HomeMy WebLinkAbout20220236 131 Excelsior North Spring Run Site Plan Other (2)
December 9, 2022
Ms. Debbie LaBreche
City of Saratoga Springs
474 Broadway
Saratoga Springs, NY 12866
RE: North Spring Run – 131 Excelsior Avenue
City of Saratoga Springs, Saratoga County, New York
Dear Ms. LaBreche:
The following comments pertain to the site plan package for North Spring Run. A comment letter was received on May 12,
2022 from Barton & Loguidice. The responses below are related to that letter.
General Comments
Comment 1: The plan seems well designed and balanced. We suggest careful attention is paid to executing signage
location and landscaping away from ingress and egress pavement and Excelsior Avenue to avoid
impacting site distance.
Response 1: Comment noted.
Comment 2: Are there any demolition wastes requiring special environmental attention like transformers or other
sensitive materials? We suspect that brewery operation did not have many materials of concern if any.
Incorporate any requirements in plan notes involving certified personnel for removals if applicable. The
same notes that address this in the SWPPP could be repeated on the plans where contractors are more
likely to see.
Response 2: A pre-demolition regulated building material inspection was completed by LaBella that
determined small traces of asbestos-containing materials and lead-based paint are present
within the building. Proper abatement and removal of these materials will be reviewed and
regulated by the City Building Department and demolition permit. An additional note has been
added to Sheet L-1.0, Removals Note 6 stating that hazardous material shall be removed and
disposed of by a licensed hazardous waste carrier.
Comment 3: How many bicycle storage spaces are available inside the structures?
Response 3: The project proposed up to 56 bike storage spaces.
Comment 4: Was a green roof considered for part of the rooftop areas? The stormwater planters provide RRv for the
project but rooftop greenery and green infrastructure could appeal to much of the environmentally
minded clientele likely to dwell here.
Response 4: A green roof was considered but was determined to not be economically feasible for the project.
Comment 5: Given the urban setting we recommend another two EV stations for a total of six or at least the conduit
and service accommodations to provide more easily in the future and not require disturbed pavement.
Response 5: The project proposes four (4) EV parking spaces with corresponding stations. The new City
UDO, which this project isn’t required to conform to, requires at least 2% of required parking
spaces be EV installed. The current design exceeds UDO requirement of 3 parking spaces (153
x 2%). Based on the applicant other facilities they feel that (4) EV spaces would adequately
service their site.
SEAF
Comment 1: No comments.
Water and Sanitary Sewer
Comment 1: Confirm number of connections to the Excelsior Avenue 12-inch water main. The plans indicate one six-
inch service and did not seem to have a tap for the easterly building or a connecting pipe between the
buildings. Please clarify.
Response 1: Water will be distributed to the easterly building via the connected pedestrian bridge, and
therefore only one service is required.
Comment 2: We recommend a secondary means of thrust restraint on the 6-inch water main service with two 45
degree bends because that area may be disturbed by other future utility maintenance or subsurface
operations. Thrust blocks in such areas would benefit by either retainer glands or restrained joint pipe
and fittings in addition to the thrust blocks. Static pressure is pretty high at this location. A significant
leak near the building(s) is worth the added restraint.
Response 2: Detail 6 on Sheet L-7.3 has been modified to indicate minimum length of restrained pipe for
bends and tee’s. All bends are proposed to have thrust blocks and restrained fittings.
Comment 3: Coordinate fire protection system design with city building and fire services.
Response 3: Comment noted. The fire department was provided with the plans for their review.
Cost Estimate for Line of Credit
Comment 1: With quantity of striping we recommend a higher unit cost for crosswalks, parking areas and related.
Response 1: The unit cost for striping has been increased.
Comment 2: Confirm light pole costs incorporate large concrete piers. Unit cost plus the decorative fixtures seems
low.
Response 2: The unit cost for the decorative light fixtures and light poles have been increased based on
recent price increases and includes the piers.
Comment 3: The unit cost for the two dumpsters seems low as a concrete slab and enclosure is also included.
Response 3: This cost does not include the cost of the dumpsters or the concrete pad. Concrete pads are
included in the concrete sidewalk cost. Unit cost has been increased based on recent cost
increases.
Comment 4: The unit cost for sanitary sewer installed seems low as it includes imported backfill materials.
Response 4: The unit cost for the sanitary sewer has been increased accordingly.
Comment 5: The unit cost of the hydrodynamic separator seems low and should include installation, imported
materials.
Response 5: The unit cost for the hydrodynamic separator is based on manufacturer costs plus installation,
but has been increased based on recent cost increases.
Comment 6: Construction unit costs have been impacted by elevated inflation and some unit costs seem low by 15-
20% due to recent trends.
Response 6: Pricing for storm, sanitary, and water line have been increased due to inflation. Additionally, the
cost for concrete curb and yard drains have been increased.
SWPPP
Comment 1: The system for stormwater management includes stormwater planters, underground pipe detention and
a hydrodynamic separator, Discharge is to existing stormwater infrastructure and conveyances.
Response 1: Comment noted.
Comment 2: Confirm hydrodynamic separator unit selected can treat peak inflow rate of water quality storm and has
an internal bypass capacity to pass the 100 year peak inflow rate.
Response 2: The 100-year storm event requires a bypass flowrate of 6.77 cfs. The DVS-48C separator has a
maximum bypass flowrate of 9.0 cfs and therefore has the capacity to pass the 100 year storm
event.
Plans
Survey Sheet by Northeast
Comment 1: This plan seems to not include the area being developed and covers land west of the site.
Response 1: An updated survey has been included in the site plans.
L-1.0-Site Preparation, Erosion & sediment Control Plan
Comment 1: Show short term demolition and soil stockpiling for prompt removals and stabilization, respectively.
Consider wind erosion of piles with notes for covering or temporary seeding.
Response 1: A demo and soil stockpile has been added to the Site Preparation, Erosion & Sediment Control
Plan, sheet L-1.0. Note 11 under Erosion and Sediment Control Notes directs the contractor to
the SWPPP for temporary and permanent stabilization measures, which would include stockpile
areas. An additional note has been added to the Temporary Stockpile detail on Sheet L-7.0
regarding mulching, seeding, or use of matting on stockpiles.
L-2.0- Layout and Materials Plan
Comment 1: Consider adding two additional EV stations. See general notes.
Response 1: See previous response.
L-3.0-Grading and Drainage Plan
Comment 1: Show line of north finished floor elevation across building representing 272.50.
Response 1: This line has been added to sheet L-3.0 and called out as “FFE ELEVATION CHANGE”.
Comment 2: We recommend moving the discharge structure closer to CB-3 and pipe to CB-3 in lieu of the wye
connection to allow easier cleaning if ever necessary.
Response 2: The stormwater planter yard drain (YD-1) has been moved and the 6” outlet pipe has been
connected to CB-3.
Comment 3: The easterly slope could likely be graded to droughty sands. A deeper depth of topsoil and premium
tackifier with hydroseed and/or other stabilization means will help reduce erosion/rills and repairs during
emergent period of vegetation establishment. Existing and undisturbed vegetated areas that are sparse
may need fertilization to blend with new landscaping.
Response 3: Rolled erosion control matting has been added to the site plans to ensure stabilization of the
slope and is shown sheet L-1.0. Comment noted about existing undisturbed vegetated areas.
Per site visit current slopes appear stabile but will be reanalyzed during construction and
recommendations provided if additional measures are required to stabilize slopes.
L-4.0 Site Utilities Plan
Comment 1: How is easterly building served with water, see general comments.
Response 1: The water connecting to the easterly building will be routed through the pedestrian bridge.
Comment 2: See previous comments regarding truck traffic and pavement thickness.
Response 2: Proposed pavement thickness is based off Geotech recommendations for the site.
Comment 3: A detail for an asphalt curb is shown but could not find where applied on the plans.
Response 3: An asphalt curb detail is not included on the site plans. All curbing is to be cast-in-place
concrete.
L-7.1 –Site Details
Comment 1: We recommend addition of protective coating such as bitumastic or equivalent as a barrier between
aluminum posts in fence detail and concrete where embedded. Aluminum reacts in contact with
concrete.
Response 1: The dumpster enclosure detail has been updated to galvanized poles with PVC vinyl coating and
metal chain link fencing with vinyl privacy slats.
Sincerely,
Douglas B. Heller, PE
Principal/Civil Engineer
dheller@thelagroup.com
G:\Proj-2019\2019013_Excelsior_Brewery_Mixed_Use\2019013Admin\01Correspondence\2.7Review_Comments\22-05-13_Comment Response
Ltr.docx