HomeMy WebLinkAbout20288483 269 Broadway New Mixed-Use Public Comment ForthePlanningBoard
RE : Proposed 269 Broadway
January 3, 2022
In reading the two Reviews provided by CHA on the project, we notice there are still several outstanding
questions to be resolved from the CHA reviews and suggest another review is required.
In addition, several issues should be addressed based upon the geotechnical report.
1. The developers have presented a Sept 5, 2019, report by Terracon for planning approval.
However,that report was prepared for Roohan Realty and does not represent the building that is
being proposed.
The geotechnical report states: "As we understand it, the project entails construction of a new
five-story mixed use building with basement level parking and plan dimensions of about 65 x 240
feet. Preliminary plans envision the first floor at an elevation of approximately 307 feet (about
five feet above Broadway), with the basement level parking at about elevation 295 (orjust above
Hamilton Street)."
The building being proposed is six stories, not five. In addition,the proposed building has parking
down to an elevation of 275 or twenty feet below what was assumed in the geotechnical report.
This is a notable change to the proposed work required. The added depth greatly undermines
both Broadway and Hamilton Streets and their sidewalks and buried utilities, as well as the bank
building to the north.
2. The geotechnical report indicates the groundwater level is expected at an elevation of between
289 to 292. Thus, the lowest level of parking (Elevation 275) will be 14 to 17 feet below ground
water level. However,the SEQR application stated the building needs no dewatering.This should
require a reopening of the SEQR application to address the water issue.
3. The proposed building is being described as a zero-lot-line building. However, the geotechnical
report requires a drainage system on the below-grade exterior walls. It states:
"Subsurface Drainage for Below-Grade Walls
Retaining structures should be provided with a foundation level drain which may consist of a
nominal 4-inch diameter perforated PVC pipe embedded at the base of a minimum 12-inch wide
column of clean crushed stone(e.g., no. 1 and no. 2 size aggregate or ASTM Blend 57 stone).The stone
should be wrapped in a filter fabric(Mirafi 140N or equivalent)to inhibit siltation. Backfill soils behind
the crushed stone drainage layer should consist of Structural Fill. The drain line should be sloped to
provide positive gravity drainage to daylight, stormwater system, or to a sump pit and pump."
The drainage system recommendation requires a minimum setback of 1 foot from the property
line. In addition, there needs to be an allowance for construction access and future maintenance
of the drainage system.
4. Even without knowledge of the proposed deep parking levels, the geotechnical report
recommends pre-construction surveys and monitoring if piles are used. It states:
"Site Preparation
Site preparation should begin with clearing and stripping of asphalt, topsoil and surficial organic
matter from the building pad. A pre-construction survey of adjoining properties should be
completed to define pre-existing cracks or deflections within the adjacent structures if H pile
foundations are selected. In addition, vibration monitoring at the site limits and at nearby
structures should be performed to verify whether the pile driving contractor's means and
methods are acceptable or require modification."
If piles are used, the pre-construction survey and vibration monitoring should be made
mandatory. The geotechnical report should be amended, and similar pre-construction surveying
and monitoring be considered due to the deep excavations required.
5. The geotechnical report recommends "Geotechnical Observations and Testing" during
construction.
This was recommended even without knowledge of the proposed deep parking areas.The report
should be updated, and the recommended observations and testing be made a mandatory
condition.
Summary:
1. CHA should complete its review of outstanding issues and the items listed below.
2. The geotechnical report was written without knowled�e of the proposed building.
3. The SEQR report incorrectly stated no dewatering was required and should be revisited.
4. The geotechnical report should be updated to address the actual proposed building:
a. The actual proposed height.
b. The proposed deep parking levels and their impact on the groundwater level, the adjacent
building, Hamilton St. and Broadway, and the buried public utilities.
c. The proposed building drawings and floor elevations should be provided to the geotechnical
engineer to assist in the preparation of a revised report.