HomeMy WebLinkAbout23-11MV and 23-A-04MV (Saratoga Springs, Munter Land Holdings) (1)
50 WEST HIGH STREET (518) 884-4705 PHONE
BALLSTON SPA, NY 12020 (518) 884-4780 FAX
SARATOGA COUNTY PLANNING BOARD
TOM L. LEWIS JASON KEMPER
CHAIRMAN DIRECTOR
March 10, 2023
Susan Barden, Principal Planner
City of Saratoga Springs City Hall
474 Broadway
Saratoga Springs, NY 12866
Sent via email to: susan.barden@saratoga-springs.org
Re: SCPB Referral Review #23-11 and 23-A-04 - Site Plan and Subdivision Review
- Munter Land Holdings, LLC
Proposed 2-lot subdivision of an existing vacant commercial parcel of 37.6 acres
located at the west end of Duplainville Road in the Grande Industrial Park.
Also proposed is construction of a 45,480-s.f. commercial warehouse with office space
and a 25,000 s.f. cold storage accessory building on a vacant 22 acre portion of that
37.6-acre parcel.
Location: Duplainville Rd. (CR# 46)
177.-1-67
IND-G (General Industrial)
Received from the City of Saratoga Springs Planning Board on January 26, 2023.
Reviewed by the Saratoga County Planning Board on February 16, 2023.
Decision: No Significant Countywide/Intercommunity Impact
Comments:
The referrals submitted reflect the intent to subdivide 22 acres from roughly 38 acres
and construct two buildings on that new lot. The development of the parcel involves
building a 45,500-s.f. warehouse with corporate offices and 25,000 sq. ft. cold storage
building of one story (less than 40 ft. in height) with 6 large grade-level OH doors and
two traditional loading dock bays along the south wall.
Municipal sanitary and water are available at the end of CR# 46 (Duplainville). The
site development also includes on-site stormwater/drainage collection, and a street
extension requires permitting from Saratoga County DPW.
The site is relatively flat with no slopes, no wetlands, nor watercourses, and is not
located in a floodplain. Select vegetation removal is indicated with necessary grading
associated with site and building preparation. A SWPPP is required as there is greater
than 1 acre of disturbance due to development (as per DEC SPDES regs under the
GP). Development plans indicate sheet-flow runoff and closed drainage structures
leading to infiltration practices on site. The site will have 31% green space remaining
following full development (30% req’d.)
- 2 -
The site will be accessed by a single-access curb cut at the terminus of CR# 46. A
traffic assessment plan was completed by Creighton Manning Engineering in
December, 2022 and shows there to be no adverse impact to the road system and
traffic patterns by the development. Based on the current site plan, there will be 45
parking spaces for the buildings, with 40 required.
It is recommended that a site lighting plan (in accord with Pl Brd practice) as well as
plans for landscaping/buffering be reviewed to determine if there will be any adverse
impacts to adjacent properties that cannot be mitigate by the proposed development
plans. For example, the city planning board should determine if there will be any
noise created by the proposed use that is not similar to those of the surrounding
industrial uses, is there to be visual screening (remaining or added) by mature vegetation on
southern and northern, and that site lighting will be by poles of a 20 ft. maximum height and that
LED lights are dark-sky-compliant with cut-off fixtures providing direct lighting fading to no
spillover at the site perimeter. We recognize that these noted recommendations are nothing
beyond or above the norm of a standard review conducted by the city’s professional staff and
planning board members.
Please contact the Saratoga County Planning Board if you have any questions regarding
this matter.
Sincerely,
____________________________________
Michael Valentine, Sr. Planner
Authorized Agent for Saratoga County
DISCLAIMER: Recommendations made by the Saratoga County Planning Board on referrals and
subdivisions are based upon the receipt and review of a “full statement of such proposed action” provided
directly to SCPB by the municipal referring agency as stated under General Municipal Law section 239. A
determination of action is rendered by the SCPB based upon the completeness and accuracy of information
presented by its staff. The SCPB cannot be accountable for a decision rendered through incomplete or
inaccurate information received as part of the complete statement.