HomeMy WebLinkAbout20230267 78 Church Site Plan Cost Estimate 2023 10 18Cost Estimate for Letter of Credit Planning Board No.: 23.0267 Project: 78 Church Street Redevelopment Location: 78 Church Street Saratoga Springs, NY Date: 10/13/2023 Firm Name & Preparer: The LA Group, Cameron Alber (Job # 2022062) On Site (All infrastructure & amenities on private property) Item # Item/Remarks Quantity Unit Unit Cost Subtotal % Complete Reduced $ Site Preparation and Grading 1 Erosion Control (including silt fence & construction access)1 LS $3,000.00 $3,000.00 0% $0.00 2 Demolition 1 LS $25,000.00 $25,000.00 0% $0.00 Hardscape 3 Stamped Concrete Pavement 400 SF $8.00 $3,200.00 0% $0.00 4 Concrete Pavement 630 SF $5.50 $3,465.00 0% $0.00 5 Asphalt Pavement 4,030 SF $5.25 $21,157.50 0% $0.00 Site Amenities 6 Landscaping 1 LS $8,000.00 $8,000.00 0% $0.00 7 Bike Rack 1 EA $500.00 $500.00 0% $0.00 8 Site Lights 1 EA $2,500.00 $2,500.00 0% $0.00 9 Fence 20 LF $60.00 $1,200.00 0% $0.00 Site Utilities 10 8" HDPE 5 LF $40.00 $200.00 0% $0.00 11 6" DIP Waterline 157 LF $90.00 $14,130.00 0% $0.00 Total onsite Work $82,352.50 $0.00 Total onsite X.25 $20,588.13 $0.00 Off Site (All infrastructure & amenities to be dedicated to the City) Item # Item/Remarks Quantity Unit Subtotal % Complete Reduced $ Misc. Utilities 12 6" PVC Sanitary line 25 LF $55.00 $1,375.00 0% $0.00 13 8" HDPE 15 LF $40.00 $600.00 0% $0.00 14 6" DIP Waterline 26 LF $90.00 $2,340.00 0% $0.00 15 Sanitary Connection 1 LS $1,500.00 $1,500.00 0% $0.00 16 6" Water Main Connection/Valve 1 EA $4,000.00 $4,000.00 0% $0.00 17 Water Fittings & Thrust Block 1 LS $1,200.00 $1,200.00 0% $0.00 Hardscape 18 Concrete Sidewalk 350 SF $5.50 $1,925.00 0% $0.00 19 Concrete Curb 62 LF $40.00 $2,480.00 0% $0.00 Amenities 20 Topsoil and Seed 1 LS $600.00 $600.00 0% $0.00 21 Trees 2 EA $700.00 $1,400.00 0% $0.00 22 Decorative Street Light 1 EA $3,500.00 $3,500.00 0% $0.00 23 As Built Drawings 1 LS $2,000.00 $2,000.00 0% $0.00 Cost Estimate for LOC Total offsite Work $22,920.00 $0.00 Total On-Site Work X25% $20,588.13 Total Off-Site work $22,920.00 Total = $43,508.13 * New LOC Reduced Amount = $44,000.00 LOC Amount = $44,000.00 City LOC Approval / Date City LOC Reduction Approval /Date * LOC cannot be reduced to less than 25% of the original LOC amount. Maximum Reduction 75% = $11,000.00 (25% LOC Amount) Cost Estimate for LOC