HomeMy WebLinkAbout20230008 Duplainville Site Plan Narrative
Verity Engineering, D.P.C.
P.O. Box 474
Troy, New York 12181
518.389.7200 | verityeng.com
1
EngineeringVerity
Project Narrative
Proposed Flex Warehouse Facility
City of Saratoga Springs, Saratoga County
December 2022
Site Address: 00 Duplainville Road
Saratoga Springs, NY 12866
Tax Map 177.-1-67
Applicant: Munter Land Holdings, LLC
c/o John Munter
881 Murray Road
Middle Grove, NY 12850
Owner: Munter Land Holdings, LLC
c/o John Munter
881 Murray Road
Middle Grove, NY 12850
Design Engineer: Verity Engineering, D.P.C.
P.O. Box 474
Troy, NY 12181
Surveyor: Gilbert VanGuilder Land Surveyor, PLLC
988 Route 146
Clifton Park, NY 12065
Zoning: IND-Gā Industrial General
Proposed use: Warehouse Expansion
Project Overview
The applicant is proposing a two (2) lot subdivision of the subject parcel and proposing to
construct a ±45,480 square feet (sq. ft.) single-story principal building incorporating flex
commercial warehouse with corporate office and a single-story ±25,000 sq. ft. cold-storage
accessory building; ±70, 480 sq. ft of proposed structures together with a proposed large
outdoor laydown area on a ±22-acre parcel, Lot B. Remaining lands of Munter Land
Holdings, LLC, Lot A ā ±14 acres, will remain in bulk deed as shown in the accompanying
subdivision map.
The development plan consists two (2) buildings, large laydown area, new access driveway,
new water and sewer services along with other private utility connections, westerly
extension of new T1 rail and T2 spur and stormwater management. The principal structure
will incorporate a ±6,240 sq. ft. corporate office section appended to a ±39,240 sq. ft.
commercial warehouse with six (6) large grade-level overhead doors and two (2) traditional
loading dock positions along the south building wall making way for the typical interior uses
in general manufacturing and storage of raw material and finished goods inventory. The
accessory warehouse is shown for the design and approval process; the applicant wishes to
phase the project and construct this building at a later juncture.
A single access curb cut is proposed extending off the west terminus of County Route 46,
a/k/a Duplainville Road which is situated in the northeast portion of the proposed Lot B. The
2 V
project will disturb greater than one (1) acre of land and will be subject to New York State
Department of Environmental Conservation (NYSDEC) stormwater regulations. Runoff from
stormwater will be conveyed via a combination of sheet flow and closed drainage structures
to various infiltration practices across the site. The project area does not contain critical
environ and species which are delineated and protected from development. The site is
absent steep slopes, wetlands, waterbodies, watercourses and not located within a flood
plain.
Description of Existing Site and Use
The subject parcel consists of undeveloped land and is located within and along the western
boundary of the Grande Industrial Park, a/k/a TMPL: 177.-1-62.212, (no logical postal
address), presently ±37.57 acres in size and wholly located within the General Industrial
(IND-G) zone. The parcel is bordered by other commercial and industrial uses to the north
and east. The parcel shares a common boundary with the Rural-Residential (RR) zone to the
west. A portion of the subject parcel contains Freedom Way, currently a private roadway.
Municipal water and sewer mains together with other private utilities exist along Freedom
Way and at the west terminus of Duplainville Road. The parcel does contain an easement to
the Niagara Mohawk Power Corporation near the southern property line.
Drainage and Surface Water
Surface runoff from the property currently does not leave the site.
Easements and Utilities
See above: Description of Existing Site and Use above. Description of Proposed Project
The applicant is proposing a two (2) lot subdivision of the subject parcel and proposing to
construct a ±45,480 square feet (sq. ft.) single-story principal building incorporating flex
commercial warehouse with corporate office and a single-story ±25,000 sq. ft. cold-storage
accessory building; ±70, 480 sq. ft of proposed structures together with a proposed large
outdoor laydown area on the proposed ±22 acre parcel.
The development plan consists two (2) buildings, large laydown area, new access driveway,
new water and sewer services along with other private utility connections, westerly
extension of new T1 rail and T2 spur and stormwater management. The principal structure
will incorporate a ±6,240 sq. ft. corporate office section appended to a ±39,240 sq. ft.
commercial warehouse with six (6) large grade-level overhead doors and two (2) traditional
loading dock positions along the south building wall making way for the typical interior uses
in general manufacturing and storage of raw material and finished goods inventory. The
accessory warehouse is shown for the design and approval process; the applicant wishes to
phase the project and construct this building at a later juncture.
A single access curb cut is proposed extending off the west terminus of County Route 46,
a/k/a Duplainville Road which is situated in the northeast portion of the proposed Lot B. The
project will disturb greater than one (1) acre of land and will be subject to a New York State
Department of Environmental Conservation (NYSDEC) Stormwater Discharge Elimination
System (SPDES) regulations for general construction under the current permit (GP-0-20-
001). Runoff from stormwater will be conveyed via a combination of sheet flow and closed
drainage structures to various infiltration practices across the site. The project area does
not contain critical environ and species which are delineated and protected from
development. The site is absent steep slopes, wetlands, waterbodies, watercourses and not
located within a flood plain. The scope of work for the proposed project involves select
3 V
removal of vegetation, grading, stormwater management including closed drainage network,
site preparation for construction of the building addition, utility service connections, paving
operations and other site appurtenances such as lighting and landscaping. The project will
require City of Saratoga Springs approval for site plan and a two-lot subdivision.
Anticipated Impacts on Services: Traffic
The proposed building addition will generate additional traffic in the AM and PM peak hours.
It is estimated that the proposed use will not have an adverse impact on traffic according to
a traffic assessment study attached herewith authored by Mark Nadolny of Creighton
Manning Engineering, LLP dated: December 7, 2022.
Water and Wastewater
New potable water and sewer connections are required to serve the proposed use. Municipal
water and sewer are available at the west terminus of CR46 to service the parcel. No
physical extension of municipal water or sewer infrastructure is proposed. The building is
proposed to be equipped with an automatic fire protection system; further engineering
details about fire flow demand and water system flow and pressure will be provided when
tenant-specific fit up requirements are known. Potable water demand is estimated as
follows:
Maximum Daily Flow: 35 Employees * 15 Gal/Employee/Day = 525 Gallons Per Day (GPD).
Daily sewer flows are expected to be the same.
Fire Protection
The site is served by Saratoga Springs Fire Department Station 2. Fire hydrants exist along
the west side of Freedom Way and at the north side of Duplainville Road approximately 548
ft. from the proposed building. A 500 ft hydrant radius is shown on the sheet C-101.
Municipal Solid Waste
The proposed project will generate additional solid waste that will require disposal to a
landfill and recycling center. Private trash collection contractors will be used to collect and
dispose of the solid waste. Dumpsters will be stored in an appropriately screened enclosure
on the south side of the building.
Impact on Adjacent Property Noise
Sound levels generated from closing of car doors, product handling and loading and rooftop
air-handling units are normal and customary to the surrounding industrial uses and will not
have adverse impacts to adjacent neighbors. Visual
The project will have no adverse visual impact. The proposed development will be screened
to the maximum extent with mature vegetation to remain along the southern and northern
portions of the parcel. See Lighting below for further details pertaining to light pollution.
Lighting
All light poles will be no taller than 20 ft. and all LED lights will be dark-sky compliant
utilizing sharp-cutoff fixtures which direct light only to targeted areas. A photometric plan
can be found on sheet C-191.
4 V
Drainage and Stormwater
Drainage patterns will not be altered from the predevelopment conditions. See: Drainage
and Surface Water above. Site disturbance is greater than one (1) acre and will be subject
to GP-0-20-001 regulations. Stormwater runoff will be conveyed via sheet flow and a closed
drainage to various infiltration practices. Please reference the sheet C-121 and the Storm
Water Pollution Prevention Plan (SWPPP) for further details. Air Quality
The project will have no adverse effect on air quality. Odor
The project will have no adverse effect on odors.
Impact to Critical Environ
NYSDEC mapping indicates the presence of rare plants or animals within the project area.
NYSDEC has indicated the proposed action will likely not result in the taking of threatened
or endangered species in a letter dated October 24, 2022 due to a lack of suitable habitat on
or near the project area.
Existing and Proposed Building Gross Floor Area
Approximate Total Gross Floor Area (GFA): 70,480 square feet (sq. ft.)
GFA Principal Building: ±45,480 sq. ft.
GFA Office: ±6,240 sq. ft.
GFA Warehouse: ±39,240 sq. ft.
GFA Accessory Building: ±25,000 sq. ft.
Building Height and Number of Floors
The new building will be one (1) story and have a split roof height with the warehouse peak
roof height of less than 40ft. Miscellaneous Site Information Parking, Parking Improvements and Site Distance
Section 6.2.6, Off-Street Parking Schedule, calls for one (1) space per two (2) employees plus
one (1) per company vehicle; forty-five (45) spaces are proposed inclusive of two (2) ADA
accessible spaces together with ADA van accessibility and five (5) company vehicles. Ample
sight distance exists easterly along CR 46 at the proposed access driveway.
Hours of Operation
Monday through Friday 24 hours per day.
Open Space Preservation/Green Space
The proposed green space is approximately 31.1%. Construction Sequence and Phasing
The project is intended to be built in a single phase.
5 V
Disposal of Chemicals
The operation will not involve the storage of regulated chemicals. The Fertilizers and
pesticides for lawn and landscape treatment will be applied by licensed contractor/personnel
and brought to the site at time of application.
Town Communication Impacts
No known communication devices or needs are proposed at this time. Variances/Waivers/Referrals
N/A