HomeMy WebLinkAbout20230017 Airosmith Garage Construction Site Plan OtherCost Estimate for Letter of Credit PB # 18.xxx Project No: 2017114 Project: 318 West Avenue / The Offices of Airosmith Development Location: 318 West Avenue Saratoga Springs, New York Date: 3/10/2023 ON-SITE WORK Item Quantity Unit Unit Cost Subtotal Site Preparation and Grading Erosion Control (including silt fence & access)1 LS $1,000.00 $1,000.00 Site Preparation 1 LS $1,200.00 $1,200.00 Hardscape Asphalt Pavement 1,200 SF $3.00 $3,600.00 Porous Asphalt Pavement 1,590 SF $4.50 $7,155.00 Site Amenities Striping 1 LS $400.00 $400.00 On-Site Total $13,355.00 On-Site Total X .25 $3,338.75 OFF-SITE WORK As Built Drawings 1 LS $800.00 $800.00 Off-Site Total $800.00 Total Site Work $14,155.00 Letter of Credit Amounts Total off-site work $800.00 Total on-site work x .25 $3,338.75 Total $4,138.75 L.O.C. amount $4,100.00