLUDE PRACTICES BEING USED FOR PRETREATMENT ONLY)
Total Contributing Impervious Area for Hydrodynamic
NONE PROVIDED
Total Contributing Impervious Area for Wet Vault
NONE PROVIDED
Total Contributing Impervious Area for Media Filter
NONE PROVIDED
"Other" Alternative SMP?
NONE PROVIDED
Total Contributing Impervious Area for "Other"
NONE PROVIDED
Provide the name and manufaturer of the alternative SMPs (i.e. proprietary practice(s)) being used for WQv treatment.
Note: Redevelopment projects which do not use RR techniques, shall use questions 28, 29, 33 and 33a to provide SMPs used, total
WQv required and total WQv provided for the project.
Manufacturer of Alternative SMP
NONE PROVIDED
Name of Alternative SMP
NONE PROVIDED
Other Permits
None
If SPDES Multi-Sector GP, then give permit ID
NONE PROVIDED
If Other, then identify
NONE PROVIDED
No
If "Yes," then indicate Siz e of Impact, in acres, to the nearest tenth
NONE PROVIDED
42. If this NOI is being submitted for the purpose of continuing or transferring coverage under a general permit for stormwater runoff
from construction activities, please indicate the former SPDES number assigned.
NONE PROVIDED
MS4 SWPPP Acceptance
Yes - Please attach the MS4 Acceptance form below
If No, skip question 44
NONE PROVIDED
MS4 SWPPP Acceptance Form Download
Download form from the link below. Complete, sign, and upload.
MS4 SWPPP Acceptance Form
MS4 Acceptance Form Upload
NONE PROVIDED
Comment
NONE PROVIDED
40. Identify other DEC permits, existing and new, that are required for this project/facility.
41. Does this project require a US Army Corps of Engineers Wetland Permit?
43. Is this project subject to the requirements of a regulated, traditional land use control MS4?
44. Has the "MS4 SWPPP Acceptance" form been signed by the principal executive officer or ranking elected official and submitted
along with this NOI?
Owner/Operator Certification
Owner/Operator Certification Form Download
Download the certification form by clicking the link below. Complete, sign, scan, and upload the form.
Owner/Operator Certification Form (PDF, 45KB)
Upload Owner/Operator Certification Form
NONE PROVIDED
Comment
NONE PROVIDED
Attachments
Date Attachment Name Context User
11/22/2023 1:43 PM SWPPP Preparer Cert.pdf Attachment Bohler Engineering
New York State Department of Environmental Conservation
Division of Water
625 Broadway, 4th Floor
Albany, New York 12233-3505
*(NOTE: Submit completed form to address above)*
NOTICE OF TERMINATION for Storm Water Discharges Authorized
under the SPDES General Permit for Construction Activity
Please indicate your permit identification number: NYR ___ ___ ___ ___ ___ ___
I. Owner or Operator Information
1. Owner/Operator Name:
2. Street Address:
3. City/State/Zip:
4. Contact Person:4a.Telephone:
4b. Contact Person E-Mail:
II. Project Site Information
5. Project/Site Name:
6. Street Address:
7. City/Zip:
8. County:
III. Reason for Termination
9a. □ All disturbed areas have achieved final stabilization in accordance with the general permit and
SWPPP. *Date final stabilization completed (month/year):
9b. □ Permit coverage has been transferred to new owner/operator. Indicate new owner/operator’s
permit identification number: NYR ___ ___ ___ ___ ___ ___
(Note: Permit coverage can not be terminated by owner identified in I.1. above until new
owner/operator obtains coverage under the general permit)
9c. □ Other (Explain on Page 2)
IV. Final Site Information:
10a. Did this construction activity require the development of a SWPPP that includes post-construction
stormwater management practices? □ yes □ no ( If no, go to question 10f.)
10b. Have all post-construction stormwater management practices included in the final SWPPP been
constructed?□yes □ no (If no, explain on Page 2)
10c. Identify the entity responsible for long-term operation and maintenance of practice(s)?
Page 1 of 3
NOTICE OF TERMINATION for Storm Water Discharges Authorized under the
SPDES General Permit for Construction Activity - continued
10d. Has the entity responsible for long-term operation and maintenance been given a copy of the
operation and maintenance plan required by the general permit? □ yes □no
10e. Indicate the method used to ensure long-term operation and maintenance of the post-construction
stormwater management practice(s):
□Post-construction stormwater management practice(s) and any right-of-way(s) needed to
maintain practice(s) have been deeded to the municipality.
□Executed maintenance agreement is in place with the municipality that will maintain the
post-construction stormwater management practice(s).
□For post-construction stormwater management practices that are privately owned, a mechanism
is in place that requires operation and maintenance of the practice(s) in accordance with the operation
and maintenance plan, such as a deed covenant in the owner or operator’s deed of record.
□For post-construction stormwater management practices that are owned by a public or private
institution (e.g. school, university or hospital), government agency or authority, or public utility; policy and
procedures are in place that ensures operation and maintenance of the practice(s) in accordance with the
operation and maintenance plan.
10f. Provide the total area of impervious surface (i.e. roof, pavement, concrete, gravel, etc.) constructed
within the disturbance area?
(acres)
11. Is this project subject to the requirements of a regulated, traditional land use control MS4? □ yes
□no
(If Yes, complete section VI - “MS4 Acceptance” statement
V. Additional Information/Explanation:
(Use this section to answer questions 9c. and 10b., if applicable)
VI. MS4 Acceptance - MS4 Official (principal executive officer or ranking elected official) or Duly
Authorized Representative (Note: Not required when 9b. is checked -transfer of coverage)
I have determined that it is acceptable for the owner or operator of the construction project identified in
question 5 to submit the Notice of Termination at this time.
Printed Name:
Title/Position:
Signature: Date:
Page 2 of 3
NOTICE OF TERMINATION for Storm Water Discharges Authorized under the
SPDES General Permit for Construction Activity - continued
VII. Qualified Inspector Certification - Final Stabilization:
I hereby certify that all disturbed areas have achieved final stabilization as defined in the current version
of the general permit, and that all temporary, structural erosion and sediment control measures have
been removed. Furthermore, I understand that certifying false, incorrect or inaccurate information is a
violation of the referenced permit and the laws of the State of New York and could subject me to
criminal, civil and/or administrative proceedings.
Printed Name:
Title/Position:
Signature: Date:
VIII.Qualified Inspector Certification - Post-construction Stormwater Management Practice(s):
I hereby certify that all post-construction stormwater management practices have been constructed in
conformance with the SWPPP. Furthermore, I understand that certifying false, incorrect or inaccurate
information is a violation of the referenced permit and the laws of the State of New York and could
subject me to criminal, civil and/or administrative proceedings.
Printed Name:
Title/Position:
Signature: Date:
IX. Owner or Operator Certification
I hereby certify that this document was prepared by me or under my direction or supervision. My
determination, based upon my inquiry of the person(s) who managed the construction activity, or those
persons directly responsible for gathering the information, is that the information provided in this
document is true, accurate and complete. Furthermore, I understand that certifying false, incorrect or
inaccurate information is a violation of the referenced permit and the laws of the State of New York and
could subject me to criminal, civil and/or administrative proceedings.
Printed Name:
Title/Position:
Signature: Date:
(NYS DEC Notice of Termination - January 2015)
Page 3 of 3
SWPPP Preparer Certification Form
SPDES General Permit for Stormwater
Discharges From Construction Activity
(GP-0-20-0 01)
Project Site Information
Project/Site Name
Owner/Operator Information
Owner/Operator (Company Name/Private Owner/Municipality Name)
Certification Statement – SWPPP Preparer
I hereby certify that the Stormwater Pollution Prevention Plan (SWPPP) for this
project has been prepared in accordance with the terms and conditions of the
GP-0-20-001. Furthermore, I understand that certifying false, incorrect or inaccurate
information is a violation of this permit and the laws of the State of New York and
could subject me to criminal, civil and/or administrative proceedings.
First name MI Last Name
Signature Date
Revised: January 2020
NYS Department of Environmental Conservation
Division of Water
625 Broadway, 4th Floor
Albany, New York 12233-3505
MS4 Stormwater Pollution Prevention Plan (SWPPP) Acceptance
Form
for
Construction Activities Seeking Authorization Under SPDES General Permit
*(NOTE: Attach Completed Form to Notice Of Intent and Submit to Address Above)
I. Project Owner/Operator Information
1. Owner/Operator Name:
2. Contact Person:
3. Street Address:
4. City/State/Zip:
II. Project Site Information
5. Project/Site Name:
6. Street Address:
7. City/State/Zip:
III. Stormwater Pollution Prevention Plan (SWPPP) Review and Acceptance Information
8. SWPPP Reviewed by:
9. Title/Position:
10. Date Final SWPPP Reviewed and Accepted:
IV. Regulated MS4 Information
11. Name of MS4:
12. MS4 SPDES Permit Identification Number: NYR20A
13. Contact Person:
14. Street Address:
15. City/State/Zip:
16. Telephone Number:
Page 1 of 2
MS4 SWPPP Acceptance Form -continued
V. Certification Statement -MS4 Official (principal executive officer or ranking elected official) or
Duly Authorized Representative
I hereby certify that the final Stormwater Pollution Prevention Plan (SWPPP) for the construction project
identified in question 5 has been reviewed and meets the substantive requirements in the SPDES
General Permit For Stormwater Discharges from Municipal Separate Storm Sewer Systems (MS4s).
Note: The MS4, through the acceptance of the SWPPP, assumes no responsibility for the accuracy and
adequacy of the design included in the SWPPP. In addition, review and acceptance of the SWPPP by
the MS4 does not relieve the owner/operator or their SWPPP preparer of responsibility or liability for
errors or omissions in the plan.
Printed Name:
Title/Position:
Signature:
Date:
VI. Additional Information
(NYS DEC -MS4 SWPPP Acceptance Form -January 2015)
Page 2 of 2
C. INSPECTION NOTES, CONSTRUCTION/
OPERATION AND MAINTENANCE /
INSPECTION REPORT FORMS,
INSPECTOR CERTIFICATION FORM,
INSPECTION LOG
INSPECTION NOTES:
THIS SECTION CONTAINS A GENERAL MAINTENANCE PLAN, INSPECTION
REPORT FORMS, MANUALS AND LOGS TO ASSIST THE INSPECTION, PROPER
INSTALLATION AND CONTINUED OPERATIONS AND MAINTENANCE OF THE SYSTEM
DURING CONSTRUCTI ON AND AFTER, FOR THE LIFETIME OF THE FACILITY. THE
INSPECTOR SHALL MEET THE REQUIREMENTS AS OUTLINED IN THE GENERAL PERMIT
AND SHALL BE FAMILIAR WITH THE COMPONENTS OF THE STORMWATER
MANAGEMENT SYSTEM.
THE INSPECTOR SHALL FOLLOW ALL DOCUMENTS INCLUDED IN THE SWPPP.
THE PROPER INSTALLATION AND PROTECTION OF STORMWATER MANAGEMENT
FACILITIES DURING CONSTRUCTION IS CRITICAL TO THE LONG TERM OPERATION OF
THIS SYSTEM. THE CONSTRUCTION SEQUENCING AND PLAN NOTES ON THE
EROSION AND SEDIMENT CONTROL PLAN MUST BE FOLLOWED WITH SPECIFIC
ATTENTION TO THE PROPER MARKING, PROTECTION AND INSTALLATION OF THE
STORM FACILITY.
STORMWATER FROM DISTURBED AREAS SHALL BE DIVERTED TO THE
TEMPORARY EROSION CONTOL MEASURES AS SHOWN ON THE EROSION AND
SEDIMENT CONTROL PLAN. THE STORMWATER SYSTEM SHALL NOT BE CONNECTED
TO THE STORM MANAGEMENT AREA OR ANY STORMWATER DIVERTED TO THE
SYSTEM UNTIL THE CONTRIBUTING AREAS HAVE BEEN COMPLETELY STABILIZED
AND INSPECTED BY THE TOWN STORMWATER COORDINATOR (IF APPLICABLE).
New York State Stormwater Management Design Manual Appendix F
F-12
Infiltration Basin Construction Inspection Checklist
Project:
Location:
Site Status:
Date:
Time:
Inspector:
CONSTRUCTION SEQUENCE
SATISFACTORY/
UNSATISFACTORY
COMMENTS
1. Pre-Construction Runoff diverted Soil permeability tested
Groundwater / bedrock depth
2. Excavation Size and location Side slopes stable
Excavation does not compact subsoils
3. Embankment Barrel Anti-seep collar or Filter diaphragm Fill material
New York State Stormwater Management Design Manual Appendix F
F-13
CONSTRUCTION SEQUENCE
SATISFACTORY/
UNSATISFACTORY
COMMENTS
4. Final Excavation Drainage area stabilized Sediment removed from facility Basin floor tilled Facility stabilized
5. Final Inspection Pretreatment facility in place Inlets / outlets Contributing watershed stabilized
before flow is routed to the factility
Comments:
Actions to be Taken:
New York State Stormwater Management Design Manual Appendix F
F-20
Open Channel System Construction Inspection Checklist
Project:
Location:
Site Status:
Date:
Time:
Inspector:
CONSTRUCTION SEQUENCE
SATISFACTORY /
UNSATISFACTORY
COMMENTS
1. Pre-Construction Pre-construction meeting Runoff diverted Facility location staked out
2. Excavation Size and location Side slope stable Soil permeability Groundwater / bedrock Lateral slopes completely level Longitudinal slopes within design
range
Excavation does not compact subsoils
3. Check dams Dimensions Spacing Materials
New York State Stormwater Management Design Manual Appendix F
F-21
CONSTRUCTION SEQUENCE
SATISFACTORY /
UNSATISFACTORY
COMMENTS
4. Structural Components
Underdrain installed correctly Inflow installed correctly Pretreatment devices installed
5. Vegetation Complies with planting specifications Topsoil adequate in composition and
placement
Adequate erosion control measures in
place
6. Final inspection Dimensions Check dams Proper outlet Effective stand of vegetation and
stabilization
Contributing watershed stabilized
before flow is routed to the factility
Comments:
New York State Stormwater Management Design Manual Appendix F
F-22
Actions to be Taken:
New York State Stormwater Management Design Manual Appendix G
G-6
Infiltration Trench Operation, Maintenance, and
Management Inspection Checklist
Project:
Location:
Site Status:
Date:
Time:
Inspector:
MAINTENANCE ITEM
SATISFACTORY /
UNSATISFACTORY
COMMENTS
1. Debris Cleanout (Monthly) Trench surface clear of debris Inflow pipes clear of debris Overflow spillway clear of debris Inlet area clear of debris
2. Sediment Traps or Forebays (Annual) Obviously trapping sediment Greater than 50% of storage volume
remaining
3. Dewatering (Monthly) Trench dewaters between storms
4. Sediment Cleanout of Trench (Annual) No evidence of sedimentation in
trench
Sediment accumulation doesn=t yet
require cleanout
5. Inlets (Annual)
New York State Stormwater Management Design Manual Appendix G
G-7
MAINTENANCE ITEM
SATISFACTORY /
UNSATISFACTORY
COMMENTS
Good condition No evidence of erosion
6. Outlet/Overflow Spillway (Annual) Good condition, no need for repair No evidence of erosion
7. Aggregate Repairs (Annual) Surface of aggregate clean Top layer of stone does not need
replacement
Trench does not need rehabilitation
Comments:
Actions to be Taken:
New York State Stormwater Management Design Manual Appendix G
G-13
Open Channel Operation, Maintenance, and
Management Inspection Checklist
Project:
Location:
Site Status:
Date:
Time:
Inspector:
MAINTENANCE ITEM
SATISFACTORY/
UNSATISFACTORY
COMMENTS
1. Debris Cleanout (Monthly) Contributing areas clean of debris
2. Check Dams or Energy Dissipators (Annual, After Major Storms) No evidence of flow going around
structures
No evidence of erosion at downstream
toe
Soil permeability Groundwater / bedrock
3. Vegetation (Monthly) Mowing done when needed Minimum mowing depth not exceeded No evidence of erosion Fertilized per specification
4. Dewatering (Monthly) Dewaters between storms
New York State Stormwater Management Design Manual Appendix G
G-14
MAINTENANCE ITEM
SATISFACTORY/
UNSATISFACTORY
COMMENTS
5. Sediment deposition (Annual) Clean of sediment
6. Outlet/Overflow Spillway (Annual) Good condition, no need for repairs No evidence of erosion
Comments:
Actions to be Taken:
INSPECTION CERTIFICATION FORM
Name New York SPDES Permit number
(fill in when obtained)
Certification:
“I certify under penalty of law that this document and all
attachments were prepared under my direction or supervision in
accordance with a system designed to assure that qualified
personnel properly gathered and evaluated the information
submitted. Based on my inquiry of the person or persons who
manage the system, or those persons directly responsible for
gathering the information, the information submitted is, to the
best of my knowledge and belief, true, accurate, and complete. I
am aware that there are significant penalties for submitting
false information, including the possibility of fine and
imprisonment for knowing violations.”
Signature Date Title
GP-0-20-001
CONSTRUCTION ACTIVITY FORM
NOTE: The contractor is responsible for maintaining an accurate and complete log of construction
activities, including, but not limited to, commencement of stabilization, major grading activities,
timeframes when construction ceases on a portion of site (temporary or permanent) until the Notice
of Termination (NOT) is filed.
MAJOR STABILIZATION AND GRADING ACTIVITIES
Construction Activity Contractor Name Start Date End Date Location
D. CONTRACTOR/OWNER CERTIFICATION FORMS,
CONSTRUCTION ACTIVITY FORM
CONTRACTOR CERTIFICATION FORM
Proposed Microproduction Brewery
South Broadway
City of Saratoga Springs,
Saratoga County, NY
Contractor responsible for the implementation of the SWPPP:
THBC NY, LLC
Company Name Business Telephone Number
Business Address City, State, Zip Code
Business Facsimile E-mail Address
CERTIFICATION:
"I hereby certify under penalty of law that I understand and agree to comply with the terms and
conditions of the SWPPP and agree to implement any corrective actions identified by the qualified
inspector during a site inspection. I also understand that the owner or operator must comply with the
terms and conditions of the most current version of the New York State Pollutant Discharge
Elimination System ("SPDES") general permit for stormwater discharges from construction activities
and that it is unlawful for any person to cause or contribute to a violation of water quality standards.
Furthermore, I am aware that there are significant penalties for submitting false information, that I do
not believe to be true, including the possibility of fine and imprisonment of knowing violations.”
Signature Date
Printed Name Title
Company Name Business Telephone Number
Business Address City, State, Zip Code
Owner/Operator Certification Form
SPDES General Permit For Stormwater
Discharges From Construction Activity
(GP-0-15-002)
Project/Site Name: ________________________________________________________
eNOI Submission Number: _________________________________________________
eNOI Submitted by: Owner/Operator SWPPP Preparer Other
Certification Statement - Owner/Operator
I have read or been advised of the permit conditions and believe that I understand them. I also understand
that, under the terms of the permit, there may be reporting requirements. I hereby certify that this document
and the corresponding documents were prepared under my direction or supervision. I am aware that there are
significant penalties for submitting false information, including the possibility of fine and imprisonment for
knowing violations. I further understand that coverage under the general permit will be identified in the
acknowledgment that I will receive as a result of submitting this NOI and can be as long as sixty (60) business
days as provided for in the general permit. I also understand that, by submitting this NOI, I am acknowledging
that the SWPPP has been developed and will be implemented as the first element of construction, and
agreeing to comply with all the terms and conditions of the general permit for which this NOI is being
submitted.
Owner/Operator First Name M.I. Last Name
___________________________________________________________
Signature
________________________________
Date
E. NYSOPRHP MAP AND LETTER
Site Location
New York State Office of Parks, Recreation and Historic Preservation
Division for Historic Preservation, Peebles Island, PO Box 189, Waterford, New York 12188-0189
(518) 237-8643 • https://parks.ny.gov/shpo
KATHY HOCHUL ERIK KULLESEID
Governor Commissioner
November 15, 2023
Steve Wilson
Project Manager
Bohler Engineering
17 Computer Drive West
Alb, NY 12205
Re: DEC
THBC NY, LLC (Treehouse Brewing Company)
3376 United States Route 9, Saratoga Springs, NY 12866
23PR09559
Dear Steve Wilson:
Thank you for requesting the comments of the Division for Historic Preservation of the Office of
Parks, Recreation and Historic Preservation (OPRHP). We have reviewed the submitted
materials in accordance with the New York State Historic Preservation Act of 1980 (section
14.09 of the New York Parks, Recreation and Historic Preservation Law). These comments are
those of the Division for Historic Preservation and relate only to Historic/Cultural resources.
They do not include potential environmental impacts to New York State Parkland that may be
involved in or near your project.
OPRHP has reviewed the Phase I Archaeological Survey Report prepared for this project
(October 2023; 23SR00600). No archaeological sites were identified by the survey and the
OPRHP concurs with the report recommendation that no additional archaeological work is
necessary.
Please note that these comments pertain only to archaeological resources. Please continue to
consult with Leslie Krupa in the Survey and Evaluation Unit at Leslie.Krupa@parks.ny.gov. If
you have any questions concerning archaeology, I can be reached at
Jessica.Schreyer@parks.ny.gov.
Sincerely,
Jessica Schreyer
Historic Preservation Program Analyst - Archaeologist
F. STORMWATER MANAGEMENT REPORT
STORMWATER MANAGEMENT REPORT
THBC NY, LLC
Proposed Microproduction Brewery
Site Location:
3376 South Broadway
City of Saratoga Springs,
Saratoga County,
State of New York
December 4, 2023
Prepared by:
17 Computer Drive West, Albany, NY 12205
Phone: (518) 438-9900
Fax: (518) 438-0900
www.bohlereng.com
No. NYB230191
Page | 1
Table of Contents
I. Introduction .......................................................................................................................................... 2
II. Existing Stormwater Conditions ............................................................................................................ 2
a. Existing Stormwater Conditions Summary ....................................................................................... 2
b. Existing Drainage Tributary Map ....................................................................................................... 3
III. Proposed Stormwater Conditions ..................................................................................................... 4
a. Proposed Stormwater Conditions Summary .................................................................................... 4
b. Proposed Drainage Tributary Map .................................................................................................... 6
IV. Conclusion ......................................................................................................................................... 7
a. Pre-Development and Post-Development Storm Water Discharge Comparison Table ................... 8
b. WQv and RRv Calculations & Table ................................................................................................... 9
c. Pre and Post Development Watershed Hydrological Analysis ......................................................... 10
f. NRCS Soils Data………………………………………………………………………………………………………………………….
g. Geotechnical Report ……………………………………..………………………………………………………………………….
Page | 2
I. Introduction
The applicant, THBC NY, LLC. is proposing to develop a ±10.7-acre site within the City of
Saratoga Springs, Saratoga County, New York. The project site is located at 3376 US Route 9 (South
Broadway), approximately ±1,300 feet south of the intersection with Crescent Ave and is currently
developed with portions of paved parking. A new 2-story, ±22,778 sf microproduction brewery
and three pavilions are proposed along with new patio seating, parking facilities, utility
connections, stormwater management facilities, and other appurtenances as depicted on the
Proposed Site Plan Documents prepared by Bohler, dated November 30, 2023, no revisions listed.
This Stormwater Pollution Prevention Plan (SWPPP) has been prepared as required by the
New York State Department of Environmental Conservation SPDES General Permit for Stormwater
Discharges from Construction Activity Permit No. GP-0-20-001.
This report will briefly discuss the proposed site development and provide a detailed analysis
of the existing and proposed site conditions and the proposed stormwater management system.
Hydraulic calculations included in this report were generated for the 1, 10 and 100 year storm
events utilizing the SCS TR-20 and HydroCad Stormwater modeling software.
II. Existing Stormwater Conditions
a. Existing Stormwater Conditions Summary
The existing overall ±10.7- acre parcel is currently undeveloped except for a small area
of paved parking and consists primarily of wooded and grassed areas. Based on the survey, the
majority of stormwater from the site sheet flows overland in a southeasterly direction towards
the existing wetlands located along the easterly property boundary. These wetlands eventually
discharge into the Kayaderosseras Creek, tributary to Saratoga Lake.
For analysis purposes, the project has been analyzed as one (1) watershed to
demonstrate tributary flows; Watershed EX-1.
Watershed EX-1 consists of stormwater flows associated with the entirety of the
property, and primarily consists of brush and grassed areas, wooded areas, a small area of
existing paved parking and wetlands. Stormwater from this area sheet flows overland to the
existing wetlands located along the easterly side of the subject site; designated as Design Point
1.
The existing watershed areas and topography are illustrated on the Existing Drainage
Tributary Map included on the next page of this report.
Page | 3
b.Existing Drainage Tributary Map
SOUTH BROADWAYU.S. ROUTE 9DP1
HSG A
EX-1
W E
S
EXISTING CONDITIONS
DRAINAGE AREA MAP
3376 SOUTH BROADWAY
CITY OF SARATOGA SPRINGS, NEW YORK
SCALE:1"=100' DATE: 11/22/2023
PREPARED BY
P:\2023\NYB230191.00\CAD\Drawings\Plan Sets\Civil Site Plans\NYB230191.00-SWPP-0a.dwgDP#
EX-#
A/B/C/D
DESIGN POINT
EXISTING SUBCATCHMENT
HYDROLOGIC SOIL GROUP RATING
LEGEND
SUBCATCHMENT BOUNDARY
TIME OF CONCENTRATION
Page | 4
III. Proposed Stormwater Conditions
a. Proposed Stormwater Conditions Summary
The proposed development will create new impervious areas while implementing new
buildings, parking, utilities, and stormwater management facilities along with other
appurtenances. Stormwater is proposed to be treated onsite and discharged in a way to mimic
the existing drainage patterns while treating the water for quality and reducing the discharge flow
rate from the pre-developed conditions as required and set forth in the 2015 NYSDEC Stormwater
Design Manual.
This project includes the redevelopment of ±0.4 acres of existing pavement, which is classified
by the NYSDEC as a redevelopment activity. The total impervious cover for the proposed project
will be ±4.9 acres, resulting in ±4.5 acres of new impervious cover. Per Section 9.2.1.B.II, the plan
proposes that a minimum of 25% of the water quality volume from the disturbed, impervious area
and 100% of the new impervious area is captured and treated by a standard SMP, or ±4.6 acres
total. The majority of the proposed impervious cover, including the proposed buildings, parking
areas and drive aisles, totaling ±4.7 acres, is sent to the proposed stormwater management
facilities for treatment.
In order to analyze the proposed stormwater conditions, the project site has been designed
with the same watershed as described in the existing conditions above and has been designated
as Watershed PR-1, as depicted on the Proposed Drainage Tributary Map following this section of
the report. Watershed PR-1 has been further divided into six (6) sub catchments – namely PR-1A,
PR-1B, PR-1C, PR-1D, PR-1E and PR-1F. The watersheds have unique flow paths and therefore
have been analyzed individually.
Subcatchment PR-1A consists of the wooded areas and wetlands at the easterly side of the
site. This area also includes a portion of the neighboring site to the south and surrounding existing
greenspace areas. Stormwater flows associated with this area sheet flow overland to the existing
wetlands on-site, designated as DP1, similar to existing conditions.
Subcatchments PR-1B is comprised of a portion of the proposed visitor parking area and drive
aisle along the southerly side of the site that sheet flows into sections of porous pavement where
the stormwater is treated for quality and quantity. The porous pavement is designed per the
requirements set forth by the NYSDEC Stormwater Design Manual. Stormwater above and beyond
the WQv and capacity of the porous pavement will be discharged to the existing wetlands, similar
to existing conditions.
Subcatchment PR-1C is comprised of the southern half of the proposed building, the proposed
ingress access drive and some proposed walkways and surrounding greenspace. Stormwater from
the building will flow into roof drains and will be directed to proposed aboveground infiltration
basins where stormwater will be treated for quality and quantity. Stormwater above and beyond
the WQv and capacity of the infiltration system will be discharged to a proposed swale that leads
to the existing wetlands, similar to existing conditions.
Page | 5
Subcatchment PR-1D is comprised of a portion of the parking area along the frontage of the
building and a proposed dry swale. Stormwater from the pavement portions sheet flow to a gravel
diaphragm and into a proposed dry swale where it is treated for quality and quantity. Upon
reaching the system’s capacity, stormwater will discharge out to the proposed infiltration basin
located to the south.
Subcatchment PR-1E is comprised of the northern half of the proposed building, a portion of
the proposed parking areas and associated access drive, the loading dock area and surrounding
wooded and grassed areas. Stormwater from the building will flow into roof drains and will be
directed to a proposed infiltration basin where stormwater will be treated for quality and
quantity. Stormwater from the remainder of the catchment area will sheet flow into the proposed
infiltration basin. Stormwater above and beyond the WQv and capacity of the basin will be
discharged to a dry swale and eventually into the wetlands, similar to existing conditions.
Subcatchment PR-1F is comprised of the three proposed pavilion buildings, parking areas and
drive aisles to the north and east of the building, along with patio seating areas, gravel pathways
and surrounding grassed areas. Stormwater from these areas travel via sheet flow to a proposed
swale and eventually to a proposed stormwater basin where it is treated and detained. Upon
reaching capacity, the basin discharges via an emergency spillway to the existing wetlands. The
basin is also equipped with a low flow orifice to be released at a controlled rate to the existing
wetlands, as it does today.
As designed, the Stormwater management systems provide the required quality and
quantity treatment for the project, as set forth in the 2015 New York State DEC Stormwater
Management Design Manual. All calculations, flow rates, and modeling are a part of this report
and have been included herein.
The majority of stormwater from developed areas of the site will be diverted to several
proposed treatment systems located throughout the site. The proposed stormwater systems have
been designed with sufficient capacity to provide WQv treatment and detention and to mitigate
off-site discharge rates to below existing conditions for all subject storm events. The underground
infiltration systems have been designed per the NYSDEC Stormwater Management Design Manual
for infiltration systems.
The proposed watershed areas, topography and flow paths are illustrated on the
Proposed Drainage Tributary Map, included on the following page of this report.
Page | 6
b. Proposed Drainage Tributary Map
N 12°46'59" E 501.66'S 85°46'00" E 610.
8
3
'N 10°13'59" E 73.96'N 86°12'05" E 170.93'N 86°41'18" E 107.94'S 11°54'18" W 617.35'N 85°30'00" W 8
8
7
.
0
0
'
WETLAND "A"
AREA=0.53 ACRES
S C/O
S
C/O
S
DP1
HSG A
30
5
305 305306306306
307308
308
3
0
8 308309
309
305
302303304304304306
3
0
7 3083
0
8
308305304306307 306306
3
0
7
3
0
7
3
0
8308308
308
305
306307307308 308305306
306
306
306 30530330430
6
308
305306307
3
0
5
302
302303304305 306
307
308
306
305306
303
303
304 3053053
0
4
3
0
4 304307308 308
W E
S
PROPOSED CONDITIONS
DRAINAGE AREA MAP
3376 SOUTH BROADWAY
CITY OF SARATOGA SPRINGS, NEW YORK
SCALE:1"=100' DATE: 11/22/2023
PREPARED BY
P:\2023\NYB230191.00\CAD\Drawings\Plan Sets\Civil Site Plans\NYB230191.00-SWPP-0a.dwgDP#
PR-#
XX#
A/B/C/D
X-#
DESIGN POINT
EXISTING SUBCATCHMENT
BASIN OR MODELED DRAINAGE
STRUCTURE
HYDROLOGIC SOIL GROUP RATING
SWALE OR MODELED JUNCTION
LEGEND
SUBCATCHMENT BOUNDARY
TIME OF CONCENTRATION
S-1
PR-1F
PR-1B
PR-1C
PR-1D
PR-1E
PR-1A
IB2
IB1
DS-1
PP-1
IB2
Page | 7
IV. Conclusion
The proposed development has been designed with a stormwater management system that meets or
exceeds the objectives set forth in the 2015 NYSDEC Stormwater Management Design Manual by
providing stormwater quality and quantity treatment practices. Uniform sizing criteria were calculated as
follows:
The 90% Rule Water Quality Volume (WQv) is discharged to infiltration treatment
practices (I-2) and dry swales (O-1). All practices have been designed per the
requirements set forth by the NYSDEC.
Runoff Reduction Volume (RRv) requirement has been achieved by exceeding the
minimum required RRv in the proposed infiltration systems, dry swales and a section
of porous pavement (RR-9).
Channel Protection (Cpv) was calculated using the 24-hour extended detention of post
developed 1year, 24 hour storm event.
Overbank Flood (Qp) protection was designed to control the peak discharge from the
10-year storm to the 10-year predevelopment rates. These calculations can be found
in the 10-year storm analysis for each watershed and the total stormwater discharge
comparison chart included in the report.
Extreme Storm (Qf) protection was designed to control the peak discharge from the
100-year storm to rates less than the 100-year predevelopment rates. These
calculations can be found in the 100-year storm analysis for each watershed and the
total stormwater discharge comparison chart included in the report.
The proposed stormwater management system, as designed, will serve to mitigate the effects of
the development of the parcel, such that the proposed use will not adversely affect any downstream or
adjacent properties. Significant stormwater quality and quantity improvements to the existing condition
are proposed as part of this redevelopment project. These improvements are expected to not only meet
but significantly exceed the objectives set forth in the NYSDEC Stormwater Management Design Manual.
Page | 8
a. Pre-Development and Post-Development Storm Water Discharge
Comparison Table
Discharge Quantity (cfs) Summary Table – DP1
Rainfall
Event
Design Point 1 %
Reduction Existing Proposed
1 Year 0.01 0.00 100%
10 Year 0.49 0.03 94%
100 year 5.90 2.80 53%
Page | 9
b. WQv and RRv Calculations & Table
Required Water Quality Volume (WQv) Calculations
P = Design rainfall event depth = 1.1 inches
Pd = Proposed disturbed area = ±11.1 acres
Ed = Existing Impervious area to be disturbed = ±0.4 acres
EI = Existing Impervious area = ±0.4 acres
PI = Proposed total impervious area = ±4.9 acres
NI = Net increase of impervious area = PI - EI = ±4.9 – ±0.4 = ±4.5 acres
Refer to GI worksheet attached within this report for WQv calculations and underground infiltration
system sizing.
Water Quality Treatment Summary Table
Runoff Reduction Volume (RRv) Water Quality Volume (WQv)
Minimum Proposed % achieved Required Proposed % achieved
±0.225 AF ±0.426 AF 189% ±0.426 AF ±0.426 CF 100%
Page | 10
c. Pre and Post Development Watershed Hydrological Analysis
Version 1.8
Last Updated: 11/09/2015
Total Water Quality Volume Calculation
WQv(acre‐feet) = [(P)(Rv)(A)] /12
Design Point: 1
P= 1.10 inch
Catchment
Number
Total Area
(Acres)
Impervious Area
(Acres)
Percent
Impervious
%
Rv WQv
(ft 3 )Description
1 1.95 1.82 93% 0.89 6,930
Porous Pavement
2 0.99 0.39 39% 0.41 1,595
Infiltration Basin
3 0.30 0.24 80% 0.77 919
Dry Swale
4 0.62 0.36 57% 0.57 1,403
Infiltration Basin
5 4.50 1.90 42% 0.43 7,726
Infiltration Basin
6
7
8
9
10
Subtotal (1‐30)8.36 4.70 56% 0.56 18,573 Subtotal 1
Total 8.36 4.70 56% 0.56 18,573 Initial WQv
Total
Contributing
Area
Contributing
Impervious Area
(Acre) (Acre)
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
Total Area
(Acres)
Impervious Area
(Acres)
Percent
Impervious
%
Runoff
Coefficient
Rv
WQv
(ft 3 )
8.36 4.70 56% 0.56 18,573
0.00 0.00
8.36 4.70 56% 0.56 18,573
0.00
8.36 4.70 56% 0.56 18,573
0
Technique
minimum 10,000 sfConservation of Natural Areas
WQv reduced by Area
Reduction techniques
Adjusted WQv after Area
Reduction and Rooftop
Disconnect
Subtract Area
Disconnection of Rooftops
WQv adjusted after Area
Reductions
Identify Runoff Reduction Techniques By Area
Breakdown of Subcatchments
Is this project subject to Chapter 10 of the NYS Design Manual (i.e. WQv is equal to post‐
development 1 year runoff volume)?......................................................................................
"<<Initial WQv"
Recalculate WQv after application of Area Reduction Techniques
Riparian Buffers maximum contributing length 75 feet to
150 feet
Up to 100 sf directly connected impervious
area may be subtracted per treeTree Planting
Filter Strips
Total
Notes
Minimum RRv
Soil Group Acres S
A 8.36 55%
B 40%
C 30%
D 20%
Total Area 8.36
S =0.55
Impervious = 4.70 acre
Precipitation 1.1 in
Rv 0.95
Minimum RRv 9,814 ft3
0.23 af
Enter the Soils Data for the site
Calculate the Minimum RRv
Runoff Reduction Techiques/Standard
SMPs
Total
Contributing
Area
Total
Contributing
Impervious
Area
WQv
Reduced
(RRv)
WQv
Treated
(acres) (acres) cf cf
Conservation of Natural Areas RR-1 0.00 0.00
Sheetflow to Riparian Buffers/Filter
Strips RR-2 0.00 0.00
Tree Planting/Tree Pit RR-3 0.00 0.00
Disconnection of Rooftop Runoff RR-4 0.00
Vegetated Swale RR-5 0.00 0.00 0
Rain Garden RR-6 0.00 0.00 0
Stormwater Planter RR-7 0.00 0.00 0
Rain Barrel/Cistern RR-8 0.00 0.00 0
Porous Pavement RR-9 1.95 1.82 6930
Green Roof (Intensive & Extensive) RR-10 0.00 0.00 0
Infiltration Trench I-1 0.00 0.00 0 0
Infiltration Basin I-2 6.11 2.65 10724 0
Dry Well I-3 0.00 0.00 0 0
Underground Infiltration System I-4
Bioretention & Infiltration Bioretention F-5 0.00 0.00 0 0
Dry swale O-1 0.30 0.24 919 0
Micropool Extended Detention (P-1) P-1
Wet Pond (P-2) P-2
Wet Extended Detention (P-3) P-3
Multiple Pond system (P-4) P-4
Pocket Pond (p-5) P-5
Surface Sand filter (F-1) F-1
Underground Sand filter (F-2) F-2
Perimeter Sand Filter (F-3) F-3
Organic Filter (F-4 F-4
Shallow Wetland (W-1) W-1
Extended Detention Wetland (W-2 W-2
Pond/Wetland System (W-3) W-3
Pocket Wetland (W-4) W-4
Wet Swale (O-2) O-2
→0.00 0.00 0
→1.95 1.82 6930
→6.41 2.88 11643 0
→0.00 0.00 0
→8.36 4.70 18,573 0
Impervious Cover √ okay
Totals by Volume Reduction
Totals by Standard SMP w/RRV
Totals by Standard SMP
Totals ( Area + Volume + all SMPs)
Runoff Reduction Volume and Treated volumes
Standard SMPs w/RRv CapacityStandard SMPs Area/Volume ReductionTotals by Area Reduction
Porous Pavement Worksheet
Ap ft2
Vw ft3
n
dt
Design Point:1
Catchment
Number
Total Area
(Acres)
Impervious
Area
(Acres)
Percent
Impervious
%
Rv WQv
(ft 3 )
Precipitation
(in)Description
1 1.95 1.82 0.93 0.89 6929.85 1.10 Porous Pavement
7.50 in/hour
Vw 6,930 ft 3
n 0.40 -
dt 1.00 ft
Ap 17,325 sf
19,161 sf
7,664 ft 3
RRv 6,930 ft 3
Design Volume
Dimensions of pavement can be provided
here
Porosity of Gravel Bed
Gravel Bed Depth
Required Surface Area
Surface Area Provided
Storage Volume Provided
Ap = Vw / (n x dt)
Determine the Runoff Reduction
Enter Site Data For Drainage Area to be Treated by Practice
Calculate Required Surface Area
Required porous pavement surface area
Design Volume
porosity of gravel bed/resevoir
depth of gravel bed/resevoir
Assume .4 for gravel
Soil Inflitration Rate
Enter Soil Infiltration Rate
Are underdrains being used? No -
Infiltration Basin Worksheet
Design Point:1
Catchment
Number
Total Area
(Acres)
Impervious
Area
(Acres)
Percent
Impervious
%
Rv WQv
(ft 3 )
Precipitation
(in)Description
2 0.99 0.39 0.39 0.41 1594.60 1.10 Infiltration Basin
39% 0.41 1,595
ft 3
7.50 in/hour
100 % WQv
1,595 ft 3
1,600 ft 3
Design
Volume 1,595 ft 3
Basal Area
Required 638 ft 2
Basal Area
Provided 1,566 ft 2
Design Depth 2.50 ft
Volume
Provided 3,915 ft 3
RRv 1,595 ft 3
Volume
Treated 0 ft 3
Sizing √ OK
Enter Impervious Area
Reduced by Disconnection of
Rooftops
<<WQv after adjusting for
Disconnected Rooftops
WQv
Enter Site Data For Drainage Area to be Treated by Practice
Pretreatment Techniques to Prevent Clogging
Size An Infiltration Basin
Infiltration Rate
Pretreatment Sizing
Pretreatment Required Volume
Pretreatment Provided
Pretreatment Techniques utilized
Okay
25% minimum;
50% if >2 in/hr
100% if >5in/hour
90% of the storage provided in the basin or WQv whichever is
smaller
The infiltration basin must provide storage equal to or greater than
the WQv of the contributing area.
This is the portion of the WQv that is not reduced/infiltrated
Storage Volume provided in infiltration basin area (not including
pretreatment.
Determine Runoff Reduction
Grass Channel
Enter the portion of the WQv that is not reduced for all practices
routed to this practice.
Infiltration practices shall be designed to exfiltrate the entire WQv
through the floor of each practice.
Dry Swale Worksheet
Design Point:1
Catchment
Number
Total Area
(Acres)
Impervious
Area
(Acres)
Percent
Impervious
%
Rv WQv
(ft 3 )
Precipitation
(in)Description
3 0.30 0.24 0.80 0.77 918.79 1.10 Dry Swale
80% 0.77 919
92 ft 3
Bottom Width 8 ft
Side Slope
(X:1)3 Okay
Longitudinal
Slope 1%Okay
Flow Depth 1.5 ft
Top Width 17 ft
Area 18.75 sf
Minimum
Length 44 ft
Actual Length 161 ft
End Point
Depth check 1.50 Okay
Storage
Capacity 3,111 ft 3
A
Yes
RRv 919 ft 3
Volume
Treated 0 ft 3
Volume
Directed 0 ft 3
Volume √Okay Check to be sure that channel is long enough to store WQv
This is the difference between the WQv calculated and the runoff
reduction achieved in the swale
Enter Site Data For Drainage Area to be Treated by Practice
Calculate Available Storage Capacity
Pretreatment (10% of WQv)
Design with a bottom width no greater than eight feet to avoid
potential gullying and channel braiding, but no less than two feet
Channels shall be designed with moderate side slopes (flatter
than 3:1) for most conditions. 2:1 is the
absolute maximum side slope
Maximum longitudinal slope shall be 4%
Maximum ponding depth of one foot at the mid-point of the
channel, and a maximum depth of 18" at the end point of the
channel (for storage of the WQv)
A maximum depth of 18" at the end point of the channel (for
storage of the WQv)
Pretreatment Technique
Enter Impervious Area Reduced
by Disconnection of Rooftops
<<WQv after adjusting for
Disconnected Rooftops
Pretreatment Provided
Gravel Diaphragm
Runoff Reduction
Runnoff Reduction equals 40% in HSG A and B and 20% in HSG C
and D up to the WQv
This volume is directed another practice
Is the Dry Swale contributing flow to another
practice?Select Practice
Soil Group (HSG)
Infiltration Basin
TW
pBW
Infiltration Basin Worksheet
Design Point:1
Catchment
Number
Total Area
(Acres)
Impervious
Area
(Acres)
Percent
Impervious
%
Rv WQv
(ft 3 )
Precipitation
(in)Description
4 0.62 0.36 0.57 0.57 1403.14 1.10 Infiltration Basin
57% 0.57 1,403
ft 3
7.50 in/hour
100 % WQv
1,403 ft 3
1,800 ft 3
Design
Volume 1,403 ft 3
Basal Area
Required 702 ft 2
Basal Area
Provided 954 ft 2
Design Depth 2.00 ft
Volume
Provided 1,908 ft 3
RRv 1,403 ft 3
Volume
Treated 0 ft 3
Sizing √ OK
Size An Infiltration Basin
Storage Volume provided in infiltration basin area (not including
pretreatment.
Determine Runoff Reduction
Enter Site Data For Drainage Area to be Treated by Practice
Enter Impervious Area
Reduced by Disconnection of
Rooftops
<<WQv after adjusting for
Disconnected RooftopsEnter the portion of the WQv that is not reduced for all practices
routed to this practice.
Pretreatment Techniques to Prevent Clogging
Pretreatment Provided
Infiltration Rate Okay
Pretreatment Sizing
25% minimum;
50% if >2 in/hr
100% if >5in/hour
Pretreatment Required Volume
Pretreatment Techniques utilized Grass Channel
WQv
90% of the storage provided in the basin or WQv whichever is
smaller
This is the portion of the WQv that is not reduced/infiltrated
Infiltration practices shall be designed to exfiltrate the entire WQv
through the floor of each practice.
The infiltration basin must provide storage equal to or greater than
the WQv of the contributing area.
Infiltration Basin Worksheet
Design Point:1
Catchment
Number
Total Area
(Acres)
Impervious
Area
(Acres)
Percent
Impervious
%
Rv WQv
(ft 3 )
Precipitation
(in)Description
5 4.50 1.90 0.42 0.43 7726.46 1.10 Infiltration Basin
42% 0.43 7,726
ft 3
7.50 in/hour
100 % WQv
7,726 ft 3
7,800 ft 3
Design
Volume 7,726 ft 3
Basal Area
Required 7,726 ft 2
Basal Area
Provided 8,746 ft 2
Design Depth 1.00 ft
Volume
Provided 8,746 ft 3
RRv 7,726 ft 3
Volume
Treated 0 ft 3
Sizing √ OK
Pretreatment Provided
Pretreatment Techniques utilized Grass Channel
Size An Infiltration Basin
Enter Impervious Area
Reduced by Disconnection of
Rooftops
<<WQv after adjusting for
Disconnected RooftopsEnter the portion of the WQv that is not reduced for all practices
routed to this practice.
Pretreatment Techniques to Prevent Clogging
Infiltration Rate Okay
Pretreatment Sizing
25% minimum;
50% if >2 in/hr
100% if >5in/hour
Enter Site Data For Drainage Area to be Treated by Practice
90% of the storage provided in the basin or WQv whichever is
smaller
This is the portion of the WQv that is not reduced/infiltrated
Storage Volume provided in infiltration basin area (not including
pretreatment.
Determine Runoff Reduction
The infiltration basin must provide storage equal to or greater than
the WQv of the contributing area.
Pretreatment Required Volume
WQv
Infiltration practices shall be designed to exfiltrate the entire WQv
through the floor of each practice.
United States
Department of
Agriculture
A product of the National
Cooperative Soil Survey,
a joint effort of the United
States Department of
Agriculture and other
Federal agencies, State
agencies including the
Agricultural Experiment
Stations, and local
participants
Custom Soil Resource
Report for
Saratoga
County, New
York
Natural
Resources
Conservation
Service
November 10, 2023
Preface
Soil surveys contain information that affects land use planning in survey areas.
They highlight soil limitations that affect various land uses and provide information
about the properties of the soils in the survey areas. Soil surveys are designed for
many different users, including farmers, ranchers, foresters, agronomists, urban
planners, community officials, engineers, developers, builders, and home buyers.
Also, conservationists, teachers, students, and specialists in recreation, waste
disposal, and pollution control can use the surveys to help them understand,
protect, or enhance the environment.
Various land use regulations of Federal, State, and local governments may impose
special restrictions on land use or land treatment. Soil surveys identify soil
properties that are used in making various land use or land treatment decisions.
The information is intended to help the land users identify and reduce the effects of
soil limitations on various land uses. The landowner or user is responsible for
identifying and complying with existing laws and regulations.
Although soil survey information can be used for general farm, local, and wider area
planning, onsite investigation is needed to supplement this information in some
cases. Examples include soil quality assessments (http://www.nrcs.usda.gov/wps/
portal/nrcs/main/soils/health/) and certain conservation and engineering
applications. For more detailed information, contact your local USDA Service Center
(https://offices.sc.egov.usda.gov/locator/app?agency=nrcs) or your NRCS State Soil
Scientist (http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/contactus/?
cid=nrcs142p2_053951).
Great differences in soil properties can occur within short distances. Some soils are
seasonally wet or subject to flooding. Some are too unstable to be used as a
foundation for buildings or roads. Clayey or wet soils are poorly suited to use as
septic tank absorption fields. A high water table makes a soil poorly suited to
basements or underground installations.
The National Cooperative Soil Survey is a joint effort of the United States
Department of Agriculture and other Federal agencies, State agencies including the
Agricultural Experiment Stations, and local agencies. The Natural Resources
Conservation Service (NRCS) has leadership for the Federal part of the National
Cooperative Soil Survey.
Information about soils is updated periodically. Updated information is available
through the NRCS Web Soil Survey, the site for official soil survey information.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its
programs and activities on the basis of race, color, national origin, age, disability,
and where applicable, sex, marital status, familial status, parental status, religion,
sexual orientation, genetic information, political beliefs, reprisal, or because all or a
part of an individual's income is derived from any public assistance program. (Not
all prohibited bases apply to all programs.) Persons with disabilities who require
2
alternative means for communication of program information (Braille, large print,
audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice
and TDD). To file a complaint of discrimination, write to USDA, Director, Office of
Civil Rights, 1400 Independence Avenue, S.W., Washington, D.C. 20250-9410 or
call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity
provider and employer.
3
Contents
Preface....................................................................................................................2
How Soil Surveys Are Made..................................................................................5
Soil Map..................................................................................................................8
Soil Map................................................................................................................9
Legend................................................................................................................10
Map Unit Legend................................................................................................11
Map Unit Descriptions.........................................................................................11
Saratoga County, New York............................................................................13
DeA—Deerfield loamy fine sand, 0 to 3 percent slopes..............................13
DeB—Deerfield loamy fine sand, 3 to 8 percent slopes..............................14
References............................................................................................................17
4
How Soil Surveys Are Made
Soil surveys are made to provide information about the soils and miscellaneous
areas in a specific area. They include a description of the soils and miscellaneous
areas and their location on the landscape and tables that show soil properties and
limitations affecting various uses. Soil scientists observed the steepness, length,
and shape of the slopes; the general pattern of drainage; the kinds of crops and
native plants; and the kinds of bedrock. They observed and described many soil
profiles. A soil profile is the sequence of natural layers, or horizons, in a soil. The
profile extends from the surface down into the unconsolidated material in which the
soil formed or from the surface down to bedrock. The unconsolidated material is
devoid of roots and other living organisms and has not been changed by other
biological activity.
Currently, soils are mapped according to the boundaries of major land resource
areas (MLRAs). MLRAs are geographically associated land resource units that
share common characteristics related to physiography, geology, climate, water
resources, soils, biological resources, and land uses (USDA, 2006). Soil survey
areas typically consist of parts of one or more MLRA.
The soils and miscellaneous areas in a survey area occur in an orderly pattern that
is related to the geology, landforms, relief, climate, and natural vegetation of the
area. Each kind of soil and miscellaneous area is associated with a particular kind
of landform or with a segment of the landform. By observing the soils and
miscellaneous areas in the survey area and relating their position to specific
segments of the landform, a soil scientist develops a concept, or model, of how they
were formed. Thus, during mapping, this model enables the soil scientist to predict
with a considerable degree of accuracy the kind of soil or miscellaneous area at a
specific location on the landscape.
Commonly, individual soils on the landscape merge into one another as their
characteristics gradually change. To construct an accurate soil map, however, soil
scientists must determine the boundaries between the soils. They can observe only
a limited number of soil profiles. Nevertheless, these observations, supplemented
by an understanding of the soil-vegetation-landscape relationship, are sufficient to
verify predictions of the kinds of soil in an area and to determine the boundaries.
Soil scientists recorded the characteristics of the soil profiles that they studied. They
noted soil color, texture, size and shape of soil aggregates, kind and amount of rock
fragments, distribution of plant roots, reaction, and other features that enable them
to identify soils. After describing the soils in the survey area and determining their
properties, the soil scientists assigned the soils to taxonomic classes (units).
Taxonomic classes are concepts. Each taxonomic class has a set of soil
characteristics with precisely defined limits. The classes are used as a basis for
comparison to classify soils systematically. Soil taxonomy, the system of taxonomic
classification used in the United States, is based mainly on the kind and character
of soil properties and the arrangement of horizons within the profile. After the soil
5
scientists classified and named the soils in the survey area, they compared the
individual soils with similar soils in the same taxonomic class in other areas so that
they could confirm data and assemble additional data based on experience and
research.
The objective of soil mapping is not to delineate pure map unit components; the
objective is to separate the landscape into landforms or landform segments that
have similar use and management requirements. Each map unit is defined by a
unique combination of soil components and/or miscellaneous areas in predictable
proportions. Some components may be highly contrasting to the other components
of the map unit. The presence of minor components in a map unit in no way
diminishes the usefulness or accuracy of the data. The delineation of such
landforms and landform segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, onsite
investigation is needed to define and locate the soils and miscellaneous areas.
Soil scientists make many field observations in the process of producing a soil map.
The frequency of observation is dependent upon several factors, including scale of
mapping, intensity of mapping, design of map units, complexity of the landscape,
and experience of the soil scientist. Observations are made to test and refine the
soil-landscape model and predictions and to verify the classification of the soils at
specific locations. Once the soil-landscape model is refined, a significantly smaller
number of measurements of individual soil properties are made and recorded.
These measurements may include field measurements, such as those for color,
depth to bedrock, and texture, and laboratory measurements, such as those for
content of sand, silt, clay, salt, and other components. Properties of each soil
typically vary from one point to another across the landscape.
Observations for map unit components are aggregated to develop ranges of
characteristics for the components. The aggregated values are presented. Direct
measurements do not exist for every property presented for every map unit
component. Values for some properties are estimated from combinations of other
properties.
While a soil survey is in progress, samples of some of the soils in the area generally
are collected for laboratory analyses and for engineering tests. Soil scientists
interpret the data from these analyses and tests as well as the field-observed
characteristics and the soil properties to determine the expected behavior of the
soils under different uses. Interpretations for all of the soils are field tested through
observation of the soils in different uses and under different levels of management.
Some interpretations are modified to fit local conditions, and some new
interpretations are developed to meet local needs. Data are assembled from other
sources, such as research information, production records, and field experience of
specialists. For example, data on crop yields under defined levels of management
are assembled from farm records and from field or plot experiments on the same
kinds of soil.
Predictions about soil behavior are based not only on soil properties but also on
such variables as climate and biological activity. Soil conditions are predictable over
long periods of time, but they are not predictable from year to year. For example,
soil scientists can predict with a fairly high degree of accuracy that a given soil will
have a high water table within certain depths in most years, but they cannot predict
that a high water table will always be at a specific level in the soil on a specific date.
After soil scientists located and identified the significant natural bodies of soil in the
survey area, they drew the boundaries of these bodies on aerial photographs and
Custom Soil Resource Report
6
identified each as a specific map unit. Aerial photographs show trees, buildings,
fields, roads, and rivers, all of which help in locating boundaries accurately.
Custom Soil Resource Report
7
Soil Map
The soil map section includes the soil map for the defined area of interest, a list of
soil map units on the map and extent of each map unit, and cartographic symbols
displayed on the map. Also presented are various metadata about data used to
produce the map, and a description of each soil map unit.
8
9
Custom Soil Resource Report
Soil Map
4767570476760047676304767660476769047677204767750476778047675704767600476763047676604767690476772047677504767780598680 598710 598740 598770 598800 598830 598860 598890 598920 598950 598980 599010
598680 598710 598740 598770 598800 598830 598860 598890 598920 598950 598980 599010
43° 3' 22'' N 73° 47' 18'' W43° 3' 22'' N73° 47' 2'' W43° 3' 15'' N
73° 47' 18'' W43° 3' 15'' N
73° 47' 2'' WN
Map projection: Web Mercator Corner coordinates: WGS84 Edge tics: UTM Zone 18N WGS84
0 50 100 200 300
Feet
0 20 40 80 120
Meters
Map Scale: 1:1,590 if printed on A landscape (11" x 8.5") sheet.
Soil Map may not be valid at this scale.
MAP LEGEND MAP INFORMATION
Area of Interest (AOI)
Area of Interest (AOI)
Soils
Soil Map Unit Polygons
Soil Map Unit Lines
Soil Map Unit Points
Special Point Features
Blowout
Borrow Pit
Clay Spot
Closed Depression
Gravel Pit
Gravelly Spot
Landfill
Lava Flow
Marsh or swamp
Mine or Quarry
Miscellaneous Water
Perennial Water
Rock Outcrop
Saline Spot
Sandy Spot
Severely Eroded Spot
Sinkhole
Slide or Slip
Sodic Spot
Spoil Area
Stony Spot
Very Stony Spot
Wet Spot
Other
Special Line Features
Water Features
Streams and Canals
Transportation
Rails
Interstate Highways
US Routes
Major Roads
Local Roads
Background
Aerial Photography
The soil surveys that comprise your AOI were mapped at
1:24,000.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service
Web Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator
projection, which preserves direction and shape but distorts
distance and area. A projection that preserves area, such as the
Albers equal-area conic projection, should be used if more
accurate calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as
of the version date(s) listed below.
Soil Survey Area: Saratoga County, New York
Survey Area Data: Version 23, Sep 6, 2023
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Sep 9, 2022—Oct 22,
2022
The orthophoto or other base map on which the soil lines were
compiled and digitized probably differs from the background
imagery displayed on these maps. As a result, some minor
shifting of map unit boundaries may be evident.
Custom Soil Resource Report
10
Map Unit Legend
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
DeA Deerfield loamy fine sand, 0 to
3 percent slopes
6.5 70.2%
DeB Deerfield loamy fine sand, 3 to
8 percent slopes
2.7 29.8%
Totals for Area of Interest 9.2 100.0%
Map Unit Descriptions
The map units delineated on the detailed soil maps in a soil survey represent the
soils or miscellaneous areas in the survey area. The map unit descriptions, along
with the maps, can be used to determine the composition and properties of a unit.
A map unit delineation on a soil map represents an area dominated by one or more
major kinds of soil or miscellaneous areas. A map unit is identified and named
according to the taxonomic classification of the dominant soils. Within a taxonomic
class there are precisely defined limits for the properties of the soils. On the
landscape, however, the soils are natural phenomena, and they have the
characteristic variability of all natural phenomena. Thus, the range of some
observed properties may extend beyond the limits defined for a taxonomic class.
Areas of soils of a single taxonomic class rarely, if ever, can be mapped without
including areas of other taxonomic classes. Consequently, every map unit is made
up of the soils or miscellaneous areas for which it is named and some minor
components that belong to taxonomic classes other than those of the major soils.
Most minor soils have properties similar to those of the dominant soil or soils in the
map unit, and thus they do not affect use and management. These are called
noncontrasting, or similar, components. They may or may not be mentioned in a
particular map unit description. Other minor components, however, have properties
and behavioral characteristics divergent enough to affect use or to require different
management. These are called contrasting, or dissimilar, components. They
generally are in small areas and could not be mapped separately because of the
scale used. Some small areas of strongly contrasting soils or miscellaneous areas
are identified by a special symbol on the maps. If included in the database for a
given area, the contrasting minor components are identified in the map unit
descriptions along with some characteristics of each. A few areas of minor
components may not have been observed, and consequently they are not
mentioned in the descriptions, especially where the pattern was so complex that it
was impractical to make enough observations to identify all the soils and
miscellaneous areas on the landscape.
The presence of minor components in a map unit in no way diminishes the
usefulness or accuracy of the data. The objective of mapping is not to delineate
pure taxonomic classes but rather to separate the landscape into landforms or
landform segments that have similar use and management requirements. The
delineation of such segments on the map provides sufficient information for the
development of resource plans. If intensive use of small areas is planned, however,
Custom Soil Resource Report
11
onsite investigation is needed to define and locate the soils and miscellaneous
areas.
An identifying symbol precedes the map unit name in the map unit descriptions.
Each description includes general facts about the unit and gives important soil
properties and qualities.
Soils that have profiles that are almost alike make up a soil series. Except for
differences in texture of the surface layer, all the soils of a series have major
horizons that are similar in composition, thickness, and arrangement.
Soils of one series can differ in texture of the surface layer, slope, stoniness,
salinity, degree of erosion, and other characteristics that affect their use. On the
basis of such differences, a soil series is divided into soil phases. Most of the areas
shown on the detailed soil maps are phases of soil series. The name of a soil phase
commonly indicates a feature that affects use or management. For example, Alpha
silt loam, 0 to 2 percent slopes, is a phase of the Alpha series.
Some map units are made up of two or more major soils or miscellaneous areas.
These map units are complexes, associations, or undifferentiated groups.
A complex consists of two or more soils or miscellaneous areas in such an intricate
pattern or in such small areas that they cannot be shown separately on the maps.
The pattern and proportion of the soils or miscellaneous areas are somewhat similar
in all areas. Alpha-Beta complex, 0 to 6 percent slopes, is an example.
An association is made up of two or more geographically associated soils or
miscellaneous areas that are shown as one unit on the maps. Because of present
or anticipated uses of the map units in the survey area, it was not considered
practical or necessary to map the soils or miscellaneous areas separately. The
pattern and relative proportion of the soils or miscellaneous areas are somewhat
similar. Alpha-Beta association, 0 to 2 percent slopes, is an example.
An undifferentiated group is made up of two or more soils or miscellaneous areas
that could be mapped individually but are mapped as one unit because similar
interpretations can be made for use and management. The pattern and proportion
of the soils or miscellaneous areas in a mapped area are not uniform. An area can
be made up of only one of the major soils or miscellaneous areas, or it can be made
up of all of them. Alpha and Beta soils, 0 to 2 percent slopes, is an example.
Some surveys include miscellaneous areas. Such areas have little or no soil
material and support little or no vegetation. Rock outcrop is an example.
Custom Soil Resource Report
12
Saratoga County, New York
DeA—Deerfield loamy fine sand, 0 to 3 percent slopes
Map Unit Setting
National map unit symbol: 2xfg8
Elevation: 0 to 1,100 feet
Mean annual precipitation: 36 to 71 inches
Mean annual air temperature: 39 to 55 degrees F
Frost-free period: 145 to 240 days
Farmland classification: Farmland of statewide importance
Map Unit Composition
Deerfield and similar soils:85 percent
Minor components:15 percent
Estimates are based on observations, descriptions, and transects of the mapunit.
Description of Deerfield
Setting
Landform:Outwash terraces, outwash deltas, outwash plains, kame terraces
Landform position (three-dimensional):Tread
Down-slope shape:Concave, convex, linear
Across-slope shape:Convex, linear, concave
Parent material:Sandy outwash derived from granite, gneiss, and/or quartzite
Typical profile
Ap - 0 to 9 inches: loamy fine sand
Bw - 9 to 25 inches: loamy fine sand
BC - 25 to 33 inches: fine sand
Cg - 33 to 60 inches: sand
Properties and qualities
Slope:0 to 3 percent
Depth to restrictive feature:More than 80 inches
Drainage class:Moderately well drained
Runoff class: Negligible
Capacity of the most limiting layer to transmit water (Ksat):Moderately high to very
high (1.42 to 99.90 in/hr)
Depth to water table:About 15 to 37 inches
Frequency of flooding:None
Frequency of ponding:None
Maximum salinity:Nonsaline (0.0 to 1.9 mmhos/cm)
Sodium adsorption ratio, maximum:11.0
Available water supply, 0 to 60 inches: Moderate (about 6.5 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 2w
Hydrologic Soil Group: A
Ecological site: F144AY027MA - Moist Sandy Outwash
Hydric soil rating: No
Custom Soil Resource Report
13
Minor Components
Windsor
Percent of map unit:7 percent
Landform:Outwash terraces, kame terraces, outwash deltas, outwash plains
Landform position (three-dimensional):Tread
Down-slope shape:Concave, convex, linear
Across-slope shape:Convex, linear, concave
Hydric soil rating: No
Wareham
Percent of map unit:5 percent
Landform:Drainageways, depressions
Down-slope shape:Concave
Across-slope shape:Concave
Hydric soil rating: Yes
Sudbury
Percent of map unit:2 percent
Landform:Outwash plains, kame terraces, outwash deltas, outwash terraces
Landform position (three-dimensional):Tread
Down-slope shape:Concave, convex, linear
Across-slope shape:Convex, linear, concave
Hydric soil rating: No
Ninigret
Percent of map unit:1 percent
Landform:Kame terraces, outwash plains, outwash terraces
Landform position (three-dimensional):Tread
Down-slope shape:Convex, linear
Across-slope shape:Convex, concave
Hydric soil rating: No
DeB—Deerfield loamy fine sand, 3 to 8 percent slopes
Map Unit Setting
National map unit symbol: 2xfg9
Elevation: 0 to 1,190 feet
Mean annual precipitation: 36 to 71 inches
Mean annual air temperature: 39 to 55 degrees F
Frost-free period: 145 to 240 days
Farmland classification: Farmland of statewide importance
Map Unit Composition
Deerfield and similar soils:85 percent
Minor components:15 percent
Estimates are based on observations, descriptions, and transects of the mapunit.
Custom Soil Resource Report
14
Description of Deerfield
Setting
Landform:Outwash deltas, outwash terraces, outwash plains, kame terraces
Landform position (three-dimensional):Tread
Down-slope shape:Concave, convex, linear
Across-slope shape:Convex, linear, concave
Parent material:Sandy outwash derived from granite, gneiss, and/or quartzite
Typical profile
Ap - 0 to 9 inches: loamy fine sand
Bw - 9 to 25 inches: loamy fine sand
BC - 25 to 33 inches: fine sand
Cg - 33 to 60 inches: sand
Properties and qualities
Slope:3 to 8 percent
Depth to restrictive feature:More than 80 inches
Drainage class:Moderately well drained
Runoff class: Very low
Capacity of the most limiting layer to transmit water (Ksat):Moderately high to very
high (1.42 to 99.90 in/hr)
Depth to water table:About 15 to 37 inches
Frequency of flooding:None
Frequency of ponding:None
Maximum salinity:Nonsaline (0.0 to 1.9 mmhos/cm)
Sodium adsorption ratio, maximum:11.0
Available water supply, 0 to 60 inches: Moderate (about 6.5 inches)
Interpretive groups
Land capability classification (irrigated): None specified
Land capability classification (nonirrigated): 2w
Hydrologic Soil Group: A
Ecological site: F144AY027MA - Moist Sandy Outwash
Hydric soil rating: No
Minor Components
Windsor
Percent of map unit:7 percent
Landform:Outwash terraces, outwash plains, kame terraces, outwash deltas
Landform position (three-dimensional):Tread
Down-slope shape:Concave, convex, linear
Across-slope shape:Convex, linear, concave
Hydric soil rating: No
Wareham
Percent of map unit:5 percent
Landform:Drainageways, depressions
Down-slope shape:Concave
Across-slope shape:Concave
Hydric soil rating: Yes
Sudbury
Percent of map unit:2 percent
Landform:Kame terraces, outwash deltas, outwash terraces, outwash plains
Landform position (three-dimensional):Tread
Custom Soil Resource Report
15
Down-slope shape:Concave, convex, linear
Across-slope shape:Convex, linear, concave
Hydric soil rating: No
Ninigret
Percent of map unit:1 percent
Landform:Outwash plains, outwash terraces, kame terraces
Landform position (three-dimensional):Tread
Down-slope shape:Convex, linear
Across-slope shape:Convex, concave
Hydric soil rating: No
Custom Soil Resource Report
16
References
American Association of State Highway and Transportation Officials (AASHTO).
2004. Standard specifications for transportation materials and methods of sampling
and testing. 24th edition.
American Society for Testing and Materials (ASTM). 2005. Standard classification of
soils for engineering purposes. ASTM Standard D2487-00.
Cowardin, L.M., V. Carter, F.C. Golet, and E.T. LaRoe. 1979. Classification of
wetlands and deep-water habitats of the United States. U.S. Fish and Wildlife
Service FWS/OBS-79/31.
Federal Register. July 13, 1994. Changes in hydric soils of the United States.
Federal Register. September 18, 2002. Hydric soils of the United States.
Hurt, G.W., and L.M. Vasilas, editors. Version 6.0, 2006. Field indicators of hydric
soils in the United States.
National Research Council. 1995. Wetlands: Characteristics and boundaries.
Soil Survey Division Staff. 1993. Soil survey manual. Soil Conservation Service.
U.S. Department of Agriculture Handbook 18. http://www.nrcs.usda.gov/wps/portal/
nrcs/detail/national/soils/?cid=nrcs142p2_054262
Soil Survey Staff. 1999. Soil taxonomy: A basic system of soil classification for
making and interpreting soil surveys. 2nd edition. Natural Resources Conservation
Service, U.S. Department of Agriculture Handbook 436. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053577
Soil Survey Staff. 2010. Keys to soil taxonomy. 11th edition. U.S. Department of
Agriculture, Natural Resources Conservation Service. http://
www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?cid=nrcs142p2_053580
Tiner, R.W., Jr. 1985. Wetlands of Delaware. U.S. Fish and Wildlife Service and
Delaware Department of Natural Resources and Environmental Control, Wetlands
Section.
United States Army Corps of Engineers, Environmental Laboratory. 1987. Corps of
Engineers wetlands delineation manual. Waterways Experiment Station Technical
Report Y-87-1.
United States Department of Agriculture, Natural Resources Conservation Service.
National forestry manual. http://www.nrcs.usda.gov/wps/portal/nrcs/detail/soils/
home/?cid=nrcs142p2_053374
United States Department of Agriculture, Natural Resources Conservation Service.
National range and pasture handbook. http://www.nrcs.usda.gov/wps/portal/nrcs/
detail/national/landuse/rangepasture/?cid=stelprdb1043084
17
United States Department of Agriculture, Natural Resources Conservation Service.
National soil survey handbook, title 430-VI. http://www.nrcs.usda.gov/wps/portal/
nrcs/detail/soils/scientists/?cid=nrcs142p2_054242
United States Department of Agriculture, Natural Resources Conservation Service.
2006. Land resource regions and major land resource areas of the United States,
the Caribbean, and the Pacific Basin. U.S. Department of Agriculture Handbook
296. http://www.nrcs.usda.gov/wps/portal/nrcs/detail/national/soils/?
cid=nrcs142p2_053624
United States Department of Agriculture, Soil Conservation Service. 1961. Land
capability classification. U.S. Department of Agriculture Handbook 210. http://
www.nrcs.usda.gov/Internet/FSE_DOCUMENTS/nrcs142p2_052290.pdf
Custom Soil Resource Report
18
1 1
Project:
Location:
Surface Elevation:±||
Termination Depth: Date Completed:| |
Proposed Location:| --
At Completion:| -- --|
| --24 Hours: --|
No Type
0.0
5.0
10.0
15.0
16.0
20.0
25.0
WOH
/12"SUBSOIL
2 2 28
7
4
3 4 3
2 1 3 2
3 3 2 2
1 1 17 2
2 - 4
4 - 6
6 - 8
8 - 10 S-5
S-4
S-3
S-2
3 - -
5
3
15
20
18
2 -
-
As Above, Loose (SP-SM)
As Above, Very Loose to Loose (SP-SM)
As Above, Loose (SP-SM)
As Above (SP-SM)-10 - 12 S-6 3 16 6
20 2415 - 17 S-7
10 - 4
6 - 8 -
Proposed Brewery/Restaurant WAI Project No.:GM2321159.Y00
RECORD OF Boring No.: B-1
SUBSURFACE EXPLORATION Page of
Elevation
20.7 feet bgs 11/8/2023
(feet bgs) (ft NAVD88) (feet bgs) (ft NAVD88)
3376 South Broadway, Saratoga Springs, Saratoga County, New York Client:WL Enterprises Asquisitions, LLC
NS feet Above NAVD88 Date Started:11/8/2023 Water Depth Elevation Cave-In Depth
--Drill / Test Method:HSA / SPT (Autohammer)Contractor:CC --
Building Logged By:OR During:6.0
At Completion:
-- --
SAMPLE INFORMATION DEPTH STRATA DESCRIPTION OF MATERIALS REMARKSDepth
(feet)Blows Per 6"
Rec.
(in.)N (feet)(Classification)
Equipment:Geoprobe 7822DT 24 Hours:
TS 6" Topsoil
18" Subsoil, Roots
Brown, Very Loose, Poorly Graded Sand with Silt (SP-SM)
TILL
As Above, Very Dense
Boring B-1 Terminated at a Depth of 20.7 Feet Below Ground Surface.
0 - 2 S-1
3 1
- -
- - -
- - -
- - -
16 -
40/
5"
As Above, Medium Dense (SP-SM)
Brown, Dense, Silty Sand with Gravel (SM)
GLACIAL
LACUSTRINE
DEPOSIT
20 - 20.7 S-8 51 - 40/2" 7 -
NOTES: bgs = below ground surface, msl = mean sea level, NA = Not Applicable, NE = Not Encountered, NS = Not Surveyed, P = Perched RECORD OF SUBSURFACE EXPLORATION
WL Restaurant Brewery Saratoga Springs NY GM2321159.Y00 Boring Logs 10-8-23.xlsx 11/22/2023
1 1
Project:
Location:
Surface Elevation:±||
Termination Depth: Date Completed:| |
Proposed Location:| --
At Completion:| -- --|
| --24 Hours: --|
No Type
0.0
5.0
10.0
15.0
20.0
25.0
LACUSTRINE
As Above (SP-SM)17 5
1/12"
1 1
DEPOSIT
As Above, Medium Dense (SP-SM)
Boring B-2 Terminated at a Depth of 22 Feet Below Ground Surface.
15 - 17 S-5 1 1 16 2 As Above (SP-SM)
1 22 18 - 10 S-4 1
45 - 7 S-3 3
As Above, Very Loose (SP-SM)
Brown, Loose, Poorly Graded Sand with Silt (SP-SM)
3 2
SUBSOIL 18" Subsoil, Roots
2 - 4 S-2 3 3 4 5 13 7
0 - 2 S-1 11 10 19 192 8
TS 12" Topsoil
SAMPLE INFORMATION DEPTH STRATA DESCRIPTION OF MATERIALS REMARKSDepth
(feet)Blows Per 6"
Rec.
(in.)N (feet)(Classification)
--Equipment:Geoprobe 7822DT 24 Hours: --
Drill / Test Method:HSA / SPT (Autohammer)Contractor:CC --At Completion: --
Building Logged By:OR During:6.0
Elevation
22.0 feet bgs 11/8/2023
(feet bgs) (ft NAVD88) (feet bgs) (ft NAVD88)
3376 South Broadway, Saratoga Springs, Saratoga County, New York Client:WL Enterprises Asquisitions, LLC
NS feet Above NAVD88 Date Started:11/8/2023 Water Depth Elevation Cave-In Depth
Proposed Brewery/Restaurant WAI Project No.:GM2321159.Y00
RECORD OF Boring No.: B-2
SUBSURFACE EXPLORATION Page of
20 - 22 S-6 2 3 8 9 12 11
NOTES: bgs = below ground surface, msl = mean sea level, NA = Not Applicable, NE = Not Encountered, NS = Not Surveyed, P = Perched RECORD OF SUBSURFACE EXPLORATION
WL Restaurant Brewery Saratoga Springs NY GM2321159.Y00 Boring Logs 10-8-23.xlsx 11/22/2023
1 1
Project:
Location:
Surface Elevation:±||
Termination Depth: Date Completed:| |
Proposed Location:| --
At Completion:| -- --|
| --24 Hours: --|
No Type
0.0
5.0
10.0
15.0
20.0
25.0
2 2
As Above (SP-SM)
Boring B-3 Terminated at a Depth of 22 Feet Below Ground Surface.
As Above, Medium Dense (SP-SM)15 - 17 S-5 4 14
LACUSTRINE
8 - 10 S-4 2 2 24 4 As Above, Very Loose to Loose (SP-SM)
3 As Above (SP-SM)5 - 7 S-3 2 2 1 2 16
2 - 4 S-2 2 2 1
Brown, Very Loose, Poorly Graded Sand with Silt (SP-SM)
0 - 2 S-1 2 2
SUBSOIL 21" Subsoil, Roots
3 2 24 5
TS 9" Topsoil
2 17 3
SAMPLE INFORMATION DEPTH STRATA DESCRIPTION OF MATERIALS REMARKSDepth
(feet)Blows Per 6"
Rec.
(in.)N (feet)(Classification)
--Equipment:Geoprobe 7822DT 24 Hours: --
Drill / Test Method:HSA / SPT (Autohammer)Contractor:CC --At Completion: --
Building Logged By:OR During:6.0
Elevation
22.0 feet bgs 11/8/2023
(feet bgs) (ft NAVD88) (feet bgs) (ft NAVD88)
3376 South Broadway, Saratoga Springs, Saratoga County, New York Client:WL Enterprises Asquisitions, LLC
NS feet Above NAVD88 Date Started:11/8/2023 Water Depth Elevation Cave-In Depth
Proposed Brewery/Restaurant WAI Project No.:GM2321159.Y00
RECORD OF Boring No.: B-3
SUBSURFACE EXPLORATION Page of
DEPOSIT
20 - 22 S-6 7 8 16 21 15 24
8 2 16 22
NOTES: bgs = below ground surface, msl = mean sea level, NA = Not Applicable, NE = Not Encountered, NS = Not Surveyed, P = Perched RECORD OF SUBSURFACE EXPLORATION
WL Restaurant Brewery Saratoga Springs NY GM2321159.Y00 Boring Logs 10-8-23.xlsx 11/22/2023
1 1
Project:
Location:
Surface Elevation:±||
Termination Depth: Date Completed:| |
Proposed Location:| --
At Completion:| -- --|
| --24 Hours: --|
No Type
0.0
5.0
10.0
15.0
20.0
21.0
25.0
SUBSOIL 15" Subsoil, Roots
1/12"
TILL
Boring B-4 Terminated at a Depth of 22 Feet Below Ground Surface.
20 - 22 S-6 7 9 29 44 12 38
As Above (SP-SM)
GLACIAL Brown, Very Dense, Silty Sand with Gravel (SM)
16 1
15 - 17 S-5 6 11 8 7 18 19 As Above, Medium Dense (SP-SM)
10 - 12 S-5 1 1
3 As Above, Very Loose (SP-SM)
DEPOSIT
LACUSTRINE As Above (SP-SM)
8 - 10 S-4 3 1 2 1 14
6 As Above (SP-SM)5 - 7 S-3 3 3 3 3 16
2 10 52 - 4 S-2 2 3 2
Brown, Loose, Poorly Graded Sand with Silt (SP-SM)
0 - 2 S-1 1 2 2 2 15 4
TS 9" Topsoil
SAMPLE INFORMATION DEPTH STRATA DESCRIPTION OF MATERIALS REMARKSDepth
(feet)Blows Per 6"
Rec.
(in.)N (feet)(Classification)
--Equipment:Geoprobe 7822DT 24 Hours: --
Drill / Test Method:HSA / SPT (Autohammer)Contractor:CC --At Completion: --
Building Logged By:OR During:5.5
Elevation
22.0 feet bgs 11/8/2023
(feet bgs) (ft NAVD88) (feet bgs) (ft NAVD88)
3376 South Broadway, Saratoga Springs, Saratoga County, New York Client:WL Enterprises Asquisitions, LLC
NS feet Above NAVD88 Date Started:11/8/2023 Water Depth Elevation Cave-In Depth
Proposed Brewery/Restaurant WAI Project No.:GM2321159.Y00
RECORD OF Boring No.: B-4
SUBSURFACE EXPLORATION Page of
NOTES: bgs = below ground surface, msl = mean sea level, NA = Not Applicable, NE = Not Encountered, NS = Not Surveyed, P = Perched RECORD OF SUBSURFACE EXPLORATION
WL Restaurant Brewery Saratoga Springs NY GM2321159.Y00 Boring Logs 10-8-23.xlsx 11/22/2023
1 1
Project:
Location:
Surface Elevation:±||
Termination Depth: Date Completed:| |
Proposed Location:| --
At Completion:| -- --|
| --24 Hours: --|
No Type
0.0
5.0
10.0
15.0
15 - 15.7 S-5 16 - 0 -
20.0
25.0
Boring B-5 Terminated at a Depth of 15.7 Feet Below Ground Surface.
No Recovery
8 - 10 S-4 4 1 1 1 14 2 As Above (SP-SM)
As Above (SP-SM)5 - 7 S-3 1 1 18 11/12"
1 18 22 - 4 S-2 2 1 1 Brown, Very Loose, Poorly Graded Sand with Silt (SP-SM)
0 - 2 S-1 2 2
SUBSOIL 12" Subsoil, Roots
3 2 20 5
TS 9" Topsoil
SAMPLE INFORMATION DEPTH STRATA DESCRIPTION OF MATERIALS REMARKSDepth
(feet)Blows Per 6"
Rec.
(in.)N (feet)(Classification)
--Equipment:Geoprobe 7822DT 24 Hours: --
RECORD OF Boring No.: B-5
SUBSURFACE EXPLORATION Page of
Elevation
15.7 feet bgs 11/8/2023
(feet bgs) (ft NAVD88) (feet bgs) (ft NAVD88)
3376 South Broadway, Saratoga Springs, Saratoga County, New York Client:WL Enterprises Asquisitions, LLC
NS feet Above NAVD88 Date Started:11/8/2023 Water Depth Elevation
40/2"
LACUSTRINE
DEPOSIT
Proposed Brewery/Restaurant WAI Project No.:GM2321159.Y00
Cave-In Depth
Drill / Test Method:HSA / SPT (Autohammer)Contractor:CC --At Completion: --
Building Logged By:OR During:5.0
NOTES: bgs = below ground surface, msl = mean sea level, NA = Not Applicable, NE = Not Encountered, NS = Not Surveyed, P = Perched RECORD OF SUBSURFACE EXPLORATION
WL Restaurant Brewery Saratoga Springs NY GM2321159.Y00 Boring Logs 10-8-23.xlsx 11/22/2023
G. CONSTRUCTION DRAWINGS